HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1933-2026
Submission Date : 07-02-2026 01:28:25 PM
Applicant Type : Firm
Project Type: NEW


FLOWER INFRACON LLP
1123, 11TH FLOOR, DLF TOWER B, JASOLA DISTRICT CENTER, JASOLA, NEW DELHI 110025
01140543200
8588824699 (Number Shared by Promoter in Public)
info@rpsgroupindia.com
ABB8366
AAIFF5387M













RPS ZINNIA
SECTOR-3B, BAHADURGARH, DISTRICT JHAJJAR, HARYANA
BAHADURGARH
JHAJJAR
01140543200
7291989510 (Number Shared by Promoter in Public)
info@rpsgroupindia.com
VIPIN KUMAR SOIN
01140543200
7291989510 (Number Shared by Promoter in Public)
head.construction@avabharat.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151329315-01-2026175000ICICI BANKHRERA Panchkula







31464.34 (Sqr/mtrs)
200
200
31464.34 (Sqr/mtrs)
Licence No 1 of 2026 Dated 02.01.2026 Granted by Honble DTCP Haryana
Yes







4414.51 Lakhs
1745.10 Lakhs
0 Lakhs
1408.48 Lakhs
1260.93 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 16631.147
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 7917.185
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 2361.316
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 150
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 3147.412
12ANY OTHER 0
13COMMERCIAL 1257.280
Total31464.34




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS128.44YET TO BE PREPARED
2WATER SUPPLY SYSTEM32.11YET TO BE PREPARED
3STORM WATER DRAINAGE169.73YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM192.67YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL133.03YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS32.11YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15PLUMBING PUMPS18.35YET TO BE PREPARED
16IRRIGATION N TUBE WELL SUPPLY9.18YET TO BE PREPARED
17CONSTRUCTION OF BOUNDARY WALL N GUARD ROOM57.34YET TO BE PREPARED
18STP N UGT CIVIL WORKS 151.38YET TO BE PREPARED
19STP MECHANICAL WORKS77.99YET TO BE PREPARED
20STREET LIGHT27.53YET TO BE PREPARED
21STEEL N CEMENT91.75YET TO BE PREPARED
22SOFT COSTS CONSULTANTS41.29YET TO BE PREPARED
23SITE DEVELOPMENT218.06YET TO BE PREPARED
24OTHERS N MISC27.53YET TO BE PREPARED


02-01-2026 (date)
02-01-2026 (date)
02-03-2026
31-12-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 149.848 24
2 118.621 1
3 118.361 15
4 142.169 19
5 144.828 1
6 148.044 18
7 107.899 14
8 107.699 2
9 149.307 20
10 102.124 8
11 100.812 1
Total123


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements08.008.008.00
Water Supply System02.002.002.00
Sewerage treatment & garbage disposal08.008.008.00
Electricity Supply System0005.00
Storm Water Drainage010.0010.0010.00
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Others and Misc1.501.501.50
Soft Costs and Consultants5.001.501.50
Steel and Cement14.005.005.00
Construction of Boundary Wall and Guard Room20.0020.0017.34
Irrigation and Tube well supply0.60
Site Development218.06
Soft Costs N Consultants5.00
Others N Misc1.50

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.008.008.008.00
Water Supply System2.002.002.002.00
Sewerage treatment & garbage disposal8.008.008.008.00
Electricity Supply System5.005.005.005.00
Storm Water Drainage10.0010.0010.0010.00
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Soft Costs and Consultants1.501.501.50
STP N UGT Civil Works10.0010.00
Others and Misc1.501.501.50
Steel and Cement5.005.005.00
Irrigation and Tube well supply0.600.600.600.60
STP and UGT Civil Works10.0010.00
Others N Misc1.50
Soft Costs Consultants1.50
Steel n Cement6.00

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.008.008.008.00
Water Supply System2.002.002.002.00
Sewerage treatment & garbage disposal8.008.008.007.00
Electricity Supply System5.005.005.0017.00
Storm Water Drainage10.0010.0010.0010.00
Parks and Playgrounds005.005.00
Clubhouse/community centres0000
Shopping area0000
Other0000
Steel and Cement5.005.005.005.00
Irrigation and Tube well supply0.600.600.600.60
STP and UGT Civil Works10.0010.0010.0010.00
Soft Costs and Consultants1.501.501.501.50
Others and Misc1.001.001.001.00

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.008.008.008.00
Water Supply System2.002.002.002.00
Sewerage treatment & garbage disposal7.007.007.007.00
Electricity Supply System17.0017.0017.0017.00
Storm Water Drainage10.0010.0010.0010.00
Parks and Playgrounds004.004.00
Clubhouse/community centres0000
Shopping area0000
Other0000
Soft Costs and Consultants1.501.501.501.50
Steel and Cement5.005.005.005.00
STP Mechanical Works11.0011.0011.00
STP and UGT Civil Works10.0010.0010.0010.00
Others and Misc1.001.001.001.00
Irrigation and Tube well supply0.600.600.600.60

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.44000
Water Supply System2.110-6790000
Sewerage treatment & garbage disposal7.007.004.030
Electricity Supply System17.0017.0017.0016.67
Storm Water Drainage10.009.733840000
Parks and Playgrounds4.004.004.002.11
Clubhouse/community centres0000
Shopping area0000
Other0000
Others and Misc1.001.005.53
STP Mechanical Works11.0011.0011.00
STP and UGT Civil Works10.0010.0011.38
Soft Costs and Consultants1.501.507.29
Steel and Cement5.001.75
Street Light10.0010.00
Plumbing Pumps10.00
Irrigation and Tube well supply1.38












Yes
No
HDFC BANK LTD
99900000004793
HDFC0000093
110240013
0093
Shri Rakesh Chand Gupta S/o Late Shri Ramesh Chand Gupta R/o House No. 946 Sector 15 Faridabad Haryana And Mr. Vipin Tehlan S/o Shri Vikram Singh Tehlan R/o 542 UJWA SOUTH WEST DELHI DELHI - 110073
Uploaded











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO. 01 OF 2026ALREADY BEEN OBTAINED02-01-2026
II. LAYOUT DRAWING NO. 11771 UNDER LC - 5489ALREADY BEEN OBTAINED02-01-2026
III. DEMARCATION CUM ZONING PLAN ALREADY BEEN OBTAINED06-02-2026








Yes


Yes


As per RERA Act and Rules













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENO
2WALL FINISHING DETAILSNO
3KITCHEN DETAILSNO
4BATHROOM FITTINGSNO
5WOOD WORK ETCNO
6DOORS AND WINDOS FRAMESNO
7GLASS WORKNO
8ELECTRIC FITTINGSNO
9CONDUCTING AND WIRING DETAILSNO
10CUPBOARD DETAILSNO
11WATER STORAGENO
12LIFT DETAILSNO
13EXTERNAL GLAZINGSNO
13.1WINDOWS/GLAZINGSNO
14DOORSNO
14.1MAIN DOORSNO
14.2INTERNAL DOORSNO
15AIR CONDITIONINGNO
16ELECTRICAL FITTINGSNO
17CNG PIPE LINENO
18PROVISION OF WIFI AND BROADBAND FACILITYNO
19EXTERNAL FINISHING/COLOUR SCHEMENO
20INTERNAL FINISHINGNO
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNO
1 . 2 WALLSNO
1 . 3 CEILINGNO
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNO
2 . 2 WALLSNO
2 . 3 CEILINGNO
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOORNO
3 . 2 WALLSNO
3 . 3 CEILINGNO
3 . 4 COUNTERSNO
3 . 5 SANITARY WARE/CP FITTINGSNO
3 . 6 FITTING/FIXTURESNO
4 . BED ROOMS
4 . 1 FLOORNO
4 . 2 WALLSNO
4 . 3 CEILINGNO
4 . 4 WARDROBESNO
5 . TOILET
5 . 1 FLOORNO
5 . 2 WALLSNO
5 . 3 CEILINGNO
5 . 4 COUNTERSNO
5 . 5 SANITARY WARE/CP FITTINGSNO
5 . 6 FIXTURESNO
6 . KITCHEN
6 . 1 FLOORNO
6 . 2 WALLSNO
6 . 3 CEILINGNO
6 . 4 COUNTERSNO
6 . 5 FIXTURESNO
6 . 6 KITCHEN APPLIANCESNO
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNO
7 . 2 WALLS & CEILINGNO
7 . 3 TOILETNO
7 . 4 BALCONYNO
8 . SIT-OUTS
8 . 1 FLOORNO
8 . 2 WALLS & CEILINGNO
8 . 3 RAILINGSNO
8 . 4 FIXTURESNO












Sr. No.Document DescriptionDate of Document UploadView Document
1 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 07-02-2026 View Document
2 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 07-02-2026 View Document
3 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 17-01-2026 View Document
4 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 07-02-2026 View Document
5 ZONING PLAN 07-02-2026 View Document
6 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 07-02-2026 View Document
7 APPROVAL LETTER DEMARCATION CUM ZONING 07-02-2026 ------
8 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 17-01-2026 View Document
9 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 07-02-2026 View Document
10 DEMARCATION PLAN 07-02-2026 View Document
11 CLUB AREA DEMARCATION CUM ZONING 07-02-2026 ------
12 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 17-01-2026 View Document
13 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 07-02-2026 View Document