UGF 11, UPPER GROUND FLOOR, BLOCK B, DIVINE CITY CENTRE, PIPLI ROAD, KURUKSHETRA, HARYANA - 136118
9991489000 (Number Shared by Promoter in Public)
decentinfraretailllp@gmail.com
ACB1857
AAVFD1997J
THE FLOWER CITY PHASE II
VILLAGE SARASWATI KHERA, SECTOR 2
PEHOWA
KURUKSHETRA
9991489000 (Number Shared by Promoter in Public)
decentinfraretailllp@gmail.com
NITIN
9991489000 (Number Shared by Promoter in Public)
decenntinfraretailllp@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
953081
12-11-2025
268500
KOTAK MAHINDRA BANK
HRERA Panchkula
11.637 (Acre)
1.00 FOR RESIDENTIAL PLOTTED AND 1.50 FOR COMMERCIAL
1.00
11.637 (Acre)
LICENSE NO 205 OF 2025 DATED 15.10.2025 VALID UPTO 14.10.2030
Yes
3399.87 Lakhs
1743.30 Lakhs
0 Lakhs
1491.20 Lakhs
165.37 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
ANY OTHER
1.359
2
COMMERCIAL AREA
0.241
3
PLOTS TO BE SOLD
6.521
4
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
5
CONSTRUCTION OF ROADS
1.474
6
PAVEMENTS
0
7
PARKS AND PLAYGROUNDS
0.879
8
GREEN BELTS
0
9
VEHICLE PARKINGS
0
10
ELECTRICITY SUB-STATION
0
11
CLUB HOUSE
0
12
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
13
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
1.163
Total
11.637
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
UHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
206.71
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
137.63
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
74.41
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
255.00
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
127.01
AS PER PROJECT REPORT
6
STREET LIGHTING
37.04
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
20.00
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
147.00
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
60.00
AS PER PROJECT REPORT
15
STP
50.00
AS PER PROJECT REPORT
16
ELECTRICAL SUB STATION
170.00
AS PER PROJECT REPORT
17
RAIN WATER HARVESTING
45.00
AS PER PROJECT REPORT
18
MAINTENANCE AS PER HSVP NORMS
161.41
AS PER PROJECT REPORT
16-10-2025 (date)
NA (date)
01-12-2025
14-10-2030
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
144.846
14
2
126.655
1
3
149.392
34
4
148.917
16
5
149.989
30
6
143.519
20
7
147.523
7
8
148.715
6
9
149.940
24
10
139.806
9
11
136.764
12
12
140.364
7
Total
180
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.30
Water Supply System
6.90
Sewerage treatment & garbage disposal
6.35
Electricity Supply System
21.25
Storm Water Drainage
3.75
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.30
10.30
10.30
10.30
Water Supply System
6.90
6.90
6.90
6.90
Sewerage treatment & garbage disposal
6.35
6.35
6.35
6.35
Electricity Supply System
21.25
21.25
21.25
21.25
Storm Water Drainage
3.75
3.75
3.75
3.75
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.30
10.30
10.30
10.30
Water Supply System
6.90
6.90
6.90
6.90
Sewerage treatment & garbage disposal
6.35
6.35
6.35
6.35
Electricity Supply System
21.252
21.25
21.25
21.25
Storm Water Drainage
3.75
3.75
3.75
3.75
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.30
10.30
10.30
10.30
Water Supply System
6.90
6.90
6.90
6.90
Sewerage treatment & garbage disposal
6.35
6.35
6.35
6.35
Electricity Supply System
21.25
21.25
21.25
21.25
Storm Water Drainage
3.75
3.75
3.75
3.75
Parks and Playgrounds
0
0
0
14.70
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
3.70
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.30
10.30
10.30
10.30
Water Supply System
6.90
6.90
6.90
6.90
Sewerage treatment & garbage disposal
6.35
6.35
6.35
6.35
Electricity Supply System
21.25
21.25
21.25
21.25
Storm Water Drainage
3.75
3.75
3.75
3.75
Parks and Playgrounds
14.70
14.70
14.70
14.70
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
3.70
3.70
3.70
3.70
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.30
10.30
10.30
Water Supply System
6.90
6.90
6.90
Sewerage treatment & garbage disposal
6.35
6.35
6.35
Electricity Supply System
21.25
21.25
21.25
Storm Water Drainage
3.70
3.75
3.75
Parks and Playgrounds
14.70
14.70
14.70
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
STREET LIGHTING
3.70
3.70
3.70
Yes
No
HDFC BANK LTD PEHOWA BRANCH KURUKSHETRA
99999811198092
HDFC0000797
136240128
000797
YASH JAIN R/O D 163 NEW FRIENDS COLONY NEW DELHI AND VINEET CHHABRA R/O TILAK COLONY PEHOWA KURUKSHETRA AND JAGRIT LUTHRA R/O C 165 PUSHPANJALI ENCALVE PITAMPURA NEW DELHI AND SARTHAK BATHLA R/O H NO 65 FRIENDS COLONY PANIPAT AND VARUN GUPTA R/O H NO 241 STATE BANK COLONY KURUKSHETRA
UPLOADED
Yes
No
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 205 OF 2025
ALREADY BEEN OBTAINED
16-10-2025
Yes
Yes
ANNEXED AS PER THE RERA ACT, 2016 AND HRERA RULES, 2017
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NOT APPLICABLE
2
WALL FINISHING DETAILS
NOT APPLICABLE
3
KITCHEN DETAILS
NOT APPLICABLE
4
BATHROOM FITTINGS
NOT APPLICABLE
5
WOOD WORK ETC
NOT APPLICABLE
6
DOORS AND WINDOS FRAMES
NOT APPLICABLE
7
GLASS WORK
NOT APPLICABLE
8
ELECTRIC FITTINGS
NOT APPLICABLE
9
CONDUCTING AND WIRING DETAILS
NOT APPLICABLE
10
CUPBOARD DETAILS
NOT APPLICABLE
11
WATER STORAGE
NOT APPLICABLE
12
LIFT DETAILS
NOT APPLICABLE
13
EXTERNAL GLAZINGS
NOT APPLICABLE
13.1
WINDOWS/GLAZINGS
NOT APPLICABLE
14
DOORS
NOT APPLICABLE
14.1
MAIN DOORS
NOT APPLICABLE
14.2
INTERNAL DOORS
NOT APPLICABLE
15
AIR CONDITIONING
NOT APPLICABLE
16
ELECTRICAL FITTINGS
NOT APPLICABLE
17
CNG PIPE LINE
NOT APPLICABLE
18
PROVISION OF WIFI AND BROADBAND FACILITY
NOT APPLICABLE
19
EXTERNAL FINISHING/COLOUR SCHEME
NOT APPLICABLE
20
INTERNAL FINISHING
NOT APPLICABLE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NOT APPLICABLE
1 . 2
WALLS
NOT APPLICABLE
1 . 3
CEILING
NOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NOT APPLICABLE
2 . 2
WALLS
NOT APPLICABLE
2 . 3
CEILING
NOT APPLICABLE
2 . 4
MODULAR WARDROBES
NOT APPLICABLE
3 . MASTER TOILET
3 . 1
FLOOR
NOT APPLICABLE
3 . 2
WALLS
NOT APPLICABLE
3 . 3
CEILING
NOT APPLICABLE
3 . 4
COUNTERS
NOT APPLICABLE
3 . 5
SANITARY WARE/CP FITTINGS
NOT APPLICABLE
3 . 6
FITTING/FIXTURES
NOT APPLICABLE
4 . BED ROOMS
4 . 1
FLOOR
NOT APPLICABLE
4 . 2
WALLS
NOT APPLICABLE
4 . 3
CEILING
NOT APPLICABLE
4 . 4
WARDROBES
NOT APPLICABLE
5 . TOILET
5 . 1
FLOOR
NOT APPLICABLE
5 . 2
WALLS
NOT APPLICABLE
5 . 3
CEILING
NOT APPLICABLE
5 . 4
COUNTERS
NOT APPLICABLE
5 . 5
SANITARY WARE/CP FITTINGS
NOT APPLICABLE
5 . 6
FIXTURES
NOT APPLICABLE
6 . KITCHEN
6 . 1
FLOOR
NOT APPLICABLE
6 . 2
WALLS
NOT APPLICABLE
6 . 3
CEILING
NOT APPLICABLE
6 . 4
COUNTERS
NOT APPLICABLE
6 . 5
FIXTURES
NOT APPLICABLE
6 . 6
KITCHEN APPLIANCES
NOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NOT APPLICABLE
7 . 2
WALLS & CEILING
NOT APPLICABLE
7 . 3
TOILET
NOT APPLICABLE
7 . 4
BALCONY
NOT APPLICABLE
8 . SIT-OUTS
8 . 1
FLOOR
NOT APPLICABLE
8 . 2
WALLS & CEILING
NOT APPLICABLE
8 . 3
RAILINGS
NOT APPLICABLE
8 . 4
FIXTURES
NOT APPLICABLE
Sr. No.
Document Description
Date of Document Upload
View Document
1
IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN