DSM-648, 6TH FLOOR, DLF TOWERS, SHIVAJIMARG, NAJAFGARH ROAD, MOTI NAGAR, WEST DELHI, NEW DELHI, DELHI, INDIA, 110015
01147108300
9971508555 (Number Shared by Promoter in Public)
crm@jindalrealty.com
http://www.jindalrealty.com
XXXX575L
U45201DL2005PLC140023
AADYAM
VILLAGE RATHDHANA, SECTOR 34
SONIPAT
SONIPAT
8571880108 (Number Shared by Promoter in Public)
crm@jindalrealty.com
DEEPAK KUMAR SUTHAR
8571880108 (Number Shared by Promoter in Public)
crm@jindalrealty.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
Annexure-B- COPY OF COLLABORATION AGREEMENT AND POWER OF ATTORNEY EXECUTED BETWEEN THE DEVELOPER AND THE LAND OWNED COMPANIES. COPIES ANNEXUED.
YES THE AGREEMENTS MADE BEFORE THE GRANT OF LICENSE.
Yes
THE LAND OWNED COMPANIES AND THE DEVELOPER ARE DESIROUS OF DEVELOPING A RESIDENTIAL PLOTTED COLONY OR ANY OTHER DEVELOPMENT AS PER APPLICABLE LAW TO THE OFFICE OF THE TOWN & COUNTRY PLANNING, HARYANA. PURSUANT TO THIS COLLABORATION AGREEMENT, THE LAND OWNED COMPANIES HAVE IRREVOCABLY, ABSOLUTELY AND UNCONDITIONALLY GRANT TO THE DEVELOPER THE ENTIRE DEVELOPMENT RIGHTS OVER THE SCHEDULED LAND. THROUGH POWER OF ATTORNEY WHICH IS DULY IRREVOCABLE AND REGISTERED, THE LAND OWNED COMPANY APPOINT THE DEVELOPER AS A LAWFUL ATTORNEY FOR DEVELOP, SALE, MARKET AND TO EXECUTE THE CONVEYANCE / SALE DEED ETC. FURTHER, AS PER CLAUSE NO. 2.2.3 OF THE COLLABORATION AGREEMENT, THE CONSIDERATION HAVE BEEN AGREED BETWEEN THE LAND OWNER COMPANIES AND THE DEVELOPER.
No
No
Yes
5446.95 Lakhs
1236.95 Lakhs
3990.28 Lakhs
35.44 Lakhs
184.28 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
4104.216
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
4104.216
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
Yes
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVNL
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
0
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
7.09
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
5.32
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
13.47
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
9.57
AS PER PROJECT REPORT
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
16-06-2023 (date)
26-09-2025 (date)
01-01-2026
31-12-2030
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
1133.665
8
8
Apartment/Shops/Other Buildings
1116.16
6
6
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
204.07
317.56
317.56
264.46
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
264.46
506.01
501.70
320.13
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
204.07
204.07
183.94
183.94
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
224.20
42.03
42.03
42.03
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
42.03
42.03
42.03
42.03
Shops
0
0
0
0
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
1.772
1.772
1.772
1.772
Sewerage treatment & garbage disposal
2.3922
2.3922
2.3922
2.3922
Electricity Supply System
3.3668
3.3668
3.3668
3.3668
Storm Water Drainage
1.329
1.329
1.329
1.329
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Yes
No
ICICI BANK LIMITED, O P JINDAL GLOBAL UNIVERSITY,VILLAGE JAGDISHPUR,NARELA ROAD,SONEPAT-131001
385605000154
ICIC0003856
110229257
0003856
Sh. Abhay Kumar Mishra
R/o Jindal Global City Sector 35 Sonipat
Sh. Sanjeev Madan,
R/o. H. No. 3A-93 NIT, Faridabad
Sh. Deepak Kumar Khemchandani
R/o Ramesh Nagar, Rajouri Garden, West Delhi, New Delhi
Uploaded in Upload Section.
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 128 OF 2023
ALREADY BEEN OBTAINED
16-06-2023
II. BUILDING PLANS OF FLOORS OF VARIOUS PLOTS.
ALREADY BEEN OBTAINED
26-09-2025
III. APPROVAL OF ZONING PLAN
ALREADY BEEN OBTAINED
13-09-2023
Yes
Yes
The RERA Provisions shall be incorporated in the Draft Agreement.
JINDAL SMART CITY, SECTOR 34, SONIPAT, HARYANA
95.2625
0
623
0
213
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
19319.32
0
13664.84
Cost of the apartments
0
0
0
Cost of the infrastructure
7988.00
0
3839.52
Others costs
11331.316
0
9825.32
16264.93572 Lakhs
34245.77730 Lakhs
5000.00 Lakhs
3552.00 Lakhs
No
15-06-2028
15-06-2028
JINDAL GLOBAL CITY - PHASE V
43.528
0
246
0
110
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6954.12
0
9410.12
Cost of the apartments
0
0
0
Cost of the infrastructure
2431.62
0
4001.50
Others costs
4522.50
0
5408.62
17946.72481 Lakhs
0.20513 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2024
13-04-2026
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILE FLOORING -SOMANI OR SIMILAR
2
WALL FINISHING DETAILS
JSW OR SIMILAR
3
KITCHEN DETAILS
WORKING COUNTER WITH MODULAR BOX
-GRANITE WITH PLY BOX