HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2083-2025
Submission Date : 10-10-2025 02:30:10 PM
Applicant Type : Company
Project Type: NEW




SIGNATTUREGLOBAL HOMES LIMITED
UNIT NO.101,GROUND FLOOR, TOWER-A, SIGNATURE TOWER SOUTH CITY-1, GURUGRAM, HARAYNA-122001
911244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
Https://www.signatureglobal.in
XXXX888R
U70100DL2008PLC176641
 
 


 
 


 
 


 
 







SIGNATURE GLOBAL SARVAM AT DXP ESTATE
VILLAGE- GADAULI KALAN, SECTOR-37D, GURUGRAM, HARYANA
KADIPUR ST
GURUGRAM
911244908200
9250785681 (Number Shared by Promoter in Public)
compliance@sigantureglobal.in
RAVI AGGARWAL
911244908200
9250785681 (Number Shared by Promoter in Public)
compliance@signatureglobal.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11202510090003216409-10-20256696256YES BANKHRERA Gurugram
21202510090003023909-10-20251888126YES BANKHRERA Gurugram
31202510270003268527-10-20256847379YES BANKHRERA Gurugram







13.5656 (Acre)
3.49
4.5
13.5656 (Acre)
172 OF 2024 Dated 03.12.2024
Yes







480187.59 Lakhs
95746.35 Lakhs
311477.26 Lakhs
1674.65 Lakhs
71289.33 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 2.547
3CONSTRUCTION OF ROADS 7.3761
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 2.505
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0.413
13COMMERCIAL 0.368
14SCHOOL 0.201
15ELECTRIC 0.0197
16RAIN 0.0268
17OPEN 0.109
Total13.5656




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDA (CONECTED)No
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNNo
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDA (OWN ARRANGEMENT)No




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS185.93SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM658.51SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE77.43SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL454.71SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING41.62SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS5.86SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15MS CHARGES250.59SUBMITTED TO TOWN & COUNTRY PLANNING


NA (date)
10-10-2025 (date)
01-01-2026
31-12-2032
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings82.7693
Apartment/Shops/Other Buildings83.7293
Apartment/Shops/Other Buildings83.9293
Apartment/Shops/Other Buildings84.1262
Apartment/Shops/Other Buildings84.45183
Apartment/Shops/Other Buildings18.973181
Apartment/Shops/Other Buildings91.392453
Apartment/Shops/Other Buildings91.652363
Apartment/Shops/Other Buildings97.0062
Apartment/Shops/Other Buildings101.701582
Apartment/Shops/Other Buildings102.204566
Apartment/Shops/Other Buildings113.624045
Apartment/Shops/Other Buildings120.701613
Apartment/Shops/Other Buildings131.96812
Apartment/Shops/Other Buildings1186.70431





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments777.93
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments02500
Shops00
Plots00

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments10000100001000010000
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments10000100001000010000
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments10000100001000010000
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments10000120001200012000
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments12000120001200012000
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments12000120001200012000
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments12000120001200010199.33
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements62.59136.37236.372
Water Supply System221.679198.479198.479
Sewerage treatment & garbage disposal153.072137.052137.052
Electricity Supply System000
Storm Water Drainage26.06623.33823.338
Parks and Playgrounds1.9731.7661.766
Clubhouse/community centres000
Shopping area000
Other000
Street light14.0118.1428.142

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.66919.66911.2570
Water Supply System19.93719.93600
Sewerage treatment & garbage disposal13.76713.76700
Electricity Supply System0000
Storm Water Drainage2.3442.34400
Parks and Playgrounds0.1770.17800
Clubhouse/community centres0000
Shopping area0000
Other0000
Street light4.4034.402
Ms Charges250.59
street light2.52












Yes
No
ICICI BANK LIMITED, 005A, UNITECH TRADE CENTRE, OPP. PARK PLAZA HOTEL, SECTOR ROAD, SUSHANT LOK PHASE-I, GURUGRAM, HARYANA,122002
777705031481
ICIC0000314
110229042
000314
Master collection account namely " SIGNATUREGLOBAL HOMES LTD SIGNATURE GLOBAL SARVAM AT DXP ESTATE COLLECTION A/C" account will be operated by Mr. Pradeep Kumar Aggarwal and Lalit Aggarwal R/o Aashirwad, Palam Farm 6, Salahapur, Bijwasan, South West Delhi-110061
Attached











No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 172 OF 2024ALREADY BEEN OBTAINED03-12-2024
II. LOI ALREADY BEEN OBTAINED16-08-2024
III. LC-IVALREADY BEEN OBTAINED03-12-2024
IV. ZONING PLANALREADY BEEN OBTAINED01-10-2025
V. PHASING APPROVALALREADY BEEN OBTAINED30-07-2025
VI. FOREST NOCALREADY BEEN OBTAINED29-10-2024
VII. AAI NOCALREADY BEEN OBTAINED17-02-2025
VIII. BR-IIIALREADY BEEN OBTAINED10-10-2025








Yes


Yes


Attached







SIGNATURE GLOBAL PARK-I (1), LOCATEDAT VILLAGE-DUNELA, SEC-36, GURUGRAM
3.91
116
0
115
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
7986.2605303.91
Cost of the apartments480002909.52
Cost of the infrastructure000
Others costs3186.2602394.39


6643.05 Lakhs
253 Lakhs
0 Lakhs
0 Lakhs
No
28-10-2026
28-10-2026




SIGNATURE GLOBAL PARK-II, LOCATED AT VILLAGE-DUNELA, SEC-36, GURUGRAM
8.26
368
0
368
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
13940.49013940.49
Cost of the apartments849708500.97
Cost of the infrastructure000
Others costs5443.4905439.52


16402.35 Lakhs
1598.73 Lakhs
0 Lakhs
0 Lakhs
No
30-12-2023
30-12-2023




SIGNATURE GLOBAL PARK-III EXT. (PHASE-1), LOCATED AT VILLAGE-DUNELA, SEC-36,GURUGRAM
3.35
152
0
152
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4466.5904142.56
Cost of the apartments240002784.10
Cost of the infrastructure000
Others costs2066.5901358.46


6368.78 Lakhs
638.76 Lakhs
0 Lakhs
0 Lakhs
No
29-12-2025
29-12-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSESTONE FINISH TILE
2WALL FINISHING DETAILSEMULSION PAINT
3KITCHEN DETAILSMODULAR KITCHEN WITH HOB, CHIMNEY.
4BATHROOM FITTINGSBRANDED CP FITTINGS
5WOOD WORK ETCLAMINATED WOODEN FLOORING
6DOORS AND WINDOS FRAMES8 FEET HIGH VENEER DOOR SHUTTER & FRAME IN PU PAINT FINISH/ SGU- ENERGY EFFICIENT GLASS/TINTED /REFLECTIVE/CLEAR GLASS WITH COMPOSITE ALUMINIUM FRAMES
7GLASS WORKMS +GLASS (MATT FINISH , SATIN FINISH)
8ELECTRIC FITTINGS AS PER ISI STANDARD
9CONDUCTING AND WIRING DETAILS AS PER ISI STANDARD
10CUPBOARD DETAILS NA
11WATER STORAGE NA
12LIFT DETAILSPASSENGER LIFT/SERVICE LIFT
13EXTERNAL GLAZINGSMS + GLASS
13.1WINDOWS/GLAZINGSGLASS WITH ALUMINIUM FRAME
14DOORS8 FEET HIGH VENEER DOOR SHUTTER & FRAME IN PU PAINT FINISH/ 8 FEET HIGH LAMINATED FLUSH DOOR SHUTTER & FRAME IN PU PAINT FINISH.
14.1MAIN DOORSMAIN DOOR : 8 FEET HIGH VENEER DOOR SHUTTER & FRAME IN PU PAINT FINISH
14.2INTERNAL DOORS8 FEET HIGH VENEER DOOR SHUTTER & FRAME IN PU PAINT FINISH/ 8 FEET HIGH LAMINATED FLUSH DOOR SHUTTER & FRAME IN PU PAINT FINISH.
15AIR CONDITIONINGSPLIT
16ELECTRICAL FITTINGSAS PER ISI STANDARD
17CNG PIPE LINE NA
18PROVISION OF WIFI AND BROADBAND FACILITY NA
19EXTERNAL FINISHING/COLOUR SCHEME NA
20INTERNAL FINISHING NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORSTONE FINISH TILE / IMPORTED MARBLE
1 . 2 WALLSEMULSION PAINT
1 . 3 CEILINGOIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSEMULSION PAINT
2 . 3 CEILINGOIL BOUNDER DISTEMPER
2 . 4 MODULAR WARDROBES NA
3 . MASTER TOILET
3 . 1 FLOORANTI SKID TILES
3 . 2 WALLSTILE DADO TILL FALSE CEILING
3 . 3 CEILINGOIL BOUND DISTEMPER ON CEILING / MOISTURE RESISTANT GYP-BOARD FALSE CEILING
3 . 4 COUNTERSGRANITE STONE
3 . 5 SANITARY WARE/CP FITTINGS BRANDED CP FITTINGS
3 . 6 FITTING/FIXTURESBRANDED CP FITTINGS
4 . BED ROOMS
4 . 1 FLOOR"TILEWOODEN FLOORING
4 . 2 WALLSEMULSION PAINT
4 . 3 CEILINGOIL BOUNDER DISTEMPER
4 . 4 WARDROBES NA
5 . TOILET
5 . 1 FLOORANTI SKID TILES
5 . 2 WALLSTILE DADO TILL FALSE CEILING
5 . 3 CEILINGOIL BOUND DISTEMPER ON CEILING / MOISTURE RESISTANT GYP-BOARD FALSE CEILING
5 . 4 COUNTERSGRANITE COUNTER​
5 . 5 SANITARY WARE/CP FITTINGS BRANDED CP FITTINGS
5 . 6 FIXTURESBRANDED CP FITTINGS
6 . KITCHEN
6 . 1 FLOORSTONE FINISH TILE , IMPORTED MARBLE
6 . 2 WALLSTILE DADO / EMULSION PAINT
6 . 3 CEILINGGRANITE COUNTER
6 . 4 COUNTERSOIL BOUND DISTEMPER
6 . 5 FIXTURESMODULAR KITCHEN WITH HOB, CHIMNEY.
6 . 6 KITCHEN APPLIANCES NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI SKID TILES
7 . 2 WALLS & CEILINGEXTERIOR TEXTURE GRADE ACRYLIC EMULSION PAINT
7 . 3 TOILETANTI SKID TILES
7 . 4 BALCONYMS +GLASS (MATT FINISH , SATIN FINISH)
8 . SIT-OUTS
8 . 1 FLOOR NA
8 . 2 WALLS & CEILING NA
8 . 3 RAILINGS NA
8 . 4 FIXTURES NA












Sr. No.Document DescriptionDate of Document UploadView Document
1 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 10-10-2025 View Document
2 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 10-10-2025 View Document
3 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 10-10-2025 View Document
4 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 09-10-2025 View Document
5 DEMARCATION PLAN 10-10-2025 View Document
6 ZONING PLAN 10-10-2025 View Document
7 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 10-10-2025 View Document
8 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 10-10-2025 View Document
9 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 09-10-2025 View Document
10 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 09-10-2025 View Document
11 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 10-10-2025 View Document
12 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 10-10-2025 View Document
13 BG IDW-SE DTCP SGHPL 13.5656ACRES 10-11-2025 ------
14 DTCP RECEIVING FOR SUBMISSION OF BG AT THE TIME OF LOI 10-11-2025 ------
15 STROM WATER PLAN 10-11-2025 ------
16 WATER SUPPLY PLAN 10-11-2025 ------
17 DTCP RECEIVING FOR SUBMISSION OF BG 10-11-2025 ------
18 ROAD AND PAVMENTS 10-11-2025 ------
19 SERVICE ESTIMATES BOOKLET 10-11-2025 ------
20 SEWERAGE PLAN 10-11-2025 ------
21 TYPE -A (TOWER - 8 ) LEFT SIDE & ROAD SIDE ELEVATION 11-12-2025 ------
22 TOWER - 09 ) 16TH , 25TH & 34TH REFUGE FLOOR & AREA LINE DIAGRAM 11-12-2025 ------
23 TOWER - 09 ) 2ND FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
24 TYPE -A (TOWER - 6 )LEFT SIDE & ROAD SIDE ELEVATION 11-12-2025 ------
25 CLUB HOUSE (1ST ,TERRACE & MUMTY FLOOR PLAN) & AREA LINE DIAGRAM 11-12-2025 ------
26 TOWER - 09 ) 3RD TO 15TH, 17TH TO 24TH, 26TH TO 40TH TYPICAL FLOOR & AREA LINE DIAGRAM 11-12-2025 ------
27 1ST FLOOR & AREA LINE DIAGRAM (TYPE B1 TOWER 4) 11-12-2025 ------
28 TOWER - 09 ) SECTION 1 & 2 11-12-2025 ------
29 BG IDW-SE DTCP SGHPL 13.5656ACRES 11-12-2025 ------
30 SEWERAGE PLAN_ 11-12-2025 ------
31 SERVICE ESTIMATES BOOKLET 11-12-2025 ------
32 TOWER - 09 ) 3RD TO 15TH, 17TH TO 24TH, 26TH TO 40TH TYPICAL FLOOR & AREA LINE DIAGRAM 11-12-2025 ------
33 APPROVAL OF BUILDING PLAN 11-12-2025 ------
34 TYPE -A (TOWER - 7) 34TH REFUGE FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
35 CA CERTIFICATE FOR LAND COST 11-12-2025 ------
36 TYPE -A (TOWER - 7 ) 1ST TO 15TH,17TH TO 24TH,26TH TO 31TH FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
37 STROM WATER PLAN 11-12-2025 ------
38 TYPE -A (TOWER - 6 )TLMR & OHT FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
39 SECTION 1 & 2 (TYPE B1 TOWER 4) 11-12-2025 ------
40 DTCP RECEIVING FOR SUBMISSION OF BG 11-12-2025 ------
41 ROAD AND PAVMENTS 11-12-2025 ------
42 ( COMMERCIAL & SCHOOL) SERVICE FLOOR & MUMTY FLOOR PLAN 11-12-2025 ------
43 TOWER - 09 ) 1ST FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
44 TYPE -A (TOWER - 7 ) 16TH & 25TH REFUGE FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
45 TYPE -A (TOWER - 7 ) SECTION AA & SECTION BB 11-12-2025 ------
46 TOWER - 09 ) ALL SIDE ELEVATION 11-12-2025 ------
47 STILT FLOOR PLAN & AREA LINE DIAGRAM (TYPE B1 TOWER 4 & TYPE B TOWER 5) 11-12-2025 ------
48 DTCP RECEIVING FOR SUBMISSION OF BG AT THE TIME OF LOI 11-12-2025 ------
49 ( COMMERCIAL & SCHOOL) 1ST FLOOR & AREA LINE DIAGRAM 11-12-2025 ------
50 WATER SUPPLY PLAN 11-12-2025 ------
51 REVISED ZONING PLAN 13.5656 ACRES 11-12-2025 ------
52 COMMERCIAL & SCHOOL ) GROUND FLOOR & AREA LINE DIAGRAM 11-12-2025 ------
53 ( EWS ) ,LIFT MACHINE ROOF TOP 11-12-2025 ------
54 ( EWS ) 18TH REFUGE FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
55 TYPE -A (TOWER - 6 &7)STILT FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
56 TYPE -A (TOWER - 6 )1ST FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
57 TYPE -A (TOWER - 7 ) 2ND FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
58 TYPE -A (TOWER - 7 ) GARDEN SIDE ELEVATION AND RIGHT SIDE ELEVATION 11-12-2025 ------
59 TYPE -A (TOWER - 7 ) STILT FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
60 TYPE -A (TOWER - 7 ) TLMR & OHT FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
61 TYPE -A (TOWER - 8 ) STILT FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
62 TYPE-A (TOWER-6 )SECTION AA & SECTION BB 11-12-2025 ------
63 ALL SIDE ELEVATION (TYPE B1 TOWER 4) 11-12-2025 ------
64 TOWER - 09 ) SECTION 1 & 2 11-12-2025 ------
65 REVISED ZONING PLAN 13.5656 ACRES (1) 11-12-2025 ------
66 STATEMNET OF NET CASHFLOW 11-12-2025 ------
67 TYPE -A (TOWER - 7 )3RD TO 15TH & 17TH,TO 24TH,26TH TO 31ST FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
68 TYPE -A (TOWER - 7) 32ND TO 33RD & 35TH TO 41TH FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
69 TYPE -A (TOWER - 7)TERRACE FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
70 TYPE -A (TOWER - 8 ) GARDEN SIDE ELEVATION AND RIGHT SIDE ELEVATION 11-12-2025 ------
71 TYPE -A (TOWER - 8 ) SECTION AA & SECTION BB 11-12-2025 ------
72 TYPE -A (TOWER -7 )TYPICAL & REFUGE FLOOR PLAN (UNIT-A _ UNIT-B & UNIT-C)& AREA LINE DIAGRAM 11-12-2025 ------
73 2ND TO 15, 17TH TO 24, 26TH TO 33 & 35 TO 41 FLOOR & AREA LINE DIAGRAM (TYPE B1 TOWER 4) 11-12-2025 ------
74 16TH 25TH & 34TH FLOOR AREA LINE DIAGRAM FLOOR & AREA LINE DIAGRAM (TYPE B1 TOWER 4) 11-12-2025 ------
75 CLUB HOUSE ((STILT FLOOR PLAN) & 1ST BASEMENT FLOOR PLAN) & AREA LINE DIAGRAM 11-12-2025 ------
76 LIFT MACHINE ROOM & AREA LINE DIAGRAM (TYPE B1 TOWER 4) 11-12-2025 ------
77 TERRACE FLOOR PLAN & AREA LINE DIAGRAM (TYPE B1 TOWER 4) 11-12-2025 ------
78 TOWER - 09 ) ALL SIDE ELEVATION 11-12-2025 ------
79 TOWER - 09 ) STILT FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
80 TOWER - 09 ) TERRACE FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
81 TOWER - 09 ) 1ST FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
82 TOWER - 09 ) 2ND FLOOR PLAN & AREA LINE DIAGRAM 11-12-2025 ------
83 TOWER - 09 ) 16TH , 25TH & 34TH REFUGE FLOOR & AREA LINE DIAGRAM 11-12-2025 ------
84 CA CERTIFICATE FOR COST INCURRED_ 11-12-2025 ------
85 CA CERTIFICATE FOR NON-DEFUALT_19072025 11-12-2025 ------
86 TOWER - 09 ) TYPICAL & REFUGE FLOOR PLAN (UNIT-A _ UNIT-B & UNIT-C) 11-12-2025 ------
87 LICENSE NO. 172 OF 2024 11-12-2025 ------
88 REP-II_ SARVAM 11-12-2025 ------
89 ROJNAMCHA_LICENSE ENTRY 11-12-2025 ------