HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2174-2026
Submission Date : 18-02-2026 11:07:47 AM
Applicant Type : Company
Project Type: NEW




SOBHA LIMITED
PLOT NO. 136-P, 5TH FLOOR, RIDER HOUSE BUILDING, SECTOR 44 , GURUGRAM
1244855555
9205028885 (Number Shared by Promoter in Public)
haryana.rera@sobha.com
Http://www.sobha.com/
XXXX723E
L45201KA1995PLC018475
 
 


 
 


 
 


 
 







SOBHA CRESCENT PHASE - 1
SECTOR 63A, VILLAGE BEHRAMPUR, GURUGRAM MANESAR URBAN COMPLEX
WAZIRABAD ST
GURUGRAM
01244855555
9205028885 (Number Shared by Promoter in Public)
haryana.rera@sobha.com
SHILPA MALIK
01244855555
9205028885 (Number Shared by Promoter in Public)
haryana.rera@sobha.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
112309-02-202612IDBI BANK LIMITEDHRERA Gurugram







4.960 (Acre)
3.50
2.70
11.9968 (Acre)
57 of 2025 dated 17.04.2025
No
Address     IREO CAMPUS, SECTOR 59, NEAR BEHRAMPUR, GURGAON, 122101
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, WEST DELHI, NEW DELHI 110015
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, SOUTH DELHI, NEW DELHI, 110017
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, SOUTH DELHI, NEW DELHI, 110017
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, WEST DELHI, NEW DELHI 110015
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, WEST DELHI, NEW DELHI 110015
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, WEST DELHI, NEW DELHI 110015
Annexure-B- COLLABORATOR
BEFORE GRANT OF LICENSE
Yes
AS PER DEVELOPMENT AGREEMENT SUBMITTED.
No
Yes
Yes







215897.63 Lakhs
107217.82 Lakhs
40347.80 Lakhs
22096.00 Lakhs
46236.01 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 2013.105
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 6479.252
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 9198.053
13CONSTRUCTION OF CIRCULATION ROAD 2382
Total20072.41




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM1219.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE51.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM3188.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL677.00AS PER PROJECT REPORT
6STREET LIGHTING200.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS30.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0.00AS PER PROJECT REPORT
10SHOPPING AREA0.00AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM94.00AS PER PROJECT REPORT
12SCHOOL0.00AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0.00AS PER PROJECT REPORT
14ANY OTHER10468.00AS PER PROJECT REPORT
15PARKING522.00AS PER PROJECT REPORT
16STP326.00AS PER PROJECT REPORT
17UNDERGROUND WATER TANK389.00AS PER PROJECT REPORT
18RAIN WATER HARVESTING125.00AS PER PROJECT REPORT
19ELECTRIC SUB STATION283.00AS PER PROJECT REPORT
20FIRE AND HVAC AND AC FOR APARTMENTS4524.00AS PER PROJECT REPORT


NA (date)
NA (date)
01-10-2026
31-03-2033
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings157.36852
Apartment/Shops/Other Buildings141.171212
Apartment/Shops/Other Buildings118.011162
Apartment/Shops/Other Buildings138.8512
Apartment/Shops/Other Buildings123.3062
Apartment/Shops/Other Buildings100.2472





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments672.19
Shops0
Plots0

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments672.19672.19672.19672.19
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments673.811344.391344.391344.39
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1344.391344.391344.391344.39
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1344.392261.293269.993269.99
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3276.441925.601925.601925.60
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1925.601925.601925.601926.61
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System55.3455.3455.3455.34
Sewerage treatment & garbage disposal42.3142.3142.3142.31
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other475.25475.25475.25475.25
Parking23.7023.7023.7023.70
Rain water harvesting20.8320.8320.8320.83
STP54.3154.3154.3154.31
Underground water tank64.8164.8164.8164.81

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System55.3455.3455.3455.34
Sewerage treatment & garbage disposal42.3142.3142.3142.31
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other475.25475.25475.25475.25
STP54.3154.44
Underground water tank64.8164.96
Rain water harvesting20.8320.88
Parking23.7023.7023.7023.70

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System55.3455.3455.3455.34
Sewerage treatment & garbage disposal42.3142.3142.3142.31
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other475.25475.25475.25475.25
Parking23.7023.7023.7023.70

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System55.3455.3455.3455.34
Sewerage treatment & garbage disposal42.3142.3142.3142.31
Electricity Supply System00398.50398.50
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other475.25475.25475.25475.25
Parking23.7023.7023.7023.70
Fire and HVAC and AC for Apartments565.50565.50

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System55.3455.3455.3455.34
Sewerage treatment & garbage disposal0000
Electricity Supply System398.50398.50398.50398.50
Storm Water Drainage8.508.508.508.50
Parks and Playgrounds007.507.50
Clubhouse/community centres0000
Shopping area0000
Other475.25475.25475.25475.25
Electrical sub station47.1547.1547.1547.15
Fire and HVAC and AC for Apartments565.50565.50565.50565.50
Street Lighting33.3233.3233.3233.32
Parking23.7023.7023.7023.70

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System55.3456.8100
Sewerage treatment & garbage disposal0000
Electricity Supply System398.50398.5000
Storm Water Drainage8.508.5200
Parks and Playgrounds7.507.5000
Clubhouse/community centres0000
Shopping area0000
Other475.25487.8100
Fire and HVAC and AC for Apartments565.50565.50
Electrical sub station47.1547.26
Parking23.7024.3323.50
Street Lighting33.3233.40

ParticularsYear-2033
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Renewable energy system23.5023.50












No
No
IDBI BANK LTD., SHOP NO. 6-7, VIPUL SQUARE, SUSHANT LOK PHASE-1, B-BLOCK, GURUGRAM ? 122002, HARYANA
0171102000019673
IBKL0000171
110259013
171
Shilpa Malik, H. N0 1742b/3 Frist Floor Street no 7, Near Nokia Care On Old Delhi Road Rajiv Nagar Gurgaon
Yes











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LC VALREADY BEEN OBTAINED17-04-2025
II. DEMARCATION CUM ZONINGALREADY BEEN OBTAINED14-11-2025
III. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED30-05-2024
IV. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED06-11-2025
V. FOREST NOCALREADY BEEN OBTAINED11-08-2025








Yes


Yes









SOBHA ARANYA PHASE-1, SECTOR 80, GURUGRAM
14.81747
524
0
178
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
397591.39397591.3942202.03
Cost of the apartments119411.63119411.636171.19
Cost of the infrastructure1863.831863.830.00
Others costs276315.93276315.9336030.84


45068.87209 Lakhs
119426.27156 Lakhs
0.00 Lakhs
0.00 Lakhs
No
31-10-2030
31-10-2030




SOBHA ALTUS, SECTOR 106, GURUGRAM
5.5100
296
0
105
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
207352.61207352.6110778.44
Cost of the apartments52148.4952148.492808.26
Cost of the infrastructure882.35882.350
Others costs154321.77154321.777970.18


7535.86014 Lakhs
22560.82238 Lakhs
0.00 Lakhs
0.00 Lakhs
No
31-12-2031
31-12-2031




SOBHA CITY, PHASE-6, SECTOR 108, GURGAON
16.3995
396
0
385
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
95990.0195990.0164295.59
Cost of the apartments426574265717944
Cost of the infrastructure719719205
Others costs52614.0152614.0146146.59


112273.81213 Lakhs
39748.42638 Lakhs
0.00 Lakhs
0.00 Lakhs
No
31-12-2028
31-12-2028










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSESUPERIOR QUALITY VITRIFIED TILE/ CERAMIC NITRIFIED
2WALL FINISHING DETAILSPLASTIC EMULSION PAINT
3KITCHEN DETAILSSUPERIOR QUALITY CERAMIC TILE /PLASTIC EMULSION
4BATHROOM FITTINGSPNC/EQUIVALENT
5WOOD WORK ETCDOORS
6DOORS AND WINDOS FRAMESBOTH SIDE MASONITE SKIN DOORS AND ALUMINIUM/UPVC/GLASS WINDOWS
7GLASS WORKHARDEND GLASS
8ELECTRIC FITTINGSCLIPSAL-OPALE/EQUIVALENT
9CONDUCTING AND WIRING DETAILSHAVELLS, COBRA,SALZER, POLYCAB, LAPP/EQUIVALENT
10CUPBOARD DETAILSN/A
11WATER STORAGEN/A
12LIFT DETAILS7 LIFT PER FLOOR
13EXTERNAL GLAZINGSEXTERIOR PAINT
13.1WINDOWS/GLAZINGSHEAVY-DUTY ALUMINUM GLAZED LIDING WINDOWS
14DOORSBOTH SIDE MASONITE SKIN
14.1MAIN DOORSBOTH SIDE MASONITE SKIN
14.2INTERNAL DOORSBOTH SIDE MASONITE SKIN
15AIR CONDITIONINGN/A
16ELECTRICAL FITTINGSCLIPSAL-OPALE/EQUIVALENT
17CNG PIPE LINEN/A
18PROVISION OF WIFI AND BROADBAND FACILITYN/A
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR PAINT
20INTERNAL FINISHINGPLASTIC EMULSION
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORSUPERIOR QUALITY VITRIFIED TILE
1 . 2 WALLSPLASTIC EMULSION
1 . 3 CEILINGPLASTIC EMULSION
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORSUPERIOR QUALITY VITRIFIED TILE
2 . 2 WALLSPLASTIC EMULSION
2 . 3 CEILINGPLASTIC EMULSION
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORCERAMIC NITRIFIED
3 . 2 WALLSCERAMIC NITRIFIED
3 . 3 CEILINGPLASTIC EMULSION
3 . 4 COUNTERSWHITE COUNTERTOP BASIN
3 . 5 SANITARY WARE/CP FITTINGSFIITINGS
3 . 6 FITTING/FIXTURESFIITINGS
4 . BED ROOMS
4 . 1 FLOORSUPERIOR QUALITY VITRIFIED TILE
4 . 2 WALLSPLASTIC EMULSION
4 . 3 CEILINGPLASTIC EMULSION
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORSUPERIOR QUALITY CERAMIC TILE
5 . 2 WALLSSUPERIOR QUALITY CERAMIC TILE
5 . 3 CEILINGCALCIUM SILICATE
5 . 4 COUNTERSWHITE COUNTERTOP BASIN
5 . 5 SANITARY WARE/CP FITTINGSFITTINGS
5 . 6 FIXTURESFITTINGS
6 . KITCHEN
6 . 1 FLOORSUPERIOR QUALITY VITRIFIED TILE
6 . 2 WALLSSUPERIOR QUALITY CERAMIC TILE /PLASTIC EMULSION
6 . 3 CEILINGPLASTIC EMULSION
6 . 4 COUNTERSN/A
6 . 5 FIXTURESFIXTURES
6 . 6 KITCHEN APPLIANCESN/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORSUPERIOR QUALITY CERAMIC TILE
7 . 2 WALLS & CEILINGPLASTIC EMULSION
7 . 3 TOILETN/A
7 . 4 BALCONYAVAILABLE
8 . SIT-OUTS
8 . 1 FLOORN/A
8 . 2 WALLS & CEILINGN/A
8 . 3 RAILINGSN/A
8 . 4 FIXTURESN/A












Sr. No.Document DescriptionDate of Document UploadView Document
1 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 16-02-2026 View Document
2 DEMARCATION PLAN 10-02-2026 View Document
3 ZONING PLAN 10-02-2026 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 16-02-2026 View Document
5 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 16-02-2026 View Document
6 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 16-02-2026 View Document
7 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 16-02-2026 View Document