9050281632 (Number Shared by Promoter in Public)
visionpridegreen@gmail.com
XXXX988E
U70101DL2013PTC250631
VISION PRIDE GREEN
VILLAGE GARH SHAHJAHANPUR,SECTOR-17
SONIPAT
SONIPAT
9910098163 (Number Shared by Promoter in Public)
visionpridegreen@gmail.com
ARVIND KUMAR
9910098163 (Number Shared by Promoter in Public)
visionpridegreen@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
0
10-12-2025
315000
RTGS VIDE UTR NO HDFCR52025121093185508 HDFC BANK
HRERA Panchkula
6.81 (Acre)
1.00 FOR PLOTTED AND 1.50 FOR COMMERCIAL
1.00
6.81 (Acre)
LICENSE NO. 246 OF 2023 DATED 15.11.2023 VALID UPTO 14.11.2028 AND TRANSFER OF LICENSE VIDE MEMO 17314-18 DATED 09.05.2025 ISSUED BY DTCP HARYANA
Yes
3778.62 Lakhs
1875.58 Lakhs
0 Lakhs
1840.08 Lakhs
62.96 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.839
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1.22
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.537
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.681
12
ANY OTHER
0.26
13
COMMERCIAL AREA
0.273
Total
6.81
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
UHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
340
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
75
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
50
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
280
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
170
AS PER PROJECT REPORT
6
STREET LIGHTING
25
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
20
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
50
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
20
AS PER PROJECT REPORT
15
BOUNDARY WALL
175
AS PER PROJECT REPORT
16
LAND FILLING
125
AS PER PROJECT REPORT
17
TOE WALLS
55
AS PER PROJECT REPORT
18
MAIN GATE
22
AS PER PROJECT REPORT
19
UGT
135
AS PER PROJECT REPORT
20
RAIN WATER HARVESTING
42
AS PER PROJECT REPORT
29-10-2025 (date)
NA (date)
01-01-2026
14-11-2028
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
96.707
12
2
125.997
1
3
126.546
13
4
119.207
8
5
97.052
8
6
112.737
1
7
113.430
7
8
145.846
44
9
107.625
22
10
135.062
3
11
129.314
6
Total
125
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
30.90
30.90
30.90
30.90
Water Supply System
6.818
6.818
6.818
6.818
Sewerage treatment & garbage disposal
15.45
15.45
15.45
15.45
Electricity Supply System
25.45
25.45
25.45
25.45
Storm Water Drainage
4.545
4.545
4.545
4.545
Parks and Playgrounds
4.545
4.545
4.545
4.545
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
2.272
2.272
2.272
2.272
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
30.90
30.90
30.90
30.90
Water Supply System
6.818
6.818
6.818
6.818
Sewerage treatment & garbage disposal
15.45
15.45
15.45
15.45
Electricity Supply System
25.45
25.45
25.45
25.45
Storm Water Drainage
4.545
4.545
4.545
4.545
Parks and Playgrounds
4.545
4.545
4.545
4.545
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
2.272
2.272
2.272
2.272
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
30.90
30.90
30.90
Water Supply System
6.818
6.818
6.818
Sewerage treatment & garbage disposal
15.45
15.45
15.45
Electricity Supply System
25.45
25.45
25.45
Storm Water Drainage
4.545
4.545
4.545
Parks and Playgrounds
4.545
4.545
4.545
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
STREET LIGHTING
2.272
2.272
2.272
Yes
No
AU SMALL FINANCE BANK SECTOR 16 FARIDABAD HARYANA
2502211878536030
AUBL0002118
110765003
002118
SANDEEP KAUSHIK R/O H NO 410 SECTOR 15 SONIPAT HARYANA
UPLOADED
Yes
Yes
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 246 OF 2023
ALREADY BEEN OBTAINED
15-11-2023
II. ZONING CUM DEMARCATION
ALREADY BEEN OBTAINED
04-12-2025
Yes
Yes
ANNEXED AS PER RERA ACT, 2016 AND HRERA RULES,2017
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: