HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2137-2025
Submission Date : 23-01-2026 04:57:58 PM
Applicant Type : Company
Project Type: NEW




BPTP LIMITED
OT-14, 3RD FLOOR, NEXTDOOR PARKLANDS,SECTOR-76 FARIDABDFARIDABAD HR 121004
9717790021
9717790021 (Number Shared by Promoter in Public)
Rera.gurugram@bptp.com
Http://bptp.com
XXXX442A
U45201HR2003PLC082732
 
 


 
 


 
 


 
 


 
 


 
 







BPTP GREEN OAKS BOULEVARD II
SECTOR 70A GURUGRAM
GURGAON
GURUGRAM
9810810516
9810810516 (Number Shared by Promoter in Public)
RERA.GURUGRAM@BPTP.COM
DEVENDER KUMAR
9810810516
9810810516 (Number Shared by Promoter in Public)
rera.gurugram@bptp.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
126626522-01-202645023INDUSIND BANK SECTOR 44 NOIDAHRERA Gurugram
226626422-01-202615073INDUSIND BANK SECTOR 44 NOIDAHRERA Gurugram







0.247 (Acre)
1.50
1.15
15.6250 (Acre)
61 of 2021
Yes







1215.15 Lakhs
72.27 Lakhs
720.14 Lakhs
48.11 Lakhs
374.63 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.115
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0.132
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total0.247




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS10.74SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM4.30SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE1.72SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM23.63SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL1.29SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS2.15SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15FIRE4.30SUBMITTED TO TOWN & COUNTRY PLANNING


NA (date)
04-09-2025 (date)
01-04-2026
31-12-2032
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings616.96231





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments18.4418.447.567.56
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments12.1013.617.5610.59
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments10.5912.1013.616.05
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments7.569.076.059.07
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments47.5347.5357.0433.27
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments38.0252.2842.7838.02
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments52.2866.54
Shops00
Plots00




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00.340
Water Supply System0.340.100.39
Sewerage treatment & garbage disposal0.101.890.12
Electricity Supply System1.8902.13
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements01.070.970.86
Water Supply System0.430.520.600.64
Sewerage treatment & garbage disposal0.130.15180.19
Electricity Supply System2.362.843.313.54
Storm Water Drainage0000.34
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.071.181.070.97
Water Supply System0.340.470.130.09
Sewerage treatment & garbage disposal0.100.140.040.03
Electricity Supply System1.892.600.710.47
Storm Water Drainage0.340.340.340.34
Parks and Playgrounds0.110.210.210.26
Clubhouse/community centres0000
Shopping area0000
Other0000
FIRE0.34

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.070.860.320.21
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0.190.210.210.17
Clubhouse/community centres0000
Shopping area0000
Other0000
FIRE0.520.860.640.43

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.320.210.210.32
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0.190.130.150.06
Clubhouse/community centres0000
Shopping area0000
Other0000
FIRE0.520.520.260.21

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0.06
Clubhouse/community centres0
Shopping area0
Other0












Yes
No
RBL BANK, GROUND FLOOR, M-6, HAUZ KHAS, NEW DELHI - 110016
400011111141
RATN0000141
110176006
0141
Mr. Kabul Chawla Address: 7, Amrita Shergill Marg Delhi-110003 Mr. Sudhanshu Tripathi Address: 202, 3rd Floor, Jor Bagh, , Delhi -110003 Mr. Manik Malik D- 2/2406, Vasant Kunj, South West Delhi, Delhi- 110070 Mr. Sachin Gupta H.No C-5/32. Yamuna Vihar, Delhi -110053 Mr. Rakesh Kumar Agrawal D-308 , Narwana Apartment , 89, IP Extension , Patparganj Delhi- 110092 Mr. Amit Singhal Address: E3/28, Nand Nagri Mandoli Delhi-110093 Mr. Sanjeev Loknath Agrawal Flat no 32 Sudarshan Apartments IP Extension Delhi -110092
ATTACHED











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
No
No


Yes
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. SERVICE PLAN ESTIMATES APPROVALALREADY BEEN OBTAINED07-11-2024
II. ZONING PLANALREADY BEEN OBTAINED09-02-2023
III. BUILDING PLANALREADY BEEN OBTAINED04-09-2025
IV. ROADSALREADY BEEN OBTAINED23-01-2026
V. ELECTRICAL LOADALREADY BEEN OBTAINED08-02-2023
VI. SITE PLANALREADY BEEN OBTAINED04-09-2025
VII. WATER SUPPLY (ASSURANCE GRANTED)ALREADY BEEN OBTAINED08-10-2021
VIII. SEWAGE DISPOSAL (ASSURANCE GRANTED)ALREADY BEEN OBTAINED28-09-2021
IX. STORM WATER DRAINAGE (ASSURANCE GRANTED)ALREADY BEEN OBTAINED29-09-2021








Yes


Yes


As per HRERA rules







102 EDEN ESTATE II
7.03125
0
65
0
65
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2934.302934.3
Cost of the apartments000
Cost of the infrastructure1453.7201387.67
Others costs1480.5801546.63


10634.48 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-09-2021
31-12-2032




102 EDEN ESTATE III
9.903
0
126
0
103
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4760.0904760.09
Cost of the apartments000
Cost of the infrastructure2358.0001967.54
Others costs2402.0902792.55


28366.63 Lakhs
9488.94 Lakhs
0 Lakhs
0 Lakhs
No
02-04-2025
27-11-2029




ASTAIRE GARDEN
97.98125
0
1129
0
851
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
91369.15091369.15
Cost of the apartments000
Cost of the infrastructure45017.87044974.17
Others costs46351.28046394.98


202055.21 Lakhs
2710.25 Lakhs
0 Lakhs
0 Lakhs
No
01-04-2011
31-08-2026




DOWNTOWN 66
4.235
504
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
000
Cost of the apartments000
Cost of the infrastructure000
Others costs000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-01-2026
31-10-2032




VERTI GREENS
9.4292
885
0
471
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
210964.120210964.12
Cost of the apartments178633.0207891.03
Cost of the infrastructure000
Others costs32331.10203073.09


149808.65 Lakhs
120388.54 Lakhs
0 Lakhs
0 Lakhs
No
01-04-2025
14-06-2032




GAIA RESIDENCIES
1.6838
531
0
0
64
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
93542.92093542.92
Cost of the apartments82337.770432.98
Cost of the infrastructure000
Others costs11205.15093109.94


25170.18 Lakhs
21697.71 Lakhs
0 Lakhs
0 Lakhs
No
01-10-2025
01-10-2032




GREEN OAKS
15.5625
0
258
0
197
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6630.3806630.38
Cost of the apartments000
Cost of the infrastructure3658.5503658.55
Others costs2971.8302971.83


42671.15 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-10-2021
27-08-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEINTERNAL TILE - NITCO-CREMA BELLINI TILE EXTERNAL STONE-NITCO-GISELLE GREY, NITCO-CREMA BELLA WALKWAY – AS/LANDSCAPE
2WALL FINISHING DETAILSEXTERNAL – 1.DULUX RAJKOT FARMHOUSE BEIGE(60YY 75/108) WITH TEXTURE. 2. VOX FRONTO– SLAT PANEL WALNUT V BLACK 3. FRP CORNICE FINISHED SAME AS WALL SCHEME INTERNAL- 1. DULUX RAL 9010 (PURE WHITE)
3KITCHEN DETAILSNIL
4BATHROOM FITTINGSJAQUAR & AQUIANT
5WOOD WORK ETCFAçADE (VOX FRONTO-SLAT PANEL WALNUT V-BLACK)
6DOORS AND WINDOS FRAMESFRAME SIZE-110X60 DOOR QUANTITY- 23 WINDOW QUANTITY- 37
7GLASS WORKONLY EXTERNAL FACADE
8ELECTRIC FITTINGS-
9CONDUCTING AND WIRING DETAILS-
10CUPBOARD DETAILSNIL
11WATER STORAGEDOMESTIC WATER – 2700 LTRS FIRE WATER TANK – 25000 LTRS FLUSHING WATER – 2700 LTRS
12LIFT DETAILS 2 NOS. (1750X1850)
13EXTERNAL GLAZINGS-
13.1WINDOWS/GLAZINGS-
14DOORS-
14.1MAIN DOORS-
14.2INTERNAL DOORS-
15AIR CONDITIONING-
16ELECTRICAL FITTINGS-
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYNIL
19EXTERNAL FINISHING/COLOUR SCHEME1.DULUX RAJKOT FARMHOUSE BEIGE(60YY 75/108) WITH TEXTURE. 2. VOX FRONTO– SLAT PANEL WALNUT V BLACK 3. FRP CORNICE FINISHED SAME AS WALL SCHEME 4. METAL PIPES & FRAMES FINISHED IN COAL MINE. 5. (STONE)NITCO-GISELLE GREY, NITCO-CREMA BELLA 6. VOX SOFIT WALNUT CEILING PANEL 7. METAL PATTERNED JAALI 8. (ALSTONE HPL) DREAMY GREY & CUSTOMIZED TEXTURED HPL
20INTERNAL FINISHINGPAINT DULUX RAL 9010 (PURE WHITE) TOILET 1. SIMPOLO RICCO TILE-AURORA PEARL (WALL) 2. SIMPOLO RICCO TILE-CONMET DOVE (FLOOR) 3. SIMPOLO,SPARKO WHITE POLISHED COUNTER TOP
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNIL
1 . 2 WALLSNIL
1 . 3 CEILINGNIL
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNIL
2 . 2 WALLSNIL
2 . 3 CEILINGNIL
2 . 4 MODULAR WARDROBESNIL
3 . MASTER TOILET
3 . 1 FLOORNIL
3 . 2 WALLSNIL
3 . 3 CEILINGNIL
3 . 4 COUNTERSNIL
3 . 5 SANITARY WARE/CP FITTINGSNIL
3 . 6 FITTING/FIXTURESNIL
4 . BED ROOMS
4 . 1 FLOORNIL
4 . 2 WALLSNIL
4 . 3 CEILINGNIL
4 . 4 WARDROBESNIL
5 . TOILET
5 . 1 FLOORNIL
5 . 2 WALLSNIL
5 . 3 CEILINGNIL
5 . 4 COUNTERSNIL
5 . 5 SANITARY WARE/CP FITTINGSNIL
5 . 6 FIXTURESNIL
6 . KITCHEN
6 . 1 FLOORNIL
6 . 2 WALLSNIL
6 . 3 CEILINGNIL
6 . 4 COUNTERSNIL
6 . 5 FIXTURESNIL
6 . 6 KITCHEN APPLIANCESNIL
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNIL
7 . 2 WALLS & CEILINGNIL
7 . 3 TOILETNIL
7 . 4 BALCONYNIL
8 . SIT-OUTS
8 . 1 FLOORNIL
8 . 2 WALLS & CEILINGNIL
8 . 3 RAILINGSNIL
8 . 4 FIXTURESNIL












Sr. No.Document DescriptionDate of Document UploadView Document
1 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 23-01-2026 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 23-01-2026 View Document
3 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 23-01-2026 View Document
4 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 23-01-2026 View Document
5 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 23-01-2026 View Document
6 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 23-01-2026 View Document
7 FOREST NOC BPTP 20-04-2026 View Document
8 NEC 20-04-2026 View Document
9 POWER SHIFTING UNDERTAKING 20-04-2026 View Document
10 10AUTO DEBIT UNDERTAKING 20-04-2026 View Document
11 COLLABORATION 20-04-2026 View Document
12 FORM LC-IV 20-04-2026 View Document
13 ALLOTMENT LETTER 20-04-2026 View Document
14 WILDLIFE CLEARANCEUNDERTAKING 20-04-2026 View Document
15 ELEVATION AND SECTION 20-04-2026 View Document
16 SERVICE ESTIMATE APPROVAL 20-04-2026 View Document
17 PERT CHART CONSTRUCTION 20-04-2026 View Document
18 FORM LC-IV-B 20-04-2026 View Document
19 ROAD LAYOUT 20-04-2026 View Document
20 LAND SCHEDULE 15.5625 ACRES IN SEC-70A, GGM 20-04-2026 View Document
21 FIRE SCHEME APPROVAL 20-04-2026 View Document
22 AKSHHIZRA 20-04-2026 View Document
23 AGREEMENT TO SALE 20-04-2026 View Document
24 APPLICATION FORM 20-04-2026 View Document
25 ORDER MERGER-AMALGAMATED GURUGRAM, 20-04-2026 View Document
26 REP II 20-04-2026 View Document
27 ELECTRICAL APPROVAL DTD 08.02.2023 FOR DDJAY SEC-70A 20-04-2026 View Document
28 WATER SUPPLY LAYOUT 20-04-2026 View Document
29 LICENSE 20-04-2026 View Document
30 FLOOR PLAN 20-04-2026 View Document
31 BOARD RESOLUTION 20-04-2026 View Document
32 FLUSHING WATER LAYOUT 20-04-2026 View Document
33 CA CERTIFICATE NO DEFAULT 20-04-2026 View Document
34 ZONING PLAN APPROVED LETTER ON 09.02.2023 (15.5625ACS) 20-04-2026 View Document
35 STORM WATER LAYOUT 20-04-2026 View Document
36 BANK UNDERTAKING 20-04-2026 View Document
37 SEWERAGE LAYOUT 20-04-2026 View Document
38 CA CERTIFICATE COST FINAL BOULEVARD II 20-04-2026 View Document
39 COVEYANCE DEED 20-04-2026 View Document
40 BR III 20-04-2026 View Document
41 PAYMENT RECEIPT 20-04-2026 View Document
42 TITLE SEARCH. 20-04-2026 View Document
43 LICENSE ENTRY 20-04-2026 View Document
44 LICENSE NO. 61 OF 2021 FOR DDJAY OF 15.5625ACS SEC-70A 20-04-2026 View Document
45 LOI 15.5625ACS. 20-04-2026 View Document
46 NCZ UNDERTAKING 20-04-2026 View Document
47 NETWORTH 20-04-2026 View Document
48 STORM WATER CONN.- ASSURANCE APPROVAL LETTER DTD 29.09.2021 20-04-2026 View Document
49 TERRACE PLAN 20-04-2026 View Document
50 WATER DOMESTIC - ASSURANCE APPROVAL LETTER DTD 08.10.2021 20-04-2026 View Document