HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1881-2025
Submission Date : 21-11-2025 02:26:49 PM
Applicant Type : Firm
Project Type: NEW


KUBER HOMES
624-21, NEAR NEW BUS STAND, AZADGARH, ROHTAK -124001
7407436000 (Number Shared by Promoter in Public)
kuberhomesirsa@gmail.com
614202500011
ABCFK0656R

















KUBER HOMES SIRSA
VILLAGE CHHATARGARH, SECTOR 24 AND 25
SIRSA
SIRSA
7407436000 (Number Shared by Promoter in Public)
kuberhomessirsa@gmail.com
PAWAN
7407436000 (Number Shared by Promoter in Public)
kuberhomessirsa@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1020-11-2025265000ONLINE PAYMENT THROUGH RTGS PUNBR52025112019511965 PNBHRERA Panchkula







12.081 (Acre)
1.00 FOR RESIDENTIAL AND 1.50 FOR COMMERCIAL
1.00
12.081 (Acre)
LICENSE NO 202 OF 2025 DATED 16.10.2025 VALID UPTO 15.10.2030 ISSUED BY DTCP HARYANA
Yes







2931.51 Lakhs
1087.86 Lakhs
0 Lakhs
1493.65 Lakhs
350 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 6.236
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.912
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.919
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 1.208
12ANY OTHER 1.523
13COMMERCIAL AREA 0.283
Total12.081




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS200.70AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM100.05AS PER PROJECT REPORT
3STORM WATER DRAINAGE70.80AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM100.80AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL100.90AS PER PROJECT REPORT
6STREET LIGHTING45AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING10YET TO BE PREPARED
8PLAYGROUNDS AND PARKS85AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE300YET TO BE PREPARED
10SHOPPING AREA120AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM25AS PER PROJECT REPORT
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER15AS PER PROJECT REPORT
15LAND FILLING 140.40AS PER PROJECT REPORT
16ENTRANCE GATE55AS PER PROJECT REPORT
17BOUNDARY WALL130AS PER PROJECT REPORT
18SITE OFFICE20AS PER PROJECT REPORT


16-10-2025 (date)
NA (date)
01-12-2025
30-09-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 128.88 16
2 123.26 7
3 122.88 16
4 129.64 8
5 130.56 16
6 143.68 16
7 149.94 12
8 149.23 22
9 148.35 1
10 142.88 11
11 134.30 11
12 101.23 22
13 146.72 8
14 99.70 22
Total188


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10
Water Supply System5
Sewerage treatment & garbage disposal5
Electricity Supply System5
Storm Water Drainage3.50
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10101010
Water Supply System5555
Sewerage treatment & garbage disposal5555
Electricity Supply System5555
Storm Water Drainage3.503.503.503.50
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10101010
Water Supply System5555
Sewerage treatment & garbage disposal5555
Electricity Supply System5555
Storm Water Drainage3.503.503.503.50
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10101010
Water Supply System5555
Sewerage treatment & garbage disposal5555
Electricity Supply System5555
Storm Water Drainage3.503.503.503.50
Parks and Playgrounds08.508.508.50
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING4.504.504.50

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10101010
Water Supply System5555
Sewerage treatment & garbage disposal5555
Electricity Supply System5555
Storm Water Drainage3.503.503.503.50
Parks and Playgrounds8.508.508.508.50
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING4.504.504.504.50

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements101010
Water Supply System555
Sewerage treatment & garbage disposal555
Electricity Supply System555
Storm Water Drainage3.503.503.50
Parks and Playgrounds8.508.508.50
Clubhouse/community centres000
Shopping area000
Other000
STREET LIGHTING4.504.504.50












Yes
No
PUNJAB NATIONAL BANK MDU ROHTAK BRANCH
7522002900000038
PUNB0752200
124024022
752200
ANOOP R/O VPO CHHICHRANA SONIPAT, JATIN DHAWAN R/O 6-720, 8 MARLA, PANIPAT, PAWAN R/O H NO 624-21, ROHTAK, KARAMBIR SINGH R/O VILLAGE FARMANA ROHTAK
UPLOADED











Yes
No
Yes
No
Yes
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO 202 OF 2025ALREADY BEEN OBTAINED16-10-2025
II. ZONING PLANALREADY BEEN OBTAINED20-11-2025








Yes


Yes


ANNEXED AS PER THE RERA ACT, 2016 AND HRERA RULES, 2017













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE
2WALL FINISHING DETAILSNOT APPLICABLE
3KITCHEN DETAILSNOT APPLICABLE
4BATHROOM FITTINGSNOT APPLICABLE
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESNOT APPLICABLE
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSNOT APPLICABLE
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGENOT APPLICABLE
12LIFT DETAILSNOT APPLICABLE
13EXTERNAL GLAZINGSNOT APPLICABLE
13.1WINDOWS/GLAZINGSNOT APPLICABLE
14DOORSNOT APPLICABLE
14.1MAIN DOORSNOT APPLICABLE
14.2INTERNAL DOORSNOT APPLICABLE
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSNOT APPLICABLE
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE
20INTERNAL FINISHINGNOT APPLICABLE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 21-11-2025 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 21-11-2025 View Document
3 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 21-11-2025 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 21-11-2025 View Document
5 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 21-11-2025 View Document