9818989294 (Number Shared by Promoter in Public)
madhu.rao@eka-dhoot.com
https://risinghomes92.com
XXXX874R
U70109DL2006PTC152635
ALTIS AT DXP 92
SECTOR-92, GURUGRAM HARYANA
HARSARU ST
GURUGRAM
01244966700
9818989294 (Number Shared by Promoter in Public)
madhu.rao@ekalife.com
UMESH KUMAR
01244966700
9818989294 (Number Shared by Promoter in Public)
madhu.rao@eka-dhoot.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
422153
20-02-2026
200000
STATE BANK OF INDIA
HRERA Gurugram
2
422180
18-04-2026
231000
STATE BANK OF INDIA
HRERA Gurugram
3
422191
29-04-2026
844700
STATE BANK OF INDIA
HRERA Gurugram
2.68 (Acre)
1.75
1.75
48.818 (Acre)
44 of 2009 and 68 of 2011
Yes
23200.58 Lakhs
696 Lakhs
9156.49 Lakhs
6338.51 Lakhs
7009.858 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0.00
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.17
3
CONSTRUCTION OF ROADS
0.26
4
PAVEMENTS
0.47
5
PARKS AND PLAYGROUNDS
0.33
6
GREEN BELTS
0.07
7
VEHICLE PARKINGS
0.50
8
ELECTRICITY SUB-STATION
0.03
9
CLUB HOUSE
0.68
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.04
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.13
12
ANY OTHER
0
Total
2.68
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
CONNECTED
No
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
110
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
90
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
70
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
299.15
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
180
AS PER PROJECT REPORT
6
STREET LIGHTING
60
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
120
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
0
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
35
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
UNDERGROUND WATER TANK
450
AS PER PROJECT REPORT
16
RAIN WATER HARVESTING
200
AS PER PROJECT REPORT
17
STP
200
AS PER PROJECT REPORT
18
ELECTRICAL SUB STATION
600
AS PER PROJECT REPORT
19
PARKING
400
AS PER PROJECT REPORT
20
CONSTRUCTION OF CIRCULATION ROADS
150
AS PER PROJECT REPORT
21
ELECTRIFICATION
27.37
AS PER PROJECT REPORT
17-02-2026 (date)
17-02-2026 (date)
01-03-2026
31-03-2032
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
117.47
25
1
Apartment/Shops/Other Buildings
117.49
25
1
Apartment/Shops/Other Buildings
117.562
25
1
Apartment/Shops/Other Buildings
117.771
25
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
57.39
114.77
286.93
474.39
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
608.29
845.48
987.03
891.39
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
868.43
811.05
784.27
661.85
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
260.15
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
500
Water Supply System
200
Sewerage treatment & garbage disposal
300
Electricity Supply System
0
Storm Water Drainage
300
Parks and Playgrounds
930
Clubhouse/community centres
0
Shopping area
0
Other
0
Electrical Sub Station
647.43
Rain Water Harvesting
200
Security and Fire Fighting
200
STP
20
Street Lighting
50
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
Water Supply System
0
0
0
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
0
0
0
Storm Water Drainage
0
0
0
Parks and Playgrounds
0
0
0
Clubhouse/community centres
22.57
45.14
109.84
Shopping area
0
0
0
Other
0
0
0
Electrical Sub Station
30
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
18
Sewerage treatment & garbage disposal
0
0
0
36
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
21
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
209.9
267.83
228.71
221.66
Shopping area
0
0
0
0
Other
0
0
0
0
Electrical Sub Station
30
60
Rain water harvesting
20
20
40
STP
20
20
20
20
Underground Water Tank
90
Electrical sub station
60
Underground water tank
90
90
Electric Sub Station
60
Renewable energy system
7
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
22
22
22
Water Supply System
18
18
18
18
Sewerage treatment & garbage disposal
36
36
36
36
Electricity Supply System
29.92
59.83
59.83
59.83
Storm Water Drainage
21
28
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
191.09
121.88
88.52
7.52
Shopping area
0
0
0
0
Other
0
0
0
0
Security and Fire Fighting
24
24
24
Street Lighting
12
12
12
Renewable Enery system
7
Underground Water Tank
90
90
Rain water harvesting
40
40
20
STP
20
20
20
40
Electric Sub Station
60
Parking
100
100
Renewable Energy
7
Electrical Sub Station
60
60
Renewable Energy System
7
Rain Water Harvesting
20
Street Lighting System
6
Renewable energy system
7
Electrical sub station
60
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
22
22
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
59.83
29.92
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Street Lighting
12
6
Electric Sub Station
60
parking
100
Security and Fire Fightig
24
Construction of circulation roads
150
Electrification
27.37
Electrical Sub Station
60
STP
20
Security and Fire Fighting
24
Parking
100
Yes
Yes
STATE BANK OF INDIA
44946284036
SBIN0050933
110002777
0933
As per Board Resolution attached.
Uploaded.
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. BR-III
ALREADY BEEN OBTAINED
17-02-2026
Yes
Yes
The allottees are bound to make the due payments as per the payment plan. And the promoter shall comply with its obligations as per RERA's rules and regulations.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
LIVING & DINING AREA: STONE FLOORING
MASTER BEDROOM: LAMINATED WOODEN FLOORING
OTHER BEDROOMS: VITIRIFIED TILE FLOORING
BATHROOMS: VITRIFIED TILE FLOORING
BALCONIES: VITRIFIED TILE FLOORING
REST OF THE AREAS: VITRIFIED TILE FLOORING
2
WALL FINISHING DETAILS
EMULSTION PAINT OVER GYPSUM / PLASTER
3
KITCHEN DETAILS
GRANITE STONE TOP PLATFORM WITH SS SINK
CERAMIC TILE DADO UPTO 600MM ABOVE PLATFORM
4
BATHROOM FITTINGS
WATER CONSERVING CP FITTINGS OF REPUTED MAKE
WHITE COLOUR CHINAWEAR OF REPUTED MAKE
5
WOOD WORK ETC
NONE
6
DOORS AND WINDOS FRAMES
ENTRANCE DOOR: 110MM X 55MM DOUBLE REBATE RED MARANTI DOOR FRAME POLISHED
INTERNAL DOORS: 110MM X 55 MM SINGLE REBATE RED MARANTI DOOR FRAME
WINDOWS: UPVC WINDOWS
7
GLASS WORK
LAMINATED GLASS RAILING WITH STAINLESS STEEL PIPE RAILING FOR EXTERNAL BALCONIES
8
ELECTRIC FITTINGS
ISI MARK MODULAR SWITCHES
9
CONDUCTING AND WIRING DETAILS
1.2MM THICK PVC CONDUITS AND COPPER WIRING- ISI CERTIFIED
10
CUPBOARD DETAILS
NIL
11
WATER STORAGE
UNDERGROUND AND OVERHEAD TANKS - CONCRETE TANKS - ONE DAY STORAGE
12
LIFT DETAILS
2 NOS. PASSENGER AND ONE NO. SERVICE LIFTS - 1.75 M/ SEC SPEED - WITH AUTOMATIC RESCUE DEVICE, INTERCOM FACILITY AND CCTV INSTALLED PER EACH TOWER / WING