H & O HOUSE D-64, DEFENSE COLONY, NEW DELHI-110048
01124628583
9821396549 (Number Shared by Promoter in Public)
info@zaragroup.in
http://www.zaragroup.in
XXXX912C
U45201DL2004PTC125145
ZARA AAVAAS- 2
SECTOR-104, GURUGRAM
GURGAON
GURUGRAM
9958700716
9958700716 (Number Shared by Promoter in Public)
INFO@ZARAGROUP.IN
RAJEEV SRIVASTAVA
9958700716
9958700716 (Number Shared by Promoter in Public)
rajeev.srivastava@zaragroup.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
Address W/O SH. AJIT SINGH KATARIA 547/2B 9 NEAR JYOTI PARK GURGAON HARYANA 122001
Annexure-B- COLLABORATION AGREMENT, SALE DEED AND GENERAL POWER OF ATTORNEY (UPLOADED)
BEFORE GRANT OF LICENCE
Yes
LANDOWNER - 40%
DEVELOPER - 60%
No
Yes
Yes
3342.03 Lakhs
1394 Lakhs
1650 Lakhs
123.03 Lakhs
175 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1278.44
3
CONSTRUCTION OF ROADS
1315
4
PAVEMENTS
418.25
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
244.54
7
VEHICLE PARKINGS
567.59
8
ELECTRICITY SUB-STATION
112.13
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
42.19
13
COMMERCIAL
195.16
Total
4173.3
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
HUDA
Yes
ELECTRICITY
DAKSHIN HARYANA BIJLI VITRAN NIGAM
Yes
SEWAGE DISPOSAL
HUDA
Yes
STORM WATER DRAINAGE
HUDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
24.18
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
43.78
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
12.99
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
25.50
SUBMITTED TO HUDA
6
STREET LIGHTING
3.94
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
0.76
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
11.88
SUBMITTED TO HUDA
03-01-2019 (date)
NA (date)
15-02-2019
15-08-2022
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
59.954
132
4
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Yes
Yes
AXIS BANK LTD. LAJPAT NAGAR NEW DELHI
919020008120705
UTIB0000126
110211017
000126
1. VIPUL SUCHDEVA R/O C-12 DEFENCE COLONY NEW DELHI - 110024 OR 2. AJAY BHARTI R/O E-184 NEAR BHARTI EYE HOSPITAL GREATER KAILASH PART - 1 NEW DELHI - 110048
AS ATTACHED
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
No
No
No
No
No
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. DRINKING WATER
ALREADY BEEN OBTAINED
02-04-2018
II. APPROVED ZONING PLAN
ALREADY BEEN OBTAINED
10-11-2017
III. APPROVED BUILDING PLAN/ SITE PLAN
ALREADY BEEN OBTAINED
03-01-2019
IV. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
13-07-2018
V. HUDA CONSTRUCTION WATER NOC
ALREADY BEEN OBTAINED
02-04-2018
VI. ELECTRICAL LOAD AVAILABILITY
ALREADY BEEN OBTAINED
17-04-2018
VII. FOREST NOC
ALREADY BEEN OBTAINED
18-09-2014
VIII. CONSENT TO ESTABLISH
ALREADY BEEN OBTAINED
15-12-2018
IX. MINING NOC
ALREADY BEEN OBTAINED
18-12-2018
X. LICENCE
ALREADY BEEN OBTAINED
08-11-2017
XI. SERVICE PLAN & ESTIMATES
APPLIED FOR BUT YET TO RECEIVE
11-02-2019
XII. FIRE SCHEME
YET TO FILE FOR APPROVAL
NA
Yes
No
will be submitted after getting the RERA Registration Number
ZARA AAVAAS
5
818
0
812
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1220
0
7600
Cost of the apartments
8175
0
5700
Cost of the infrastructure
3025
0
1200
Others costs
1000
0
700
13600 Lakhs
5000 Lakhs
0 Lakhs
0 Lakhs
No
01-03-2019
01-05-2019
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILES IN ROOMS. CERAMICS TILE IN TOILETS
2
WALL FINISHING DETAILS
OIL BOUND DISTEMPER
3
KITCHEN DETAILS
CERAMIC TILES UPTO 2 FEET ABOVE COUNTER
4
BATHROOM FITTINGS
REPUTED BRAND CP FITTINGS
5
WOOD WORK ETC
NO
6
DOORS AND WINDOS FRAMES
ALUMINIUM / UPVC FOR EXTERNAL WINDOW. WOOD WORK IN INTERNAL DOOR
7
GLASS WORK
AS REQUIRED
8
ELECTRIC FITTINGS
ISI MARK
9
CONDUCTING AND WIRING DETAILS
ISI MARK
10
CUPBOARD DETAILS
NO
11
WATER STORAGE
UNDERGROUND & OVERHEAD TANK
12
LIFT DETAILS
AS REQUIRED
13
EXTERNAL GLAZINGS
AS REQUIRED
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
FLUSH DOOR
14.1
MAIN DOORS
FLUSH DOOR
14.2
INTERNAL DOORS
FLUSH DOOR
15
AIR CONDITIONING
NO
16
ELECTRICAL FITTINGS
ISI MARK
17
CNG PIPE LINE
N.A.
18
PROVISION OF WIFI AND BROADBAND FACILITY
N.A.
19
EXTERNAL FINISHING/COLOUR SCHEME
GOOD QUALITY EXTERIOR PAINT
20
INTERNAL FINISHING
OIL BOUND DISTEMPER IN WALL & CEILING
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
VITRIFIED TILE
1 . 2
WALLS
OIL BOUND DISTEMPER
1 . 3
CEILING
OIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
VITRIFIED TILE
2 . 2
WALLS
OIL BOUND DISTEMPER
2 . 3
CEILING
OIL BOUND DISTEMPER
2 . 4
MODULAR WARDROBES
N.A.
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC TILES
3 . 2
WALLS
CERAMIC TILES
3 . 3
CEILING
FALSE CEILING
3 . 4
COUNTERS
NO
3 . 5
SANITARY WARE/CP FITTINGS
AS REQUIRED
3 . 6
FITTING/FIXTURES
AS REQUIRED
4 . BED ROOMS
4 . 1
FLOOR
VITRIFIED TILE
4 . 2
WALLS
OIL BOUND DISTEMPER
4 . 3
CEILING
OIL BOUND DISTEMPER
4 . 4
WARDROBES
NO
5 . TOILET
5 . 1
FLOOR
CERAMIC FLOOR TILE
5 . 2
WALLS
CERAMIC WALL TILE
5 . 3
CEILING
FALSE CEILING
5 . 4
COUNTERS
N.A.
5 . 5
SANITARY WARE/CP FITTINGS
AS REQUIRED
5 . 6
FIXTURES
REPUTED MAKE
6 . KITCHEN
6 . 1
FLOOR
VITRIFIED ILE
6 . 2
WALLS
CERAMIC TILE UPTO 2 FEET HEIGHT
6 . 3
CEILING
OIL BOUND DISTEMPER
6 . 4
COUNTERS
MARBLE/ GRANITE
6 . 5
FIXTURES
AS PER REQUIREMENT
6 . 6
KITCHEN APPLIANCES
N.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
N.A.
7 . 2
WALLS & CEILING
N.A.
7 . 3
TOILET
N.A.
7 . 4
BALCONY
N.A.
8 . SIT-OUTS
8 . 1
FLOOR
N.A.
8 . 2
WALLS & CEILING
N.A.
8 . 3
RAILINGS
N.A.
8 . 4
FIXTURES
N.A.
Sr. No.
Document Description
Date of Document Upload
View Document
1
AREA DETAILS PLAN BLOCK 20 TO 23
01-02-2019
------
2
ELEVATION & SECTION BLOCK 20 TO 22
01-02-2019
------
3
BALANCE SHEET AND AUDIT REPORT 2016
01-02-2019
------
4
DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT