HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1900-2025
Submission Date : 17-12-2025 05:57:03 PM
Applicant Type : Company
Project Type: NEW




MANSHA BUILDCON PVT. LTD.
P-23 SECTOR 75, FARIDABAD-121002 HARYANA
9810855773 (Number Shared by Promoter in Public)
malikassociates@gmail.com
http://www.manshagroup.in
XXXX898D
U70109HR2006PTC081926
 
 


 
 


 
 







MANSHA OASIS
VILLAGE FAFUNDA AND GADKHEDA, SECTOR 123-124
DAYALPUR ST
FARIDABAD
8447129022 (Number Shared by Promoter in Public)
malikassociates@gmal.com
HIMANSHU MALIK
8447129022 (Number Shared by Promoter in Public)
malikassociates@gmal.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1017-12-2025922000ONLINE PAYMENT SHALL BE DONE. HRERA Panchkula







21.79375 (Acre)
1.5 FOR COMMERCIAL AND 1.0 FOR RESIDENTIAL PLOTTED
1.0
21.79375 (Acre)
LICENSE NO. 220 OF 2025 DATED 13-11-2025 (VALID UPTO 12-11-2030)
No
Address     P-23, SECTOR 75 FARIDABAD
Address     1041 SECTOR 15 FARIDABAD
Address     D-173, NARMDA APARTMENT, ALKNANDA, SOUTH DELHI-110019
Address     H. NO. 1149, SEC 15, FARIDABAD
Annexure-B- COLLABORATION AGREEMENT AND POWER OF ATTORNEY EXECUTED
YES, REGISTERED.
Yes
AS PER COLLABORATION AGREEMENT THE LAND OWNERS WILL GET %AGE OF NET REVENUE SHARED AGAINST THEIR LAND CONTRIBUTION.
No
Yes
Yes







19797.70 Lakhs
8037.58 Lakhs
0.00 Lakhs
3859.62 Lakhs
7900.050 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 11.00
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 7.3452
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0.03555
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13COMMERCIAL 0.7839
14UGT AND STP 1.9171
15ELECTRIC SUB STATION 0.08303
16NURSERY SCHOOL 0.200
17SPACE FOR SERVICES 0.42392
Total21.7887




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS646.40AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM324.68AS PER PROJECT REPORT
3STORM WATER DRAINAGE332.93AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM475.50AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL208.95AS PER PROJECT REPORT
6STREET LIGHTING150.51AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING75.50AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS88.31AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER1556.84AS PER PROJECT REPORT


13-11-2025 (date)
NA (date)
13-01-2026
12-11-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 398.75 5
2 264.5 4
3 240.465 4
4 176.532 3
5 188.012 7
6 212.85 1
7 359.419 12
8 412.383 4
9 386.141 4
10 249.173 14
11 273.937 2
12 175.595 34
13 221.72 4
14 208.84 4
15 198.26 5
16 157.463 2
17 178.88 3
18 312.062 3
19 184.357 2
20 166.957 12
21 204.5 3
22 176.532 2
23 188.012 7
24 175.595 21
25 221.72 3
26 208.84 2
27 198.26 4
28 178.88 6
29 184.357 2
30 166.957 14
31 50.00 10
32 50.04 17
33 50.042 22
34 3597.91 1
Total243


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.3942.0242.0242.02
Water Supply System9.7421.1021.1021.10
Sewerage treatment & garbage disposal6.2713.5813.5813.58
Electricity Supply System14.2730.9130.9130.91
Storm Water Drainage9.9921.6421.6421.64
Parks and Playgrounds2.655.745.745.74
Clubhouse/community centres0000
Shopping area0000
Other53.49115.89115.89115.89

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements42.0242.0242.0242.02
Water Supply System21.1021.1021.1021.10
Sewerage treatment & garbage disposal13.5813.5813.5813.58
Electricity Supply System30.9130.9130.9130.91
Storm Water Drainage21.6421.6421.6421.64
Parks and Playgrounds5.745.745.745.74
Clubhouse/community centres0000
Shopping area0000
Other115.89115.89115.89115.89

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements42.0242.0242.0242.02
Water Supply System21.1021.1021.1021.10
Sewerage treatment & garbage disposal13.5813.5813.5813.58
Electricity Supply System30.9130.9130.9130.91
Storm Water Drainage21.6421.6421.6421.64
Parks and Playgrounds5.745.745.745.74
Clubhouse/community centres0000
Shopping area0000
Other115.89115.89115.89115.89

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements21.0121.0121.0119.39
Water Supply System10.5510.5510.559.74
Sewerage treatment & garbage disposal6.796.796.796.27
Electricity Supply System15.4515.4515.4514.27
Storm Water Drainage10.8210.8210.829.99
Parks and Playgrounds2.872.872.872.65
Clubhouse/community centres0000
Shopping area0000
Other57.9457.9457.9453.49

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements21.0121.0121.0119.39
Water Supply System10.5510.5510.559.74
Sewerage treatment & garbage disposal6.796.796.796.27
Electricity Supply System15.4515.4515.4514.27
Storm Water Drainage10.8210.8210.829.99
Parks and Playgrounds2.872.872.872.65
Clubhouse/community centres0000
Shopping area0000
Other57.9457.9457.9453.49












Yes
No
ICICI BANK LIMITED, (100% COLLECTION), BRANCH SCO 45, OMAXE WORLD STREET, SEC 79, FARIDABAD
777705981094
ICIC0007323
NOT PROVIDED
007323
Sh. Naresh Kumar Malik R/o H. No. 1041, Sector 14, Faridabad
Uploaded in upload Section











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 220 OF 2025ALREADY BEEN OBTAINED13-11-2025
II. APPROVAL OF DEMARCATION-CUM-ZONING PLAN ALREADY BEEN OBTAINED17-12-2025








Yes


Yes


THE RERA PROVISIONS SHALL BE INCORPORATED IN THE PROPOSED AGREEMENT TO SELL.







MANSHA CITY SECTOR 9 PALWAL
8.76875
0
191
0
191
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1427.7701427.77
Cost of the apartments000
Cost of the infrastructure611.910611.91
Others costs815.860815.86


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
22-04-2022
22-04-2022




MANSHA VEGA STREET (SECTOR 82, FARIDABAD)
4.234
0
60
0
60
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4448.6604448.66
Cost of the apartments000
Cost of the infrastructure739.200739.20
Others costs3709.4603709.46


4130.82 Lakhs
1316.14 Lakhs
0 Lakhs
0 Lakhs
No
16-05-2026
16-05-2026




MANSHA OAKS (SECTOR 98,FARIDABAD)
7.1125
0
132
0
132
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2934.4102934.41
Cost of the apartments000
Cost of the infrastructure1143.3201143.32
Others costs1791.0901791.09


5503.02 Lakhs
643.89 Lakhs
0 Lakhs
0 Lakhs
No
15-04-2026
17-05-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED COLONY
2WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
3KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED COLONY
4BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5WOOD WORK ETCNOT APPLICABLE BEING PLOTTED COLONY
6DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED COLONY
7GLASS WORKNOT APPLICABLE BEING PLOTTED COLONY
8ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
10CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED COLONY
11WATER STORAGENOT APPLICABLE BEING PLOTTED COLONY
12LIFT DETAILSNOT APPLICABLE BEING PLOTTED COLONY
13EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
13.1WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
14DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.1MAIN DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.2INTERNAL DOORSNOT APPLICABLE BEING PLOTTED COLONY
15AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED COLONY
16ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
17CNG PIPE LINENOT APPLICABLE BEING PLOTTED COLONY
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED COLONY
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED COLONY
20INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED COLONY
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
1 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
1 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
2 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
2 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . 4 MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
3 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
3 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
3 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
3 . 6 FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
4 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
4 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
4 . 4 WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
5 . TOILET
5 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
5 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
5 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
5 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5 . 6 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
6 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
6 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
6 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
6 . 5 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED COLONY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
7 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
7 . 3 TOILETNOT APPLICABLE BEING PLOTTED COLONY
7 . 4 BALCONYNOT APPLICABLE BEING PLOTTED COLONY
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
8 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
8 . 3 RAILINGSNOT APPLICABLE BEING PLOTTED COLONY
8 . 4 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 07-12-2025 View Document
2 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 07-12-2025 View Document
3 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 07-12-2025 View Document
4 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 07-12-2025 View Document
5 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 07-12-2025 View Document
6 PAYMENT PLAN 06-02-2026 ------