HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-385-2019
Submission Date : 16-04-2019 12:55:31 PM
Applicant Type : Firm
Project Type: ONGOING


AGRASAIN SPACES LLP
A-59, SECTOR -11, FARIDABAD 121006
01294054330
9999987330 (Number Shared by Promoter in Public)
agrasainspacesllp@gmail.com
AAD6477
ABCFA0837E















AAGMAN
SECTOR 70 FARIDABAD
BALLABGARH
FARIDABAD
9999028142 (Number Shared by Promoter in Public)
agrasainspacesllp@gmail.com
R B SINGH
9999028142 (Number Shared by Promoter in Public)
rbsingh6060@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1015-02-201900000ABCDHRERA Panchkula
284552219-06-2017541300ORIENTAL BANK OF COMMERCEHRERA Panchkula
39377928-06-2017433100HDFC BANKHRERA Panchkula







5.35 (Acre)
225
2.242
5.35 (Acre)
13 OF 2015
Yes







13000 Lakhs
640 Lakhs
9110 Lakhs
850 Lakhs
2400 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3462.04
3CONSTRUCTION OF ROADS6006
4PAVEMENTS1000
5PARKS AND PLAYGROUNDS3255
6GREEN BELTS600
7VEHICLE PARKINGS3744
8ELECTRICITY SUB-STATION100
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY366
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER1735
13COMMUNITY360
14AAGANWADI190
15COMMERCIAL832
Total21650.04




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSAS PER MASTER PLANNo
WATER SUPPLYHUDANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS215YET TO BE PREPARED
2WATER SUPPLY SYSTEM150YET TO BE PREPARED
3STORM WATER DRAINAGE65YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM5YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL130YET TO BE PREPARED
6STREET LIGHTING15YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING50YET TO BE PREPARED
8PLAYGROUNDS AND PARKS5YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA215YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


13-02-2019 (date)
13-02-2019 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE A58.46922422404
2APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE A'49.17622422404
3APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE B48.80013613603
4APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE B139.453686803
5APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE B239.788686803






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TYPE A -A'-B-B1-B2720ANNEXED


01-07-2016
30-09-2019
30-09-2019
01-05-2018
95
30-09-2019
ATTACHED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NIL
01-06-2018
95
30-09-2019
GIVEN
30/09/2019


0
0
0
391
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1000
Shops0
Plots0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments600
Shops0
Plots0

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments600600600600
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments110600600600
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements500025
Water Supply System40000
Sewerage treatment & garbage disposal30000
Electricity Supply System0000
Storm Water Drainage15000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area150025
Other250050

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0505040
Water Supply System0504020
Sewerage treatment & garbage disposal0404020
Electricity Supply System010100
Storm Water Drainage0202010
Parks and Playgrounds0050
Clubhouse/community centres0000
Shopping area0757550
Other0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Particulars Remarks, if any
i. No. of Flats/Apartments constructed736
ii. No. of Flats/ Apartments booked0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application1275 Lakhs
Land cost (If any)640 Lakhs
Apartments35 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.600 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession11725 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project11725 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS2160
II. WATER SUPPLY SYSTEM2000
III. STORM WATER DRAINAGE600
IV. ELECTRICITY SUPPLY SYSTEM250
V. SEWAGE TREATMENT & GARBAGE DISPOSAL1300
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER1430
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.50
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
AXIS BANK, SECTOR 7 FARIDABAD
919020030117906
UTIB0000039
110211005
039
HIMANSHU GUPTA H NO 632, SECTOR 21 A, FARIDABAD
ATTACHED











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENCEALREADY BEEN OBTAINED20-06-2018
II. FOREST NOCNOCALREADY BEEN OBTAINED12-11-2018
III. AAI NOCALREADY BEEN OBTAINED30-01-2019
IV. BR IIIALREADY BEEN OBTAINED13-02-2019
V. ENVIRONMENT CLEARANCEAPPLIED FOR BUT YET TO RECEIVENA








Yes


Yes









AGRASAIN SPACES LLP SECTOR 70 FARIDABAD
5.35
720
0
720
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
12300123008084
Cost of the apartments10920109206941
Cost of the infrastructure740740500
Others costs640640640


5931 Lakhs
9945.42 Lakhs
0 Lakhs
0 Lakhs
No
30-09-2019
30-09-2019










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE IN DRAWING/ DINING/ BEDROOM CERAMIC TILE IN TOILET/ BALCONY AREA
2WALL FINISHING DETAILSOBD ON CEMENT PLASTER ON WALL & CEILING
3KITCHEN DETAILSSS SINK SINGLE BOWL, CHROME PLATED BIB COCK
4BATHROOM FITTINGSONE ENGLISH SEAT, ONE WASH BASIN, CHROME PLATED BIB COCK
5WOOD WORK ETCENAMEL PAINTED FLUSH SHUTTER WITH MS HARDWARES
6DOORS AND WINDOS FRAMES MS/UPVC PROFILE SECTION
7GLASS WORKIN EXTERNAL WINDOW
8ELECTRIC FITTINGSPIANO TYPE SWITCH & SOCKET
9CONDUCTING AND WIRING DETAILSPVC CONCEALED CONDUITING & COPPER WIRING
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGEHALF DAY CAPACITY IN COMMON OVER HEAD RCC TANK
12LIFT DETAILS12 NOS IN SIX NO TOWER (2 NOS LIFT IN EACH TOWER)
13EXTERNAL GLAZINGSNOT APPLICABLE
13.1WINDOWS/GLAZINGSUPVC/ MS WINDOW SHUTTER WITH GLASS PANES
14DOORSENAMEL PAINTED FLUSH SHUTTER
14.1MAIN DOORSENAMEL PAINTED FLUSH SHUTTER
14.2INTERNAL DOORSENAMEL PAINTED FLUSH SHUTTER
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSSTRANDED PIANO TYPE SWITCH & SOCKET ONLY. FIXTURE NOT APPLICABLE
17CNG PIPE LINEPROVISION MADE IN THE FLATS
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMEFINE TEXTURE FINISH ON CEMENT PLASTER IN COLOUR PATTERN
20INTERNAL FINISHINGPLEASING SHADE IN OIL BOUND DISTEMBER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSOIL BOUND DISTEMPER OVER CEMENT PLASTER
1 . 3 CEILINGOIL BOUND DISTEMPER OVER CEMENT PLASTER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILE
2 . 2 WALLSOIL BOUND DISTEMPER OVER CEMENT PLASTER
2 . 3 CEILINGOIL BOUND DISTEMPER OVER CEMENT PLASTER
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILE
3 . 2 WALLSGLAZED CERAMIC TILE 2100 MM HIGH
3 . 3 CEILINGGRID FALSE CEILING
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSONE WASH BASIN, ONE ENGLISH SEAT, STANDARD CHROME PLATED BIB COCK
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILE
4 . 2 WALLSOIL BOUND DISTEMPER OVER CEMENT PLASTER
4 . 3 CEILINGOIL BOUND DISTEMPER OVER CEMENT PLASTER
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORCERAMIC TILE
5 . 2 WALLSGLAZED CERAMIC TILE 2100 MM HIGH
5 . 3 CEILINGGRID FALSE CEILING
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSONE WASH BASIN, ONE ENGLISH SEAT, STANDARD CHROME PLATED BIB COCK
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILE
6 . 2 WALLSGLAZED TILE 600MM HIGH
6 . 3 CEILINGOIL BOUND DISTEMPER OVER CEMENT PLASTER
6 . 4 COUNTERSGRANITE STONE
6 . 5 FIXTURESONE BOWL SS SINK, STANDARD CHROME PLATED BIB COCK
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILE
7 . 2 WALLS & CEILINGOIL BOUND DISTEMPER OVER CEMENT PLASTER
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYMILS STEEL ENAMEL PAINTED RAILING, CERAMIC TILE IN FLOOR
8 . SIT-OUTS
8 . 1 FLOORVITRIFIED TILE
8 . 2 WALLS & CEILINGOIL BOUND DISTEMPER OVER CEMENT PLASTER
8 . 3 RAILINGSMILS STEEL ENAMEL PAINTED
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN28-03-2019 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND28-03-2019 View Document
3A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS28-03-2019 View Document
4DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.28-03-2019 View Document
5CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT04-02-2019 View Document
6NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT04-02-2019 View Document
7DEMARCATION PLAN04-02-2019 View Document
8ZONING PLAN04-02-2019 View Document
9IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN04-02-2019 View Document
10DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD04-02-2019 View Document
11SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN28-03-2019 View Document
12CASH FLOW STATEMENT OF THE PROPOSED PROJECT15-04-2019 View Document