HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1815-2025
Submission Date : 18-09-2025 10:03:47 PM
Applicant Type : Registered Society or Trust or Authority
Project Type: NEW




THE JAI GURU DEV GOVT EMPLOYEES COOPERATIVE GROUP HOUSING SOCIETY LIMITED
PLOT NO. 3, SECTOR-10, HUDA BYE PASS, REWARI, HARYANA 123401
9991516336 (Number Shared by Promoter in Public)
praveenyadav40707@gmail.com
XXXX890N
1220R
THE HARYANA CO-OPERATIVE SOCIETIES ACT, 1984
 
 


 
 











BLISSFUL HOMES
PLOT NO.3 SECTOR-10 HUDA BYE PASS REWARI
REWARI
REWARI
9991615336 (Number Shared by Promoter in Public)
PRAVEENYADAV40707@GMAIL.COM
PARVEEN YADAV
9991615336 (Number Shared by Promoter in Public)
PRAVEENYADAV40707@GMAIL.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
120351803616-07-202550000ICICI BANKHRERA Panchkula







0.494 (Acre)
1.75
1.746
0.494 (Acre)
HARYANA URBAN DEVELOPMENT AUTHORITY REWARI ALLOTMENT OF GHS SITE VIDE LETTER MEMO NO. 6062 DATED 13.08.2007
Yes







1646 Lakhs
46 Lakhs
1430 Lakhs
100 Lakhs
70 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 700
3CONSTRUCTION OF ROADS 824.31
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 300
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 175.69
Total2000




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS25AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM12AS PER PROJECT REPORT
3STORM WATER DRAINAGE0AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM15AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL15AS PER PROJECT REPORT
6STREET LIGHTING8AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING8AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS17AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT


NA (date)
NA (date)
01-01-2024
31-12-2026
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings98.108101
Apartment/Shops/Other Buildings98.827101
Apartment/Shops/Other Buildings99.687101





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments700
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments40125
Shops00
Plots00

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments145130150140
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements45
Water Supply System03
Sewerage treatment & garbage disposal05
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4750
Water Supply System2430
Sewerage treatment & garbage disposal6400
Electricity Supply System0780
Storm Water Drainage0000
Parks and Playgrounds2645
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and Firefighting242
Street Lighting2222












No
No
ICICI BANK BAWAL NEAR BANIPUR CHOWK HARYANA
349805000726
ICIC0003498
123229203
3498
LAL SINGH YADAV AND PARVEEN KUMAR
ATTACHED











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. BUILDING PLAN APPROVED VIDE MEMO NO. 87358ALREADY BEEN OBTAINED19-03-2025








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEINTERNAL FLOORING OF THE FLAT LIVING/DINNING/BEDROOMS/PASSAGES VITRIFIED TILES.
2WALL FINISHING DETAILSINTERNAL WALLS/CEILINGS OF THE FLAT OBD FINISH
3KITCHEN DETAILSGRANITE MARBLE COUNTER MOUNTED ON FRAME OR SLAB 2. SS SINGLE BOWL SINK 3. CP FITTINGS 4. CERAMIC TILES UPTO TWO TO TWO AND A HALF FEET ABOVE COUNTER.
4BATHROOM FITTINGSTAPS FITTINGS PROVIDED 2. WC'S AND WASH BASINS
5WOOD WORK ETCNOT PROVIDED
6DOORS AND WINDOS FRAMESNOT PROVIDED
7GLASS WORKNOT PROVIDED
8ELECTRIC FITTINGSISI APPROVED SWITCHES AND PLATES OTHER FIXTURES LIKE LIGHTS, FANS ETC
9CONDUCTING AND WIRING DETAILSDISTRIBUTION BOX,CONDUTING,WIRING (AS PER I.S. CODE)
10CUPBOARD DETAILSNOT PROVIDED
11WATER STORAGERCC UNDER GROUND WATER TANK OF ADEQUATE CAPACITY OVERHEAD STORAGE TANKS AS PER HSVP RULES
12LIFT DETAILSPASSENGER LIFT WILL BE PROVIDED OF REPUTED MAKE LIKE KONE, JOHNSONS OR EQUIVALENT.
13EXTERNAL GLAZINGSGLASS WORK OR EQUIVALENT
13.1WINDOWS/GLAZINGSGLASS WORK OR EQUIVALENT
14DOORSAS PER STANDARD
14.1MAIN DOORSFLUSH DOOR WITH WOODEN FRAME
14.2INTERNAL DOORSFLUSH DOORS WITH PAINT OR EQUIVALENT
15AIR CONDITIONINGNOT PROVIDED
16ELECTRICAL FITTINGSNOT PROVIDED
17CNG PIPE LINEOPTIONAL
18PROVISION OF WIFI AND BROADBAND FACILITYNOT PROVIDED
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR PAINT
20INTERNAL FINISHINGOBD FINISH PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD FINISH
1 . 3 CEILINGOBD FINISH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSOBD FINISH
2 . 3 CEILINGOBD FINISH
2 . 4 MODULAR WARDROBESNOT PROVIDED
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES
3 . 2 WALLSCERAMIC TILES UPTO DOOR SIL LEVEL
3 . 3 CEILINGOBD FINISH
3 . 4 COUNTERSGRANITE MARBLE COUNTER
3 . 5 SANITARY WARE/CP FITTINGS1. CP FITTINGS 2. SANITARY WARE
3 . 6 FITTING/FIXTURESNOT PROVIDED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOBD FINISH
4 . 3 CEILINGOBD FINISH
4 . 4 WARDROBESNOT PROVIDED
5 . TOILET
5 . 1 FLOORCERAMIC TILES
5 . 2 WALLSCERAMIC TILES
5 . 3 CEILINGOBD FINISH
5 . 4 COUNTERSNOT PROVIDED
5 . 5 SANITARY WARE/CP FITTINGS1. CP FITTINGS 2. SANITARY WARE
5 . 6 FIXTURESNOT PROVIDED
6 . KITCHEN
6 . 1 FLOORCERAMIC TILES
6 . 2 WALLSCERAMIC TILES
6 . 3 CEILINGOBD FINISH
6 . 4 COUNTERSGRANITE MARBLE COUNTER MOUNTED
6 . 5 FIXTURES1. CP FITTINGS 2. SANITARY WARE
6 . 6 KITCHEN APPLIANCESNOT PROVIDED
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGOBD FINISH
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYCERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1 REGISTRATION CERTIFICATE AND BYE LAWS OF THE SOCIETY 17-09-2025 ------
2 FLOOR PLANS 17-09-2025 ------
3 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 13-09-2025 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 13-09-2025 View Document
5 PROOF OF PAYMENT 17-09-2025 ------
6 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 13-09-2025 View Document
7 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 13-09-2025 View Document
8 FIRE SCHEME 17-09-2025 ------
9 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 17-09-2025 View Document
10 ELEVATION PLAN 17-09-2025 ------
11 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 17-09-2025 View Document
12 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 13-09-2025 View Document
13 ELEVATION PLANS 17-09-2025 ------
14 BOARD RESOLUTION 17-09-2025 ------
15 CONVEYANCE DEED 17-09-2025 ------
16 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 13-09-2025 View Document
17 AIRPORT AUTHORITY OF INDIA 17-09-2025 ------