HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2085-2025
Submission Date : 03-11-2025 12:29:23 PM
Applicant Type : Company
Project Type: NEW




AIPL BHARAT INFRASTRUCTURE PRIVATE LIMITED
AIPL BUSINESS CLUB, 5TH FLOOR, GOLF COURSE EXTENSION ROAD, SECTOR 62, GURUGRAM, HARYANA- 122101
01246077777
9999337265 (Number Shared by Promoter in Public)
rera-haryana@aipl.com
https://aipl.com
XXXX609L
U68100HR2024PTC124408
 
 


 
 


 
 


 
 


 
 







RIVIERA AT AIPL LAKE CITY
VILLAGE DAULTABAD SECTOR- 103
KADIPUR ST
GURUGRAM
01246077777
9999337265 (Number Shared by Promoter in Public)
rera-haryana@aipl.com
MR MAHIR PRUTHY
01246077777
9999337265 (Number Shared by Promoter in Public)
rera-haryana@aipl.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1198430-10-2025620863HDFC BANK LTD.HRERA Gurugram
2198530-10-20251955539HDFC BANK LTD.HRERA Gurugram
3200117-11-2025141346HDFC BANK LTD.HRERA Gurugram







5.1375 (Acre)
315
315
5.1375 (Acre)
62 of 2025 Dated 01.05.2025
No
Address     AIPL BUSINESS CLUB, 5TH FLOOR, GOLF COURSE EXTENSION ROAD, SECTOR 62, GURUGRAM- 122101
Address     AIPL BUSINESS CLUB, 5TH FLOOR, GOLF COURSE EXTENSION ROAD, SECTOR 62, GURUGRAM- 122101
Annexure-B- ANNEXURE-B- AA A COLLABORATOR
COLLABORATION AGREEMENT DATED 17.01.2025
Yes
AS PER THE ATTACHED COLLABORATION AGREEMENT
No
Yes
Yes







98725.52 Lakhs
18372.85 Lakhs
45654.57 Lakhs
1781.07 Lakhs
32917.03 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 1.0639
3CONSTRUCTION OF ROADS 1.152
4PAVEMENTS 0.236
5PARKS AND PLAYGROUNDS 0.785
6GREEN BELTS 0.239
7VEHICLE PARKINGS 0.18
8ELECTRICITY SUB-STATION 0.102
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 1.3796
Total5.1375




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHVBNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS827.76AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM20.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE30.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM66.75AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL30.00AS PER PROJECT REPORT
6STREET LIGHTING50.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING66.50AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS354.76AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM20.00AS PER PROJECT REPORT
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15STP100.00AS PER PROJECT REPORT
16UNDERGROUND WATER TANK75.00AS PER PROJECT REPORT
17RAIN WATER HARVESTING30.00AS PER PROJECT REPORT
18ELECTRICAL SUB STATION110.30AS PER PROJECT REPORT


03-11-2025 (date)
03-11-2025 (date)
01-01-2026
30-06-2033
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings170.94830
Apartment/Shops/Other Buildings149.5730
Apartment/Shops/Other Buildings146.60830
Apartment/Shops/Other Buildings137.87350
Apartment/Shops/Other Buildings132.02450
Apartment/Shops/Other Buildings125.1430
Apartment/Shops/Other Buildings119.75860
Apartment/Shops/Other Buildings110.8360
Apartment/Shops/Other Buildings17.73610
Apartment/Shops/Other Buildings11.9670





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments214.61
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments899.21997.3627111146.041197.36
Shops0.792.643.962.64
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1246.031296.041496.661447.45
Shops3.963.963.352.55
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1593.131742.781892.782043.05
Shops6.877.227.226.96
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1993.312143.572193.132293.13
Shops6.696.436.876.87
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2496.212395.162292.602090.84
Shops3.794.847.409.16
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1990.841838.821488.201235.91
Shops9.1611.1811.8014.09
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1088.731090.32887.33747.87
Shops11.279.692.642.12
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Rain water harvesting0
Street Lighting0
Security and fire fighting0
Renewable energy system0
STP0
Underground water tank0
Electrical sub station0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.6926.6327.2029.14
Water Supply System2.002.002.002.00
Sewerage treatment & garbage disposal3.003.003.003.00
Electricity Supply System0000
Storm Water Drainage3.003.003.003.00
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank3.753.757.507.50
Rainwater Harvesting1.501.503.003.00

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements31.0834.9642.7341.39
Water Supply System2.002.002.002.40
Sewerage treatment & garbage disposal3.003.003.003.00
Electricity Supply System0000
Storm Water Drainage3.003.003.003.00
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank7.507.507.507.50
Rainwater Harvesting3.003.003.003.00

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements41.3949.6757.9457.94
Water Supply System2.001.6000
Sewerage treatment & garbage disposal3.003.0000
Electricity Supply System0000
Storm Water Drainage3.003.0000
Parks and Playgrounds0007.10
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and fire fighting001.332.00
Electrical sub station4.323.318.177.29
Rainwater Harvesting2.402.101.801.50
Underground Water Tank6.005.254.503.75

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements57.9449.6741.3941.39
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0003.34
Storm Water Drainage0000
Parks and Playgrounds7.1017.7424.8326.61
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank2.250.7500
Rainwater Harvesting0.900.3000
Street Lighting02.502.502.50
Electrical sub station6.127.188.357.13
Security and fire fighting3.333.333.333.33
STP02.005.005.00

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements45.5341.3924.838.28
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System3.343.343.346.68
Storm Water Drainage0000
Parks and Playgrounds29.8324.8335.4839.02
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical sub station5.525.785.817.72
Street Lighting2.502.502.502.50
Security and fire fighting5.325.325.325.32
Renewable Energy System002.002.00
STP5.0010.0010.0010.00

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.288.288.288.28
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System6.686.686.686.68
Storm Water Drainage0000
Parks and Playgrounds37.2527.6915.447.10
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and fire fighting5.326.655.324.66
Electrical sub station5.605.525.524.82
Renewable Energy System2.002.002.002.00
STP10.0010.0010.0010.00
Street Lighting2.505.005.005.00

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.284.144.142.93
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System6.686.683.343.34
Storm Water Drainage0000
Parks and Playgrounds8.878.8719.7717.24
Clubhouse/community centres0000
Shopping area0000
Other0000
Renewable Energy System2.002.002.002.00
Electrical sub station3.553.812.582.21
Street Lighting5.005.005.000
STP5.005.002.001.00
Security and fire fighting3.333.3300












Yes
No
HDFC BANK LTD., SECTOR-56, GURUGRAM
99999000884646
HDFC0003871
110240358
003871
MR DALJEET SINGH, MR HARINDER SINGH AND MR GURDEEP SINGH
No Default has been made











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


No
No
No
No
No
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED29-05-2025
II. LICENCEALREADY BEEN OBTAINED01-05-2025








Yes


Yes


As per provided BBA













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEMARBLE FOR LIVING AREA , LAMINATED WOODEN FLOORING FOR BEDROOM & TILES FOR KITCHEN & BALCONY AREA.
2WALL FINISHING DETAILSACRYLIC EMULSION PAINT
3KITCHEN DETAILSTILES FOR FLOORING, TILES UPTO 2' ABOVE COUNTER & ACRYLIC EMULSION PAINT ON REMAINING AREA. GRANITE / MARBLE / ENGINEERED STONE FOR COUNTER
4BATHROOM FITTINGSWASH BASIN, FLOOR-MOUNTED / WALL-HUNG WCS
5WOOD WORK ETC LAMINATED / VENEERED FLUSH DOOR
6DOORS AND WINDOS FRAMESPOLISHED FRAME WITH PAINTED / LAMINATED / VENEERED FLUSH DOOR & UPVC / ALUMINIUM FRAMES
7GLASS WORKGLASS FOR EXTERNAL WINDOWS AND DOORS
8ELECTRIC FITTINGSMODULAR SWITCHES
9CONDUCTING AND WIRING DETAILSCOPPER WIRING
10CUPBOARD DETAILSNA
11WATER STORAGERAINWATER HARVESTING & TREATED WATER FROM STP FOR FLUSHING AND HORTICULTURE
12LIFT DETAILSNA
13EXTERNAL GLAZINGSUPVC / ALUMINIUM FRAMES WITH GLASS
13.1WINDOWS/GLAZINGSUPVC / ALUMINIUM FRAMES WITH GLASS
14DOORSPOLISHED FRAME WITH PAINTED / LAMINATED / VENEERED FLUSH DOOR
14.1MAIN DOORSPOLISHED FRAME WITH PAINTED / LAMINATED / VENEERED FLUSH DOOR
14.2INTERNAL DOORSPOLISHED FRAME WITH PAINTED / LAMINATED / VENEERED FLUSH DOOR
15AIR CONDITIONINGVRF
16ELECTRICAL FITTINGSMODULAR SWITCHES
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR GRADE TEXTURE PAINT
20INTERNAL FINISHINGACRYLIC EMULSION PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORMARBLE
1 . 2 WALLSACRYLIC EMULSION PAINT
1 . 3 CEILINGACRYLIC EMULSION PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSACRYLIC EMULSION PAINT
2 . 3 CEILINGACRYLIC EMULSION PAINT
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORMARBLE / TILES
3 . 2 WALLSTILES /ACRYLIC EMULSION PAINT
3 . 3 CEILINGACRYLIC EMULSION PAINT
3 . 4 COUNTERSMARBLE / GRANITE / ENGINEERED STONE
3 . 5 SANITARY WARE/CP FITTINGSWASH BASIN, FLOOR-MOUNTED / WALL-HUNG WCS
3 . 6 FITTING/FIXTURESMODULAR SWITCHES
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION PAINT
4 . 3 CEILINGACRYLIC EMULSION PAINT
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORTILES
5 . 2 WALLSTILES / ACRYLIC EMULSION PAINT
5 . 3 CEILINGACRYLIC EMULSION PAINT
5 . 4 COUNTERSMARBLE / GRANITE / ENGINEERED STONE
5 . 5 SANITARY WARE/CP FITTINGSWASH BASIN, FLOOR-MOUNTED / WALL-HUNG WCS
5 . 6 FIXTURESMODULAR SWITCHES
6 . KITCHEN
6 . 1 FLOORTILES
6 . 2 WALLSTILES UP TO 2' ABOVE COUNTER; BALANCE AREA IN ACRYLIC EMULSION PAINT
6 . 3 CEILINGACRYLIC EMULSION PAINT
6 . 4 COUNTERSGRANITE / MARBLE / ENGINEERED STONE
6 . 5 FIXTURESCP FITTINGS, SS SINK
6 . 6 KITCHEN APPLIANCESMODULAR KITCHEN WITH HOB, CHIMNEY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGACRYLIC PAINT(UTILITY ROOM)
7 . 3 TOILETTILES
7 . 4 BALCONYEXTERIOR GRADE PAINT
8 . SIT-OUTS
8 . 1 FLOORTILES
8 . 2 WALLS & CEILINGACRYLIC PAINT
8 . 3 RAILINGSMS/ GLASS RAILING / PARAPET WALL
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 ELECTRICAL LOAD AVAILABILITY 08-12-2025 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 08-12-2025 View Document
3 DRAFT BBA 08-12-2025 View Document
4 COMBINED ELEVATION-A TOWER-01&02; 08-12-2025 View Document
5 PROJECT REPORT 08-12-2025 View Document
6 ASSURANCE OF STORM WATER 08-12-2025 View Document
7 AIRPORT HEIGHT NOC 08-12-2025 View Document
8 CONSTRUCTION WATER NOC 08-12-2025 View Document
9 PROMOTER AFFIDAVIT FOR 4(2)(L)(D) 08-12-2025 View Document
10 FIRST FLOOR PLAN TOWER 01 & 02 08-12-2025 View Document
11 LITIGATION DETAIL 08-12-2025 View Document
12 AKS SHAJRA 08-12-2025 View Document
13 PROMOTER NET WORTH CERTIFICATE 08-12-2025 View Document
14 WATER SUPPLY SLD EWS 08-12-2025 View Document
15 BASEMENT-02 08-12-2025 View Document
16 ZONING PLAN 08-12-2025 View Document
17 DEMAND DRAFT 08-12-2025 View Document
18 NON-ENCUMBRANCE CERTIFICATE 08-12-2025 View Document
19 ELEVATION C TOWER 01 08-12-2025 View Document
20 TOILET DETAILS TOWER 01 &02; 08-12-2025 View Document
21 BASEMENT -01 08-12-2025 View Document
22 ELEVATION-A TOWER 01 08-12-2025 View Document
23 DEMARCATION PLAN 08-12-2025 View Document
24 BASEMENT -02 AREA CALCULATION 08-12-2025 View Document
25 DETAILS OF ASSETS MORTGAGED 08-12-2025 View Document
26 SPE FIRE FIGHTING LAYOUT 08-12-2025 View Document
27 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 08-12-2025 View Document
28 FIRE SCHEME APPLIED 08-12-2025 View Document
29 CA CERTIFICATE FOR FINANCIAL & INVENTORY DETAILS 08-12-2025 View Document
30 ELEVATION D TOWER 01 08-12-2025 View Document
31 TERRACE & OHT LIFT MACHINE ROOM FLLOR PLAN TOWER-01 &02; 08-12-2025 View Document
32 BR FOR BANK AUTHORIZING 08-12-2025 View Document
33 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 08-12-2025 View Document
34 ROC STATEMENT 08-12-2025 View Document
35 UNDERTAKING ROAD ACCESS 08-12-2025 View Document
36 ELEVATION C&D TOWER 02 08-12-2025 View Document
37 SECTION BB TOWER 01 08-12-2025 View Document
38 WATER SUPPLY SLD TOWER 01&02; 08-12-2025 View Document
39 BR-III 08-12-2025 View Document
40 ELEVATION A&B TOWER-02 08-12-2025 View Document
41 JAMABANDI 08-12-2025 View Document
42 NOC FROM LENDER 08-12-2025 View Document
43 GROUND COVERAGE TOWER 01 & 02 08-12-2025 View Document
44 TYPICAL(39THTO43TH),(2ND TO 17TH,19TH TO 26TH, 29TH TO 35TH TO 28TH),REFUGE FLOOR(18TH,27TH&36TH;) 08-12-2025 View Document
45 ASSURANCE FOR SEWERGE CONNECTION 08-12-2025 View Document
46 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 08-12-2025 View Document
47 DRAFT CONVEYANCE DEED 08-12-2025 View Document
48 BIPARTITE AGREEMENT 08-12-2025 View Document
49 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 08-12-2025 View Document
50 LAND TITLE SEARCH REPORT 08-12-2025 View Document
51 SERVICE ESTIMATES BOOKLET 08-12-2025 View Document
52 ENVIRONMENTAL CLEARANCE APPLIED 08-12-2025 View Document
53 LC-IV 08-12-2025 View Document
54 UNDERTAKING FOR NON-APPLICABILITY OF POWERLINE SHIFTING, FOREST LAND DIVERSION, NCZ AND WILDLIFE 08-12-2025 View Document
55 SECTION AA TOWER 01 08-12-2025 View Document
56 BASEMENT -01 AREA CALCULATION 08-12-2025 View Document
57 SPE FLUSHING & IRRIGATION LAYOUT 08-12-2025 View Document
58 ELEVATION B TOWER 01 08-12-2025 View Document
59 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 08-12-2025 View Document
60 FLOOR PLAN (43RD FLOOR) TOWER 01& 02 08-12-2025 View Document
61 MUMTY MACHIN ROOM ROOF PALM TOWER-01 &02; 08-12-2025 View Document
62 SPE ROAD LAYOUT 08-12-2025 View Document
63 TYPICAL 2ND TO17TH,19TH TO 26TH,28THTO35TH,37THTO42ND)&REFUGE;(18TH,27TH& 36TH)FLOOR TOWER-01 08-12-2025 View Document
64 FOREST NOC 08-12-2025 View Document
65 SPE DOMESTIC WATER SUPPLY LAYOUT 08-12-2025 View Document
66 SPE STORM WATER DRAINAGE LAYOUT 08-12-2025 View Document
67 BANK UNDERTAKING 08-12-2025 View Document
68 SERVICE PLAN ESTIMATE APPLIED 08-12-2025 View Document
69 MUTATION COPY 08-12-2025 View Document
70 COMBINED SECTION TOWER 01&02; 08-12-2025 View Document
71 SECTION A&B TOWER 02 08-12-2025 View Document
72 COMPLAINT REPRESENTATION 08-12-2025 View Document
73 TREE CUTTING PERMISSION 08-12-2025 View Document
74 GROUND STILT FLOOR PLAN & AREA CALCULATION TOWER-01 & 02 08-12-2025 View Document
75 SANCTION LETTER 08-12-2025 View Document
76 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 08-12-2025 View Document
77 PERT CHART 08-12-2025 View Document
78 COLLABORATION AGREEMENT 08-12-2025 View Document
79 SALE DEED 08-12-2025 View Document
80 GROUND FLOOR,TYPICAL(1ST TO5TH),6TH FLOOR,TERRACE,MUMTY.OTH PLAN& AREA CALCULATION&SECTION;&ELEVATION; 08-12-2025 View Document
81 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 08-12-2025 View Document
82 SUPERIMPOSED DEMARCATION 08-12-2025 View Document
83 SPE SEWERAGE LAYOUT 08-12-2025 View Document
84 ASSURANCE OF WATER SUPPLY 08-12-2025 View Document
85 BR AIPL BHARAT INFRASTRUCTURE 08-12-2025 View Document
86 LAND COST CLARIFICATION 08-12-2025 View Document
87 REPAYMENT SCHEDULE 08-12-2025 View Document
88 LOI 08-12-2025 View Document
89 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 08-12-2025 View Document
90 UNDERTAKING FOR MINING 08-12-2025 View Document
91 DRAFT ALLOTMENT LETTER 09-12-2025 View Document
92 DRAFT APPLICATION FORM 09-12-2025 View Document