HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2095-2025
Submission Date : 24-10-2025 12:31:16 PM
Applicant Type : Firm
Project Type: NEW


LION INFRADEVELOPERS LLP
SECOND FLOOR,TOWER B, UNIT NO TSF-01 TO TSF 08, OCUS TECHNOPOLIES, GOLF COURSE ROAD, SECTOR-54, GURGAON, HARYANA, 122002
01244047134
9311487848 (Number Shared by Promoter in Public)
legal@lioninfra.com
AAC1940
AAFFL2924B













LID NIVASA
GREEN VALLEY - 2, SECTOR-6, SOHNA
SOHNA
GURUGRAM
01244047134
9311487848 (Number Shared by Promoter in Public)
legal@lioninfra.com
RAHUL
01244047134
9811784082 (Number Shared by Promoter in Public)
civil@lioninfra.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
187903910-10-2025130485KOTAK MAHINDRA BANK LIMITEDHRERA Gurugram
287604010-10-2025130485KOTAK MAHINDRA BANK LIMITEDHRERA Gurugram
394932815-11-2025213995KOTAK MAHINDRA BANK LIMITEDHRERA Gurugram







1.2213 (Acre)
2.64
2.64
12.50 (Acre)
188 OF 2023 dated 15-09-2023
No
Address     PLOT NO. 10, 3RD FLOOR, LOCAL SHOPPING COMPLEX, B-1, VASANT KUNJ, DELHI-110070
Address     VILLAGE DAMDAMA, TEHSIL SOHNA, GURGAON
Address     FRAM-55, RAOD-2, SILVER OAK MARG, GHITORNI, GADAIPUR, SOUTH DELHI 110030
Address     FARM NO. 30, SILVER OAK FARM, GHITORNI, NEW DELHI- 110030
Annexure-B- COLLABORATOR
AGREEMENTS WERE MADE BEFORE THE GRANT OF LICENSE
Yes
LION INFRADEVELOPERS LLP(COLLABORATOR/DEVELOPER) HAS ENTERED INTO COLLABORATION AGREEMENT WITH NITIKA PROPMART PVT. LTD, SMT. SUKHPALLI W/O SH. SATBIR SINGH, SH. JATIN LOHIA S /O SH. RAVINDER SINGH LOHIA, SH. M.R. LOHIA S /O SH. PHOOL SINGH LOHIA AND SMT. SATYAWATI W /O SH. M.R. LOHIA FOR THE PURPOSE OF DEVELOPING A RESIDENT PLOTTED COLONY IN THE REVENUE ESTATE OF VILLAGE SOHNA, SECTOR - 6, SOHNA, DIST. GURUGRAM. ALL THE AGREEMENTS ARE REGISTERED WITH THE CONCERNED REVENUE DEPARTMENT. THE IMPORTANT CLAUSES OF THE SAID COLLABORATION AGREEMENTS ARE: 1. COLLABORATION AGREEMENT OF LION INFRADEVELOPERS WITH NITIKA PROPMART PRIVATE LIMITED AND JATIN LOHIA - CLAUSE NO. 1,2 AND 10. 2. COLLABORATION AGREEMENT OF LION INFRADEVELOPERS LLP WITH M.R LOHIA - 1,2 AND 10 3. ASSIGNMENT AGREEMENT OF LIONINFRADEVELOPERS LLP WITH SUKHPALI (CONFIRMING PARTY) AND NITIKA PROPMART PRIVATE LIMITED- CLAUSE NO. 2,3,5 AND 8
No
Yes
Yes







12707.46 Lakhs
331.80 Lakhs
7829.88 Lakhs
0 Lakhs
4545.78 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 4942.50
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total4942.5




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSN/ANo
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0YET TO BE PREPARED
2WATER SUPPLY SYSTEM0YET TO BE PREPARED
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
28-08-2025 (date)
01-11-2025
30-09-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings11040.2416040





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments212.84
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments437.04
Shops0
Plots0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments437.04437.04437.04303.51
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments174.82174.82174.821002.78
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments874.091048.911048.911048.91
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1048.911037.061122.99961.50
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments437.0487.41199.99
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2030)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
ICICI BANK VIPUL PLAZA SUNCITY SEC 54 GURUGRAM-122002
777705612603
ICIC0000399
110229060
0399
Mr. Jatin Lohia, Designated Partner, Lohia Farm House No. 30, Road No. 1, Silver Oak Farms, Ghitorni, Gadaipur, Delhi - 110030
Attached











Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE FROM COUNTRY AND TOWN PLANING, CHANDIGARHALREADY BEEN OBTAINED15-09-2023
II. ZONING PLAN APPROVALALREADY BEEN OBTAINED08-12-2023
III. BUILDING PLANALREADY BEEN OBTAINED28-08-2025
IV. SERVICE PLANS & ESTIMATESALREADY BEEN OBTAINED02-02-2024








Yes


Yes


As per RERA norms







MALL STREET SECTOR 35 SOHNA
0.468017
109
0
80
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1698.8301510.85
Cost of the apartments767.160767.17
Cost of the infrastructure22.38021.39
Others costs909.290722.29


965.16 Lakhs
1149.96 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2024
05-11-2024




GREEN VALLEY - 2, SECTOR 6
12.50
0
224
0
132
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
5612.3204136.68
Cost of the apartments000
Cost of the infrastructure1120.2001479.70
Others costs4492.1202656.98


8531.72 Lakhs
3820.81 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2028
30-06-2028




GREEN VALLEY, SECTOR-35
12.41875
0
225
0
175
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4822.8603102.77
Cost of the apartments931.9900
Cost of the infrastructure516.880808.90
Others costs3406.9902293.87


1557.68 Lakhs
0.0 Lakhs
0 Lakhs
0 Lakhs
No
19-08-2024
19-08-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED AND CERAMIC TILES
2WALL FINISHING DETAILSOBD
3KITCHEN DETAILSISI MARKED
4BATHROOM FITTINGSISI MARKED
5WOOD WORK ETC HARD WOOD
6DOORS AND WINDOS FRAMESWOODEN, ALUMINUM UPVC
7GLASS WORK ISI MARKED
8ELECTRIC FITTINGSISI MARKED
9CONDUCTING AND WIRING DETAILSISI MARKED
10CUPBOARD DETAILS NO
11WATER STORAGERCC/PVC
12LIFT DETAILS ISI MARKED
13EXTERNAL GLAZINGS-
13.1WINDOWS/GLAZINGSALUMINUM AND PVC
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGNO
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINE NO
18PROVISION OF WIFI AND BROADBAND FACILITY NO
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGTEXTURE PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSOBD
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOOR CERAMIC TILES
3 . 2 WALLS CERAMIC TILES
3 . 3 CEILINGGRID
3 . 4 COUNTERSNO
3 . 5 SANITARY WARE/CP FITTINGSISI MARKED
3 . 6 FITTING/FIXTURESISI MARKED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOBD
4 . 3 CEILINGOBD
4 . 4 WARDROBESNO
5 . TOILET
5 . 1 FLOOR VETRIFIED TILES
5 . 2 WALLSOBD
5 . 3 CEILINGOBD
5 . 4 COUNTERSNO
5 . 5 SANITARY WARE/CP FITTINGS ISI MARKED
5 . 6 FIXTURES ISI MARKED
6 . KITCHEN
6 . 1 FLOOR VETRIFIED TILES
6 . 2 WALLSOBD
6 . 3 CEILINGOBD
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURES ISI MARKED
6 . 6 KITCHEN APPLIANCESNO
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNO
7 . 2 WALLS & CEILINGNO
7 . 3 TOILETNO
7 . 4 BALCONYNO
8 . SIT-OUTS
8 . 1 FLOORNO
8 . 2 WALLS & CEILINGNO
8 . 3 RAILINGSNO
8 . 4 FIXTURESNO












Sr. No.Document DescriptionDate of Document UploadView Document
1 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 15-10-2025 View Document
2 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 15-10-2025 View Document
3 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 15-10-2025 View Document
4 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 15-10-2025 View Document
5 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 15-10-2025 View Document
6 APPROVED BUILDING PLANS 15-10-2025 ------
7 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 15-10-2025 View Document
8 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 15-10-2025 View Document
9 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 15-10-2025 View Document
10 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 15-10-2025 View Document
11 SPE STORM WATER 11-12-2025 ------
12 A-02 11-12-2025 ------
13 BANK UNDERTAKING 11-12-2025 ------
14 SPE SEWER 11-12-2025 ------
15 NO PRIOR SALE AFFIDAVIT 11-12-2025 ------
16 NEC-LID NIVASA 11-12-2025 ------
17 AFFIDAVIT MAST RAM LOHIA AND SATYAWATI 11-12-2025 ------
18 A-12A 11-12-2025 ------
19 A-17 11-12-2025 ------
20 ASSIGNMENT DEED-LION INFRADEVELOPERS LLP AND NITIKA PROPMART PVT LTD. 11-12-2025 ------
21 A-22 11-12-2025 ------
22 CERT- FINANCIAL AND INVENTORY 11-12-2025 ------
23 A-41 11-12-2025 ------
24 B-158 11-12-2025 ------
25 AKS SIJRA 11-12-2025 ------
26 A-25 11-12-2025 ------
27 A-11 11-12-2025 ------
28 A-20 11-12-2025 ------
29 DEMARCATION PLAN 11-12-2025 View Document
30 AFFIDAVIT - LAKSHAY LOHIA-NITIKA PROPMART 11-12-2025 ------
31 A-14 11-12-2025 ------
32 A-09 11-12-2025 ------
33 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 11-12-2025 View Document
34 LC IV & LC IV-B _BILATERALS AGREEMENTS,_LION INFRADEVELOPERS LLP,_DDJAY, SECTOR 6, SOHNA, GGN 11-12-2025 ------
35 AFFIDAVIT-SUKHPALLI 11-12-2025 ------
36 A-05 11-12-2025 ------
37 A-06 11-12-2025 ------
38 A-07 11-12-2025 ------
39 A-10 11-12-2025 ------
40 A-12 11-12-2025 ------
41 A-15 11-12-2025 ------
42 A-24 11-12-2025 ------
43 A-42 11-12-2025 ------
44 B-159 11-12-2025 ------
45 ZONING PLAN 11-12-2025 View Document
46 SPE WATER SUPPLY 11-12-2025 ------
47 SPE ROAD 11-12-2025 ------
48 SPE FLUSHING WATER 11-12-2025 ------
49 LOI_LC-5105-JE(DS)2023-21610-DATED-04.07.2023 11-12-2025 ------
50 JAMABANDI AND INTKAL 11-12-2025 ------
51 ASSIGNMENT DEED-LION INFRADEVELOPERS LLP AND JATIN LOHIA 11-12-2025 ------
52 ELECTRICAL ASSURANCE -DHBVN 11-12-2025 ------
53 AFFIDAVIT-JATIN LOHIA 11-12-2025 ------
54 APPROVED ASSURANCE OF CONSTRUCTION WATER_07.03.2024 11-12-2025 ------
55 A-01 11-12-2025 ------
56 A-03 11-12-2025 ------
57 A-04 11-12-2025 ------
58 A-08 11-12-2025 ------
59 A-16 11-12-2025 ------
60 A-18 11-12-2025 ------
61 B-167 11-12-2025 ------
62 B-166 11-12-2025 ------
63 ALLOTMENT LETTER 11-12-2025 ------
64 A-19 11-12-2025 ------
65 A-21 11-12-2025 ------
66 A-23 11-12-2025 ------
67 A-38 11-12-2025 ------
68 A-39 11-12-2025 ------
69 A-40 11-12-2025 ------
70 B-165 11-12-2025 ------
71 B-164 11-12-2025 ------
72 B-163 11-12-2025 ------
73 B-162 11-12-2025 ------
74 B-161 11-12-2025 ------
75 B-160 11-12-2025 ------
76 AGREEMENT FOR SALE 11-12-2025 ------