12A FLOOR, TOWER-2, M3M INTERNATIONAL, FINANCIAL CENTER, SECTOR-66, GURUGRAM, HARYANA
01246600000
8929012754 (Number Shared by Promoter in Public)
swcorporate2021@gmail.com
https://svabhumirealtorspvtltd.com/
XXXX025F
U68100HR2023PTC111218
SMARTWORLD NATURE'S COURT I
SECTOR M9, M10 AND M11
HARSARU ST
GURUGRAM
01246600000
8929012754 (Number Shared by Promoter in Public)
swcorporate2021@gmail.com
CHATTER SINGH
01246600000
8929012754 (Number Shared by Promoter in Public)
swcorporate2021@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
510864
04-12-2025
2486416.00
ICICI BANK LIMITED
HRERA Gurugram
2
510865
04-12-2025
1043349.00
ICICI BANK LIMITED
HRERA Gurugram
8.28 (Acre)
2.37
2.34
139.79375 (Acre)
Licence no 168 of 2025 dated 08.09.2025 Granted by Department of Town and Country Planning Haryana
No
Address 41ST FLOOR, M3M INTERNATIONAL FINANCIAL CENTER, SECTOR 66, GURUGRAM
Annexure-B- ANNEXURE-B- BY THE TERMS AND CONDITIONS OFTHE COLLABORATION AGREEMENT NO. 8775 DATED 17-09-2025.
AFTER GRANT OF LICENCE BY DTCP
Yes
ANNEXED IN FOLDER-A
No
Yes
Yes
177860.37 Lakhs
56000.00 Lakhs
66597.02 Lakhs
7573.47 Lakhs
47689.88 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0.00
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1.48
3
CONSTRUCTION OF ROADS
2.22
4
PAVEMENTS
0.60
5
PARKS AND PLAYGROUNDS
0.67
6
GREEN BELTS
1.27
7
VEHICLE PARKINGS
0.56
8
ELECTRICITY SUB-STATION
0.14
9
CLUB HOUSE
0.00
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.00
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.00
12
ANY OTHER
0.69
13
COMMUNITY AND TEMPLE
0.63
14
HSD TANK
0.02
Total
8.28
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
204.08
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
49.55
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
74.32
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
502.10
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
74.32
AS PER PROJECT REPORT
6
STREET LIGHTING
78.47
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
88.89
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
139.50
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
HARDSCAPE AND SOFTSCAPE
104.63
AS PER PROJECT REPORT
16
BOUNDARY WALL
104.63
AS PER PROJECT REPORT
17
MAIN ENTRANCE WORK AND GUARD HOUSE
39.35
AS PER PROJECT REPORT
18
PARKING MARKING
5.17
AS PER PROJECT REPORT
19
STP
188.92
AS PER PROJECT REPORT
20
UNDERGROUND TANK
130.61
AS PER PROJECT REPORT
21
RAIN WATER HARVESTING
35.92
AS PER PROJECT REPORT
22
ELECTRICAL SUB STATION
1350.70
AS PER PROJECT REPORT
23
CONSULTANCY
2449.03
AS PER PROJECT REPORT
24
INFRASTRUCTURE ESTABLISHMENT COST
1749.30
AS PER PROJECT REPORT
25
DEWATERING
103.44
AS PER PROJECT REPORT
26
GAS AND PNG WORKS
100.47
AS PER PROJECT REPORT
08-09-2025 (date)
09-12-2025 (date)
01-01-2026
30-06-2033
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
43.13
14
14
Apartment/Shops/Other Buildings
58.56
286
14
Apartment/Shops/Other Buildings
60.00
914
14
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
90.41
105.48
135.26
156.46
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
171.67
202.03
659.23
762.91
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
844.73
956.68
1086.09
1467.86
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
2090.60
2674.93
3040.40
3449.36
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
3657.12
3948.94
4265.18
4669.39
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
4077.75
4453.22
4906.13
5065.19
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2032
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
3460.27
3460.27
3371.75
3367.68
Shops
0
0
0
0
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
Water Supply System
0
0
2.48
Sewerage treatment & garbage disposal
0
0
3.72
Electricity Supply System
0
0
0
Storm Water Drainage
0
0
3.72
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Infrastructure Establishment Cost
87.47
87.47
87.47
Gas and PNG Works
5.02
5.02
5.02
Dewatering
5.17
5.17
5.17
Main Entrance work and Guard House
0.79
Boundary Wall
4.19
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
6.12
20.41
20.41
14.29
Water Supply System
4.95
2.48
2.48
2.97
Sewerage treatment & garbage disposal
7.43
3.72
3.72
4.46
Electricity Supply System
0
0
0
0
Storm Water Drainage
7.43
3.72
3.72
4.46
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Dewatering
5.17
5.17
10.34
10.34
Boundary Wall
5.23
5.23
5.23
7.32
Security and Firefighting
0
0
0
0
Gas and PNG Works
5.02
5.02
10.05
10.05
Infrastructure Establishment Cost
87.47
87.47
174.93
174.93
Rain water harvesting
1.80
1.80
2.16
Main Entrance work and Guard House
1.97
2.75
2.75
2.75
STP
7.56
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
14.29
20.41
24.49
24.49
Water Supply System
4.95
4.95
4.46
2.97
Sewerage treatment & garbage disposal
7.43
7.43
6.69
4.46
Electricity Supply System
0
25.11
50.22
75.33
Storm Water Drainage
6.69
7.43
7.43
4.46
Parks and Playgrounds
0
13.95
20.93
27.90
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Underground tank
6.53
13.06
13.06
13.06
Rain water harvesting
2.16
2.87
3.59
3.59
Infrastructure Establishment Cost
94.9231
174.93
87.47
87.47
Street Light
7.85
3.92
7.85
Dewatering
5.17
10.34
5.17
5.17
Parking Marking
0
0
0.78
Gas and PNG Works
5.02
10.05
5.02
5.02
Hardscape and Softscape
10.46
10.46
15.69
20.93
Boundary Wall
7.32
10.46
12.56
12.56
Security and Firefighting
0
8.89
0.87
14.82
STP
7.56
13.22
18.89
18.89
Main Entrance work and Guard House
3.93
3.93
2.75
3.93
Particulars
Year-2032
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
16.33
16.33
14.29
12.25
Water Supply System
2.97
3.96
4.95
4.95
Sewerage treatment & garbage disposal
4.46
5.95
7.43
7.43
Electricity Supply System
25.11
75.33
125.55
125.55
Storm Water Drainage
4.46
5.95
7.43
7.43
Parks and Playgrounds
13.95
20.93
20.93
20.93
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Gas and PNG Works
10.05
5.02
5.02
10.05
Infrastructure Establishment Cost
174.93
87.47
87.47
174.93
Consultancy
612.26
612.26
612.26
612.26
STP
28.34
47.23
26.45
20.78
Rain water harvesting
7.18
3.59
3.59
3.59
Underground tank
19.59
32.65
19.59
13.06
Parking Marking
0.78
1.29
1.29
1.03
Street Light
19.62
19.62
7.85
11.77
Hardscape and Softscape
10.46
20.93
10.46
5.23
Boundary Wall
10.46
5.23
8.37
10.46
Security and Firefighting
12.81
13.33
18.29
9.88
Electrification cost
337.67
337.67
337.67
337.67
Main Entrance work and Guard House
3.15
4.33
3.15
3.15
Dewatering
10.34
5.17
5.17
10.34
Yes
No
ICICI BANK LIMITED, SECTOR-54, SUNCITY BRANCH, GURUGRAM
777705702501
ICIC0000399
110229060
000399
1) Gaurav Bansal-C-501, Lions Society, Opposite Tau Devi Lal Park, Sector 56, Gurgaon Sector 56, Gurgaon, Haryana - 122011.
2) Rajat Jain-Villa no 44, Tulip Lvory, Gurgaon, Sector 70, Badshahpur, Gurgaon, Haryana-122101.
3) Anuj Kumar Goel- House No- C-25, Street No-1, Near Sunrise Public School, Bhajanpura, North East, Delhi- 110053.
4) Anil Mittal H No 723, Sector 31 Gurugram.
5) Meenal Sood-C-81A, Moti Nagar, Ramesh Nagar H.O, West Delhi, Delhi 110015.
6) Nitesh Goyal h no 241, Ward no 6, Tauru, Mewat, Haryana-122105.
Uploaded
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
08-09-2025
II. ELECTRIFICATION PLAN APPROVAL
ALREADY BEEN OBTAINED
01-09-2025
III. FOREST NOC
ALREADY BEEN OBTAINED
24-05-2025
IV. ASSURANCE STP TREATED CONSTRUCTION WATER
ALREADY BEEN OBTAINED
12-09-2025
V. ASSURANCE DRINKING WATER CONNECTION
ALREADY BEEN OBTAINED
12-09-2025
VI. ASSURANCE SEWERAGE CONNECTION
ALREADY BEEN OBTAINED
12-09-2025
VII. ASSURANCE STORM WATER CONNECTION
ALREADY BEEN OBTAINED
12-09-2025
Yes
Yes
As Per Harera Rules
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: