HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1755-2025
Submission Date : 05-08-2025 12:05:44 PM
Applicant Type : Company
Project Type: NEW




SPICE ONE BUILDERS PVT LTD
8D, HANSALYA, 15, BARAKHAMBHA ROAD
9540968345 (Number Shared by Promoter in Public)
sales@onecity.in
http://onegroup.co.in
XXXX548P
U45201DL2005PTC139209
 
 


 
 


 
 


 
 


 
 







ONE CITY
SECTOR-27A, DELHI ROAD, ROHTAK
SAMPLA
ROHTAK
9215688533 (Number Shared by Promoter in Public)
SALES@ONECITY.IN
DEVENDER
1123358617
9215688533 (Number Shared by Promoter in Public)
SALES@ONECITY.IN








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11046828-07-202541500HDFC BANKHRERA Panchkula







2.05 (Acre)
0
0
2.05 (Acre)
95 of 2025 (10-06-2025)
Yes







525.9888 Lakhs
153.9888 Lakhs
0 Lakhs
200 Lakhs
172 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 5296.8
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1878.2
4PAVEMENTS 219
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 902
12ANY OTHER 0
Total8296




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYUHBVNYes
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS45.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM49.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE11.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM71.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL17.00AS PER PROJECT REPORT
6STREET LIGHTING7.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


10-06-2025 (date)
NA (date)
26-07-2025
09-08-2028
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 75.10 1
2 79.95 4
3 82.72 1
4 86.97 1
5 90.35 1
6 91.16 5
7 92.70 5
8 96.75 10
9 97.98 1
10 103.39 1
11 106.41 5
12 109.35 8
13 123.68 1
14 128.17 5
15 136.80 1
Total50


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.75000
Water Supply System4.08333
Sewerage treatment & garbage disposal1.41667
Electricity Supply System5.91667
Storm Water Drainage0.91667
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
STREET LIGHTING0.58333

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.750003.750003.750003.75000
Water Supply System4.083334.083334.083334.08333
Sewerage treatment & garbage disposal1.416671.416671.416671.41667
Electricity Supply System5.916675.916675.916675.91667
Storm Water Drainage0.916670.916670.916670.91667
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING0.583330.583330.583330.58333

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.750003.750003.750003.75000
Water Supply System4.083334.083334.083334.08333
Sewerage treatment & garbage disposal1.416671.416671.416671.41667
Electricity Supply System5.916675.916675.916675.91667
Storm Water Drainage0.916670.916670.916670.91667
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING0.583330.583330.583330.58333

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.750003.750003.75000
Water Supply System4.083334.083334.08333
Sewerage treatment & garbage disposal1.416671.416671.41667
Electricity Supply System5.916675.916675.91667
Storm Water Drainage0.916670.916670.91667
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
STREET LIGHTING0.583330.583330.58333












Yes
No
HDFC BANK, B-7/3 ASAF ALI ROAD, NEW DELHI 110002
50200082105653
HDFC0000598
110250019
598
UDIT JAIN, C-479, DEFENCECOLONY, NEW DELHI-110024
No Default











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED10-06-2025
II. DEMARCATION CUM ZOINING PLANALREADY BEEN OBTAINED25-07-2025
III. SERVICE PLAN/ ESTIMATE APPROVALAPPLIED FOR BUT YET TO RECEIVENA
IV. UHBVN APPROVALYET TO FILE FOR APPROVALNA








Yes


Yes


1. 10% of the sale price to be paid as the booking amount by the allottee. 2. Name and particulars of the allottee along with contact details. 3. Area, location and price of the plot. Also, states the external electrification, sewer connection and water connection charges and IFMS to be paid by the allottee. 4. Ownership details of project land. 5. Possession of the plot unit will be given on complete payment by the allottee when sale deed is registered in the name of the allottee. 6. Payment Plan clearly mentions the timeline of payment to be made by the allottee. 7. The agreement will be registered with Sub-Registrar office, Tehsil Sampla and will be binding on both parties.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEN.A.
2WALL FINISHING DETAILSN.A.
3KITCHEN DETAILSN.A.
4BATHROOM FITTINGSN.A.
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESN.A.
7GLASS WORKN.A.
8ELECTRIC FITTINGSN.A.
9CONDUCTING AND WIRING DETAILSN.A.
10CUPBOARD DETAILSN.A.
11WATER STORAGEN.A.
12LIFT DETAILSN.A.
13EXTERNAL GLAZINGSN.A.
13.1WINDOWS/GLAZINGSN.A.
14DOORSN.A.
14.1MAIN DOORSN.A.
14.2INTERNAL DOORSN.A.
15AIR CONDITIONINGN.A.
16ELECTRICAL FITTINGSN.A.
17CNG PIPE LINEN.A.
18PROVISION OF WIFI AND BROADBAND FACILITYN.A.
19EXTERNAL FINISHING/COLOUR SCHEMEN.A.
20INTERNAL FINISHINGN.A.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN.A.
1 . 2 WALLSN.A.
1 . 3 CEILINGN.A.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN.A.
2 . 2 WALLSN.A.
2 . 3 CEILINGN.A.
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORN.A.
3 . 2 WALLSN.A.
3 . 3 CEILINGN.A.
3 . 4 COUNTERSN.A.
3 . 5 SANITARY WARE/CP FITTINGSN.A.
3 . 6 FITTING/FIXTURESN.A.
4 . BED ROOMS
4 . 1 FLOORN.A.
4 . 2 WALLSN.A.
4 . 3 CEILINGN.A.
4 . 4 WARDROBESN.A.
5 . TOILET
5 . 1 FLOORN.A.
5 . 2 WALLSN.A.
5 . 3 CEILINGN.A.
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSN.A.
5 . 6 FIXTURESN.A.
6 . KITCHEN
6 . 1 FLOORN.A.
6 . 2 WALLSN.A.
6 . 3 CEILINGN.A.
6 . 4 COUNTERSN.A.
6 . 5 FIXTURESN.A.
6 . 6 KITCHEN APPLIANCESN.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A.
7 . 2 WALLS & CEILINGN.A.
7 . 3 TOILETN.A.
7 . 4 BALCONYN.A.
8 . SIT-OUTS
8 . 1 FLOORN.A.
8 . 2 WALLS & CEILINGN.A.
8 . 3 RAILINGSN.A.
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1 DEMARCATION PLAN 01-08-2025 View Document
2 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 05-08-2025 View Document
3 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 01-08-2025 View Document
4 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 01-08-2025 View Document
5 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 01-08-2025 View Document
6 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 26-07-2025 View Document
7 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 01-08-2025 View Document
8 ZONING PLAN 01-08-2025 View Document
9 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 05-08-2025 View Document