HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1901-2025
Submission Date : 19-12-2025 04:51:20 PM
Applicant Type : Firm
Project Type: NEW


SHF SQUARE LLP
856, SECTOR 14, GURGAON, HARYANA,122001, INDIA
8745977977 (Number Shared by Promoter in Public)
ADMIN@SHFSQUARE.COM
AAO2590
ADWFS5747F













SHF NIVASA
VILLAGE TALAO, SECTOR-36
JHAJJAR
JHAJJAR
8745977977 (Number Shared by Promoter in Public)
ADMIN@SHFSQUARE.COM
NAVEEN SHARMA
8745977977 (Number Shared by Promoter in Public)
SHARMANAVEEN050@GMAIL.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
12608-12-2025134500.00HDFC BANK HRERA Panchkula







5.84375 (Acre)
1.0 FOR PLOTTED AND 1.5 FOR COMMERCIAL
1
5.84375 (Acre)
LICENSE NO. 196 OF 2025, GRANTED BY DTCP HARYANA ON 15-10-2025, IS VALID UP TO 14-10-2030.
Yes







3324.68 Lakhs
1330.81 Lakhs
0 Lakhs
1741.99 Lakhs
251.88 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 3.0908
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.46795
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.474
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0.584
12ANY OTHER 0
13COMMERCIAL 0.227
Total5.84375




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS127.72AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM171.66AS PER PROJECT REPORT
3STORM WATER DRAINAGE56.66AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM62.50AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL215.37AS PER PROJECT REPORT
6STREET LIGHTING22.82AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS25.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER335.00AS PER PROJECT REPORT
15BOUNDARY WALL450.00AS PER PROJECT REPORT
16UGT110.26AS PER PROJECT REPORT
17SOIL FILLING 165.00AS PER PROJECT REPORT


15-10-2025 (date)
NA (date)
01-01-2026
14-10-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 131.138 19
2 140.790 1
3 123.399 7
4 131.662 1
5 125.088 17
6 128.760 3
7 135.233 8
8 116.154 22
9 133.052 7
10 147.089 8
11 116.680 1
12 114.460 1
13 141.760 1
14 127.840 1
15 121.260 1
Total98


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00012.85
Water Supply System12.9515.7812.2211.12
Sewerage treatment & garbage disposal0019.1918.75
Electricity Supply System004.116.10
Storm Water Drainage4.304.304.304.30
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other18.1218.6019.1918.75
Boundary Wall25.0324.5324.1334.20
Street Lighting2.032.432.122.11
UGT10.958.407.205.10
SOIL FILING11.9514.7811.228.12

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements11.2112.5411.2312.59
Water Supply System9.778.307.108.12
Sewerage treatment & garbage disposal17.5017.3018.3317.33
Electricity Supply System6.127.205.205.60
Storm Water Drainage4.304.304.304.30
Parks and Playgrounds2.502.502.502.50
Clubhouse/community centres0000
Shopping area0000
Other17.5017.3018.3317.33
SOIL FILING10.209.105.126.12
UGT7.817.306.107.20
Boundary Wall35.6025.1225.1326.50
Street Lighting2.122.692.202.40

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements11.2005.2612.20
Water Supply System9.106.957.805.90
Sewerage treatment & garbage disposal17.1016.5017.508.13
Electricity Supply System5.415.885.125.14
Storm Water Drainage4.304.304.634.03
Parks and Playgrounds2.502.502.502.50
Clubhouse/community centres0000
Shopping area0000
Other17.1016.5017.5018.13
Street Lighting2.602.12
Boundary Wall23.5037.2026.1224.20
UGT8.106.227.506.12
SOIL FILING10.107.208.126.22

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements11.2410.259.038.12
Water Supply System6.608.328.908.66
Sewerage treatment & garbage disposal7.957.506.106.48
Electricity Supply System5.211.4100
Storm Water Drainage5.00000
Parks and Playgrounds2.502.5000
Clubhouse/community centres0000
Shopping area0000
Other17.9517.1215.1017.48
UGT6.105.205.305.66
Boundary Wall26.5022.1225.5824.77
SOIL FILING8.008.328.908.66

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System8.128.007.95
Sewerage treatment & garbage disposal6.508.215.00
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other17.5019.2116.29
SOIL FILING8.126.807.95
Boundary Wall19.77












Yes
No
HDFC BANK LTD. SCO 34 DSC SEC 23 A GURGAON HARYANA 122017
50200116944622
HDFC0000616
110240109
000616
AMIT GOEL S/O MAHAVIR GOEL R/O FLAT NO 703 JASMINIUM APARTMENTS NEAR DPS SCHOOL SECTOR 45 KANAHI 73 GURGAON HARYANA 122003
NON DEFAULT CERTIFICATE ATTACHED IN UPLOAD SECTION











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. APPROVAL OF LAYOUT PLAN ALREADY BEEN OBTAINED15-10-2025
II. APPROVAL OF DEMARCATION CUM ZONNING PLAN ALREADY BEEN OBTAINED04-12-2025








Yes


Yes


THE PROVISION OF RERA ACT AND RULES SHALL BE INCORPORATED IN THE DRAFT AGREEMENTS













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 08-12-2025 View Document
2 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 10-12-2025 View Document
3 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 16-12-2025 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 16-12-2025 View Document
5 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 16-12-2025 View Document
6 PAYMENT PLAN 04-02-2026 ------