HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2058-2025
Submission Date : 16-09-2025 03:18:44 PM
Applicant Type : Company
Project Type: NEW




M3M INDIA INFRASTRUCTURES PRIVATE LIMITED
41ST FLOOR, TOWER-1, M3M INTERNATIONAL FINANCIAL CENTER, SECTOR-66, BADSHAHPUR, GURGAON, HARYANA, INDIA, 122101
1244372000
8929012754 (Number Shared by Promoter in Public)
m3mindiainfrastructures@gmail.com
http://m3mindiainfrastructures.com/
XXXX367L
U45400HR2014PTC054057
 
 


 
 


 
 


 
 







GURGAON INTERNATIONAL CITY
SECTOR- M9, M10, M11
HARSARU ST
GURUGRAM
1244732000
8929012754 (Number Shared by Promoter in Public)
m3mindiainfrastructures@gmail.com
BHARAT VIGMAL
1244732000
8929012754 (Number Shared by Promoter in Public)
m3mindiainfrastructures@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150319210-09-2025500000ICICI BANK LIMITEDHRERA Gurugram
250326103-10-20259581986ICICI BANK LIMITEDHRERA Gurugram
350319111-09-20251500000ICICI BANK LIMITEDHRERA Gurugram







139.79375 (Acre)
1
1
139.79375 (Acre)
DTCP Licence no 168 of 2025 dated 08.09.2025 valid till 07.09.2025
Yes







123464.35 Lakhs
39981.76 Lakhs
0 Lakhs
24892.58 Lakhs
58590.01 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 33.99763
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13ORGNIZED 12.309
14COMMERCIAL 2.97428
15RESIDENTIAL 36.6084
16AREA 4.887
17UD 2.72
18INDUSTRIAL PLOTS NAMELY M THREE M INNOVATION PARK 46.29744
Total139.79375




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP Yes
WATER SUPPLYHSVP Yes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVP Yes
STORM WATER DRAINAGEHSVP Yes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS5182.26AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM1298.45AS PER PROJECT REPORT
3STORM WATER DRAINAGE1677.53AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL838.76AS PER PROJECT REPORT
6STREET LIGHTING1000.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING349.48AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS3139.64AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15ELECTRIFICATION3914.23AS PER PROJECT REPORT
16STP1397.94AS PER PROJECT REPORT
17UNDERGROUND TANK1932.06AS PER PROJECT REPORT
18RAIN WATER HARVESTING1000.00AS PER PROJECT REPORT
19ELECTRICAL SUB STATION1335.00AS PER PROJECT REPORT
20SWITCHING STATION COST 750.00AS PER PROJECT REPORT
21COST OF SEWAGE STORM WATER CONNECTION CHARGES350.00AS PER PROJECT REPORT
22ORGANIC WATER CONVERTER30.00AS PER PROJECT REPORT
23BOUNDARY WALL697.23AS PER PROJECT REPORT


08-09-2025 (date)
01-01-2015 (date)
01-10-2025
30-09-2034
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 735.79 9
2 735.41 14
3 759.32 1
4 759.91 1
5 759.52 1
6 760.3 1
7 271.42 1
8 535.79 2
9 521.26 19
10 390.76 1
11 508.17 1
12 535.8 1
13 521.62 1
14 466.35 29
15 503 1
16 509.58 1
17 535.19 1
18 514.47 1
19 480.00 16
20 457.35 1
21 458.85 1
22 460.37 1
23 461.82 1
24 463.48 1
25 464.93 1
26 466.45 1
27 467.98 1
28 469.50 1
29 471.02 1
30 472.40 1
31 474.21 1
32 475.42 1
33 477.27 1
34 478.63 1
35 480.15 1
36 595.99 1
37 593.90 1
38 577.03 1
39 1867.92 2
40 1171.10 1
41 1189.11 1
42 1217.54 1
43 1197.60 1
44 609.23 4
45 202.31 6
46 164.27 1
47 374.43 12
48 777.82 1
49 537.99 1
50 498.25 1
51 538.09 1
52 395.52 1
53 582.76 1
54 468.65 1
55 197.75 1
56 1899.21 1
57 1694.31 1
58 3287.69 1
59 507.79 1
60 900.73 1
61 308.82 1
62 1764.50 3
63 1293.90 1
64 1768.76 1
65 1696.34 1
66 1768.81 1
67 1769.04 1
68 1768.85 1
69 366.56 2
70 1115.17 1
71 1114.35 1
72 1113.50 1
73 1112.68 1
74 1063.88 4
75 1068.58 1
76 1098.41 1
77 1040.25 1
78 1072.74 1
79 1067.19 1
80 791.90 1
81 780.02 1
82 987.84 1
83 1113.30 1
84 1283.98 1
85 1282.31 1
86 1292.01 1
87 1562.54 1
88 1561.06 1
89 1558.55 1
90 1556.76 1
91 1480.80 1
92 641.19 1
93 642.75 1
94 643.98 1
95 182.24 46
96 1980.63 1
97 1962.32 1
98 1943.81 1
99 798.16 1
100 448.05 2
101 473.44 1
102 539.76 1
103 696.78 1
104 625.95 1
105 821.94 1
106 269.57 1
107 258.76 1
108 1785.25 1
109 1772.96 1
110 1772.51 1
111 1773.38 1
112 1772.56 1
113 767.61 1
114 1187.53 1
115 458.52 1
116 1316.12 1
117 1288.94 1
118 1146.37 1
119 1181.13 1
120 1344.45 1
121 1010.46 1
122 367.83 1
123 395.31 1
124 661.92 1
125 823.99 1
126 390.93 1
127 475.80 1
128 797.44 1
129 1250.73 1
130 1057.25 1
131 472.27 1
132 66666.92 1
133 44444.61 1
134 37037.18 1
135 5321.20 1
136 6715.28 1
Total291


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System7.14
Sewerage treatment & garbage disposal18.54
Electricity Supply System0
Storm Water Drainage37.07
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements9.3313.4719.1726.95
Water Supply System13.112.212.212.21
Sewerage treatment & garbage disposal16.8616.4412.0812.08
Electricity Supply System0000
Storm Water Drainage33.7216.107.387.38
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Boundary Wall69.72104.5869.7248.81

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements37.3152.3472.5598.98
Water Supply System7.0112.7212.7222.85
Sewerage treatment & garbage disposal12.0814.0116.6118.37
Electricity Supply System0000
Storm Water Drainage7.3820.6332.2144.79
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STP74.0971.2949.21
Underground Tank63.9544.6319.5119.51
Boundary Wall83.6769.7269.7283.67
Rain Water Harvesting44.2044.20

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements134.22178.27231.13290.21
Water Supply System33.2437.5339.2142.07
Sewerage treatment & garbage disposal21.2224.1625.2528.77
Electricity Supply System0000
Storm Water Drainage49.1558.3866.9372.30
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrification till Site0000
STP31.1731.1731.1741.38
Security and Fire Fighting0000
Street Light0000
Rain Water Harvesting37.6029.8029.8029.80
Boundary Wall48.8134.8613.940
Organic Waste Converter0000
Underground Tank19.5137.2951.7858.93
Electrical Sub Station0078.5068.35
IDW Connection Charges0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements351.36405.25442.57456.04
Water Supply System59.6064.6667.0069.21
Sewerage treatment & garbage disposal33.3034.0537.6641.27
Electricity Supply System261.08234.46165.57165.57
Storm Water Drainage76.6684.0489.4196.96
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting31.7036.2040.0047.30
Electrical Sub Station63.5563.5563.5555.54
STP54.1063.3378.5682.20
Street Light66.7059.9042.3042.30
Underground Tank75.7491.39100.08115.73
IDW Connection Charges19.2927.0637.42
Electrification till Site068.4068.40
Security and Fire Fighting0

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements442.57405.25351.36342.03
Water Supply System72.4576.6181.0285.96
Sewerage treatment & garbage disposal49.3252.1758.6362.32
Electricity Supply System165.57227.42386.73504.15
Storm Water Drainage100.99108.54118.77128.00
Parks and Playgrounds269.70274.72203.76203.76
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical Sub Station65.0172.3685.57105.33
STP92.40107.92114.7799.53
Security and Fire Fighting30.0230.5822.6822.68
Street Light42.3058.1098.80128.80
Rain Water Harvesting58.9064.2068.7070.50
Electrification till Site65.8546.9546.9546.95
IDW Connection Charges11.9725.9732.80
Underground Tank128.87135.82152.44171.37

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements231.13178.27134.2298.98
Water Supply System91.54105.4388.4272.06
Sewerage treatment & garbage disposal59.7255.8642.7833.89
Electricity Supply System472.84399.64317.44249.73
Storm Water Drainage133.53104.1772.4750.83
Parks and Playgrounds245.52270.64400.93449.60
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical Sub Station111.07105.0691.1881.70
Electrification till Site54.4559.4869.9069.90
IDW Connection Charges45.2638.2634.7627.02
Security and Fire Fighting27.3330.1344.6350.05
Street Light120.80102.1081.1063.80
STP85.6975.7769.6254.66
Underground Tank148.96125.58114.3883.46
Rain Water Harvesting70.5065.5060.7059.70
Organic Waste Converter7.50

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements72.5552.3454.41
Water Supply System52.0739.0839.08
Sewerage treatment & garbage disposal19.4614.687.21
Electricity Supply System122.1239.93201.97
Storm Water Drainage32.5416.9410.23
Parks and Playgrounds405.33245.52170.17
Clubhouse/community centres000
Shopping area000
Other000
STP45.0129.5015.38
Electrical Sub Station73.2944.32107.07
Rain Water Harvesting53.3048.508.90
Street Light31.2010.2051.60
Security and Fire Fighting45.1227.3318.94
Electrification till Site69.9048.1534.73
IDW Connection Charges24.4017.298.54
Organic Waste Converter7.507.507.50
Underground Tank76.5158.5438.06












Yes
Yes
KOTAK MAHINDRA BANK, GROUND FLOOR,JMD REGENT SQUARE,MG ROAD,GURUGRAM
9049911575
KKBK0000261
110485003
000261
1) Mr. Vyom Shakti Nigam-D3/103 Paras city E3 AreraColony Bhopal M.P. 462016 2) MS. Amarjot Kaur Sahni-3/66Subhash Nagar West Delhi 110027 3) Ms. Shubhra Bakshi-House No 10/6, DLF Phase-1, Sikanderpur Ghosi, Gurgaon,Haryana- 122002 4)Mr. Vidya Sagar-3G-208, Faridabad, NIT Faridabad,Haryana- 121001 5) Mr. Pradeep Kumar Katiyar- 357,Bakhothi Purwa, Thana Bilaur, Kanpur- 209202, UP 6) Mr. Pratap Singh-10A Pocket 2 MayurVihar East Delhi 110096 7) Ms. Meenal Sood- C-81A, Moti Nagar, Ramesh Nagar H.O, West Delhi, Delhi 110015 8) Mr. Anurag Kulshrestha- 1 F Pocket-3, Mayur Vihar, Phase 1, Chilla Saroda Khadar, East Delhi 9) Mr. Surender Kumar Gupta- 954 Gokul Dham, Society 1st Floor Krishna Colony, Gurugram 10) Mr.Rajiv Kumar Verma- House No.-06 E,Pratap Enclave,Mohan Garden,Uttam Nagar,,West Delhi 11) Mr.Ashok Kumar- Hajipur(15),Guragon,Haryana 12) Mr.Amit Saxena- 163,Sarai Nazar Ali,Behind M.M,G Hospital,Ghaziabad Uttar Pradesh
Uploaded











Yes
Yes
Yes
No
No
No
No
No
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENCEALREADY BEEN OBTAINED08-09-2025
II. EP APPROVALALREADY BEEN OBTAINED01-09-2025
III. FOREST NOCALREADY BEEN OBTAINED24-05-2025
IV. ASSURANCE STP TREATED WATERALREADY BEEN OBTAINED12-09-2025
V. ASSURANCE DRINKING WATHRALREADY BEEN OBTAINED12-09-2025
VI. ASSURANCE SEWERAGE CONNECTIONALREADY BEEN OBTAINED12-09-2025
VII. ASSURANCE STORM WATERALREADY BEEN OBTAINED12-09-2025








Yes


Yes


As per the HARERA Rules













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 16-09-2025 View Document
2 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 16-09-2025 View Document
3 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 16-09-2025 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 16-09-2025 View Document
5 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 16-09-2025 View Document
6 LC IV AND BILLATERALS 14-10-2025 ------
7 INFORMATION TO REVENUE DEPARTMENT 14-10-2025 ------
8 ZONING PLAN 14-10-2025 ------
9 JAMABANDI 14-10-2025 ------
10 ASSURANCE FOR SEWERAGE 14-10-2025 ------
11 CA CERTIFICATE OF INVENTORY 14-10-2025 ------
12 SHAJRA 14-10-2025 ------
13 CA CERTIFICATE NET WORTH 14-10-2025 ------
14 NON ENCUMBRANCE CERTIFICATE 14-10-2025 ------
15 ASSURANCE- STP TREATED WATER 14-10-2025 ------
16 EP APPROVAL 14-10-2025 ------
17 CA CERTIFICATE OF NON DEFAULT 14-10-2025 ------
18 CA CERTIFICATE INCURRED 14-10-2025 ------
19 LICENCE 14-10-2025 ------
20 LOI 14-10-2025 ------
21 APPLICATION OF SERVICE PLAN ESTIMATE 14-10-2025 ------
22 ASSURANCE- STORM WATER DRAINAGE 14-10-2025 ------
23 ASSURANCE- WATER SUPPLY DRINKING WATER 14-10-2025 ------
24 CASHFLOW STATEMENT 14-10-2025 ------
25 LAYOUT PLAN 14-10-2025 ------
26 MUTATION 14-10-2025 ------
27 REP-II 14-10-2025 ------
28 ALLOTMENT LETTER 04-11-2025 ------
29 APPLICATION FORM 04-11-2025 ------
30 BUILDER BUYER AGREEMENT 04-11-2025 ------
31 CONVEYANCE DEED 04-11-2025 ------