HRERA GurugramTemp Project Id : RERA-GRG-PROJ-148-2019
Submission Date : 03-01-2019 05:31:45 AM
Applicant Type : Company
Project Type: NEW




SANTUR REALTORS PVT. LTD.
E6-GROUND FLOOR,GREATER KAILASH PART 1, DELHI-110048
01146548102
9312216444 (Number Shared by Promoter in Public)
jainmanish65@yahoo.com
http://www.santurgroup.com
XXXX645F
U45200DL2011PTC218321
 
 


 
 


 
 


 
 


 
 


 
 







SANTUR ASPIRA
SECTOR-3, GURUGRAM
GURGAON
GURUGRAM
01146548102
9560558177 (Number Shared by Promoter in Public)
santurgroup@gmail.com
RAJESH KUMAR GUPTA
01146548102
9560558177 (Number Shared by Promoter in Public)
santurgroup@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
111307417-12-2018369200KOTAK MAHINDRA BANK PAMPOSH ENCLAVE GREATER KAILASH PART 1 NEW DELHI 110048HRERA Gurugram
211308019-12-2018184600KOTAK MAHINDRA BANK PAMPOSH ENCLAVE GREATER KAILASH PART 1 NEW DELHI 110048HRERA Gurugram
337484805-02-2019122211KOTAK MAHINDRA BANK PAMPOSH ENCLAVE GREATER KAILASH PART 1 NEW DELHI 110048HRERA Gurugram







2.5625 (Acre)
1.78
1.78
2.5625 (Acre)
50 of 2014
No
Address     HOUSE NO. 354/11, 12 BISWA, VILLAGE GURGAON, TEHSIL AND DISTRICT GURGAON HARYANA
Address     HOUSE NO. 353/14, 12 BISWA, VILLAGE GURGAON, TEHSIL AND DISTRICT GURGAON HARYANA
Address     HOUSE NO. 422, 12 BISWA, VILLAGE GURGAON, TEHSIL AND DISTRICT GURGAON HARYANA
Address     HOUSE NO. 354/11, 12 BISWA, VILLAGE GURGAON, TEHSIL AND DISTRICT GURGAON HARYANA
Address     HOUSE NO. 354/11, 12 BISWA, VILLAGE GURGAON, TEHSIL AND DISTRICT GURGAON HARYANA
Annexure-B- ANNEXURE B - ANNEXURE A!
COLLABORATION AGREEMENT WAS ENTERED BEFORE OBTAINING LICENCE
Yes
COLLABORATION AGREEMENT IS ON SHARING OF BUILT UP AREA
No
Yes
Yes







6831.57 Lakhs
200 Lakhs
2970.22 Lakhs
1622.55 Lakhs
2038.80 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2228.966
3CONSTRUCTION OF ROADS5808.546
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1696.488
6GREEN BELTS0
7VEHICLE PARKINGS624
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY12
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total10370




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHARYANA SHEHRI VIKAS PRADHIKARANYes
WATER SUPPLYHARYANA SHEHRI VIKAS PRADHIKARANYes
ELECTRICITYHARYANA SHEHRI VIKAS PRADHIKARANYes
SEWAGE DISPOSALHARYANA SHEHRI VIKAS PRADHIKARANYes
STORM WATER DRAINAGEHARYANA SHEHRI VIKAS PRADHIKARANYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS84.08SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM118.57SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE39.1SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM5.92SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL32.81SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING9.8SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING33SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS1.97SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA0SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM8.93SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER123SUBMITTED TO TOWN & COUNTRY PLANNING
15PARKING 812AS PER PROJECT REPORT
16STP33.15AS PER PROJECT REPORT
17UNDER GROUND WATER TANK29AS PER PROJECT REPORT
18RAIN WATER HARVESTING9AS PER PROJECT REPORT
19ELECTRICAL SUB STATION282.22AS PER PROJECT REPORT


17-01-2018 (date)
17-01-2018 (date)
01-07-2017
31-05-2021
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings36.11430
Apartment/Shops/Other Buildings112.3101
Apartment/Shops/Other Buildings112.46303
Apartment/Shops/Other Buildings108.17241
Apartment/Shops/Other Buildings108.17241
Apartment/Shops/Other Buildings108.1741
Apartment/Shops/Other Buildings108.33163
Apartment/Shops/Other Buildings107.9241
Apartment/Shops/Other Buildings108.09203
Apartment/Shops/Other Buildings217.2621
Apartment/Shops/Other Buildings216.7621
Apartment/Shops/Other Buildings214.6721





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments928
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments143163163182
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments182234136136
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments329177177.22
Shops0020
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Parking405

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other5030
Parking5050

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00040
Water Supply System004830.57
Sewerage treatment & garbage disposal00012.81
Electricity Supply System0005.92
Storm Water Drainage00015
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other202021
STP1010103.15
Parking505050
under grnd water tank19
parking50
security and fire fighting11

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements44.08000
Water Supply System40000
Sewerage treatment & garbage disposal20000
Electricity Supply System0000
Storm Water Drainage24.1000
Parks and Playgrounds1.97000
Clubhouse/community centres0000
Shopping area0000
Other0000
reneival energy system8.93
treat light9.8
parking107
Drain water harvesting9
electical service station282.22
under ground water tank10
Security and fire fightng22












Yes
No
KOTAK MAHINDRA BANK PAMPOSH ENCLAVE GREATER KAILASH I NEW DELHI 110048
5811447228
KKBK0000195
110485025
000195
Manish Jain and Sharad Jain Jointly or Severally. E-6 SECOND FLOOR GREATER KAILASH PART 1 NEW DELHI 48 AND F-69 GREEN PARK MAIN NEW DELHI 16.
Yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED18-06-2014
II. FOREST NOCALREADY BEEN OBTAINED09-02-2016
III. NATURAL CONSERVATION ZONEALREADY BEEN OBTAINED11-12-2018
IV. AIRPORT HEIGHT CLEARANCE NOCALREADY BEEN OBTAINED29-08-2014
V. HUDA CONSTRUCTION WATERALREADY BEEN OBTAINED08-12-2015
VI. ELECTRICAL LOAD AVAILABILITYALREADY BEEN OBTAINED20-11-2014
VII. ENVIRONMENTAL CLEARANCE ALREADY BEEN OBTAINED22-01-2016
VIII. CONSENT TO ESTABLISHALREADY BEEN OBTAINED03-03-2016
IX. MINING PERMISSIONALREADY BEEN OBTAINED28-04-2016
X. FIRE SCHEME APPROVALALREADY BEEN OBTAINED17-11-2017
XI. SERVICE ESTIMATESALREADY BEEN OBTAINEDNA
XII. FOREST LAND DIVERSIONALREADY BEEN OBTAINED17-07-2014








Yes


Yes


1. Land owners have entered into a collaboration agreement with the “Promoter” for the purpose of development of land at Vasika No.7399 at Sector 3 Gurgaon into a Residential Group Housing Colony. 2. The said land will have 3 Towers namely Tower A, Tower B and Tower C. 3. The Land Owner/Promoter has obtained all the necessary statutory approvals for the development of the project. 4. The units will be sold on the basis rate dependent on carpet area of the flat. But, in addition to this rate, applicable GST shall be payable by the prospective buyers. 5. Initial and subsequent subscription/charges for Club shall be borne by the prospective buyers. 6. IFMS charges; as applicable are not included in the rate as mentioned in (2) above and have to be borne by the prospective buyers at the time of the taking over of the possession of the their flats. 7. Timely payment by the buyers and timely completion of the project by the builder is the essence of this agreement. 8. The proposed date of completion of the project is 31/05/2021.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES/IMPORTED MARBLE
2WALL FINISHING DETAILSGYPSUM PLASTER WITH ACRYLIC EMULSION PAINT
3KITCHEN DETAILSVITRIFIED TILES FLOOR, 2 1/2 FT HEIGHT TILES ON THE WALLS ABOVE GRANITE COUNTER AND REST GYPSUM PLASTER. GYPSUM PLASTER WITH ACRYLIC PAINT ON CEILING. PROVISION FOR CHIMNEY, HOP, REFRIGERATOR, MICROWAVE
4BATHROOM FITTINGSCERAMIC/VITRIFIED TILES FLOORING, TILES AND GYPSUM PLASTER WITH ACRYLIC EMULSION PAINT ON WALLS. ACRYLIC EMULSION PAINT ON CEILING. MARBLE/GRANITE COUNTERS WITH WASH BASINS
5WOOD WORK ETCHARDWOOD FRAMED VENEER/LEMINATE FINISHED FLUSH DOORS.
6DOORS AND WINDOS FRAMESENGINEERED FRAMES WITH VENEER FINISH
7GLASS WORKAS PER DESIGN - ISI MAKE
8ELECTRIC FITTINGSMODULAR SWITCHES OF BRANDS LIKE LEGRAND, CRAB TREE OR EQUIVALENT
9CONDUCTING AND WIRING DETAILSALL ISI MAKE WIRES AND MCBS.
10CUPBOARD DETAILSNIL
11WATER STORAGENIL
12LIFT DETAILSNIL
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSALUMINUM/UPVC DOORS AND WINDOWS
14DOORSNA
14.1MAIN DOORSALUMINUM/UPVC/GLASS DOORS
14.2INTERNAL DOORSHARDWOOD FRAMED VENEER/LAMINATE FINISHED FLUSH DOORS
15AIR CONDITIONINGSPLIT AC - DAIKIN/VOLTAS
16ELECTRICAL FITTINGSMODULAR SWITCHES OF BRANDS LIKE LEGRAND - CRABTREE OR EQUIVALENT
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMECEMENT PLASTER WITH TEXTURE PAINT
20INTERNAL FINISHINGGYPSUM PLASTER WITH ACRYLIC EMULSION PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND03-01-2019 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN03-01-2019 View Document
3DEMARCATION PLAN03-01-2019 View Document
4ZONING PLAN03-01-2019 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN03-01-2019 View Document
6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS03-01-2019 View Document
7NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT03-01-2019 View Document
8IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN03-01-2019 View Document
9CASH FLOW STATEMENT OF THE PROPOSED PROJECT27-02-2019 View Document
10CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT27-02-2019 View Document
11DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD26-02-2019 View Document
12DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.26-02-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 PROJECT CONTINUATION- RC/REP/HARERA/GGM/17 OF 2019/7(3)/35/2023/12 DATED 07.06.2023 04-07-2023 View Document