KOHINOOR CITY
VILLAGE NILOKHERI SECTOR 13
KARNAL
KARNAL
9896298964 (Number Shared by Promoter in Public)
anantkripadevelopers@gmail.com
ROHIT WADHWA
9896037179 (Number Shared by Promoter in Public)
Rohitwadhwa123@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
Annexure-B- ANNEXURE-B- COLLABORATION AGREEMENT HAS BEEN EXECUTED BETWEEN THE LANDOWNERS AND THE DEVELOPERS UNDER ORDER MEMO NO. DULB/CTP/TP/-SCHEME/2025 GRANTED BY THE URBAN LOCAL BODIES DEPARTMENT GOVERNMENT OF HARYANA
YES THE AGREEMENT EXECUTED BEFORE THE GRANT OF LICENSE.
Yes
THE LANDOWNER HAD APPROACHED THE DEVELOPER TO OBTAIN THE LICENSE AND CONVERSION OF LAND USE FOR THE DEVELOPMENT, RESIDENTIAL PLOTTING, OR ANY OTHER USE AS MAY BE PERMITTED IN ACCORDANCE WITH THE EXISTING POLICIES, NOTIFICATIONS, RULES, OR BYE-LAWS OF THE AUTHORITY OF THE STATE OF HARYANA, AND TO CARRY OUT THE DEVELOPMENT AND CONSTRUCTION WORKS OF THE SAID APPROPRIATE PROJECT AS PER THE TERMS OF THE LICENSE/CONVERSION OF THE LAND USE THAT MAY BE GRANTED BY THE RELEVANT AUTHORITY/DEPARTMENT OF THE STATE, AND THE DEVELOPER HAS AGREED TO THE SAME
No
Yes
Yes
2132.46 Lakhs
996.00 Lakhs
0 Lakhs
700.00 Lakhs
436.46 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
6.2054
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
3.4935
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.9353
6
GREEN BELTS
0.0921
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
1.2367
12
ANY OTHER
0
13
AREA UNDER COMMERCIAL
0.4932
Total
12.4562
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
UHBVNL
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
191.24
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
110.60
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
81.27
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
93.59
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
106.33
AS PER PROJECT REPORT
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
30.17
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
STREET LIGHTING
34.16
AS PER PROJECT REPORT
16
BOUNDARY WALL
52.64
AS PER PROJECT REPORT
05-09-2025 (date)
NA (date)
01-02-2026
18-09-2030
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
135.273
7
2
112.728
1
3
135.273
7
4
140.910
36
5
124.775
5
6
140.910
36
7
147.088
10
8
107.400
6
9
104.288
6
10
92.790
1
11
81.555
1
12
143.374
7
13
137.185
1
14
120.487
7
15
150.000
16
16
147.000
20
17
75.600
2
18
148.230
1
19
149.815
12
Total
182
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)