HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1738-2025
Submission Date : 02-07-2025 11:33:45 AM
Applicant Type : Firm
Project Type: NEW


LRH REALITY LLP
4257 BUDH NAGAR TRI,NAGAR ,NEAR MOTHER DAYRI, KESHAV PURAM, NORTH WEST DELHI, DELHI,110035
9254034735 (Number Shared by Promoter in Public)
lrhllp2024@gmail.com
ACC8839
AALFL0623P















TYCOON INDUSTRIAL PARK
VILLAGE BUPANIA
BADLI
JHAJJAR
9254034735 (Number Shared by Promoter in Public)
lrhllp2024@gmail.com
SAURABH GUPTA
9212574726 (Number Shared by Promoter in Public)
lrhllp2024@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1434930-05-2025272000HDFC BANK LIMITED HRERA Panchkula







11.85 (Acre)
1
1
11.85 (Acre)
License No 07 of 2025 granted by DTCP Haryana dated 13-01-2025
Yes







2333.43 Lakhs
590.00 Lakhs
0.00 Lakhs
1631.99 Lakhs
111.44 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 6.9190
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 4.2227
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.2634
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13COMMERCIAL AREA 0.4449
Total11.85




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS521.36AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM66.24AS PER PROJECT REPORT
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM242.97AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING5.78AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15FEATURED WALL GUARD METER ROOM169.73AS PER PROJECT REPORT
16 RETAINING WALL87.58AS PER PROJECT REPORT
17 EXTERNAL PLUMBING WORK187.11AS PER PROJECT REPORT
18STP93.22AS PER PROJECT REPORT
19UNDER GROUND WATER TANK AND STP CIVIL WORK 257.99AS PER PROJECT REPORT


15-01-2025 (date)
NA (date)
01-07-2025
31-12-2029
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 1771.4610 3
2 392.5192 4
3 882.9000 6
4 1288.4725 3
5 419.2000 1
6 612.4800 1
7 703.7524 2
8 605.9046 11
9 1041.0855 1
10 1047.2460 1
11 760.5355 1
Total34


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.2017.34
Water Supply System0.000.00
Sewerage treatment & garbage disposal00
Electricity Supply System0.000.00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Featured Wall Guard Meter Room
STREET LIGHTING0.000.00
STP0.000.00
Under ground water tank and STP civil work12.567.90
External Plumbing Work0.002.30
Retaining Wall4.233.67

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements27.5337.2437.4838.82
Water Supply System0.000.000.000.00
Sewerage treatment & garbage disposal0000
Electricity Supply System0.004.998.9814.76
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Retaining Wall2.784.764.906.82
STREET LIGHTING0.301.051.100.80
Featured Wall Guard Meter Room7.298.899.65
STP0.003.653.784.42
External Plumbing Work3.803.608.408.67
Under ground water tank and STP civil work7.8012.4017.8518.86

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements38.7347.9746.8927.77
Water Supply System6.345.789.875.60
Sewerage treatment & garbage disposal0000
Electricity Supply System19.9912.8718.9717.45
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STP4.903.342.323.98
Featured Wall Guard Meter Room8.908.5911.96
Retaining Wall4.214.786.714.61
External Plumbing Work8.479.6712.7613.40
Under ground water tank and STP civil work17.8218.2023.9425.73
STREET LIGHTING0.001.17
STREET LIGHT POLE1.36

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements29.7545.5035.5022.50
Water Supply System6.138.405.104.23
Sewerage treatment & garbage disposal0000
Electricity Supply System17.7921.4020.4522.35
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Under ground water tank and STP civil work22.7120.2512.824.89
STREET LIGHTING0.000.000.00
STP9.8912.654.766.89
Featured Wall Guard Meter Room11.4012.2012.30
External Plumbing Work14.9016.9022.1018.20
Retaining Wall4.775.204.254.21

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements27.6211.2011.4212.20
Water Supply System6.154.123.211.31
Sewerage treatment & garbage disposal0000
Electricity Supply System25.7623.456.986.78
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Under ground water tank and STP civil work6.988.907.456.93
Featured Wall Guard Meter Room14.409.208.56
Retaining Wall4.785.915.875.12
External Plumbing Work15.3412.769.106.74
STREET LIGHTING0.000.000.000.00
STP7.438.989.456.78

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements05.80
Water Supply System0.000.00
Sewerage treatment & garbage disposal00
Electricity Supply System0.000.00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
STP2.12
Under ground water tank and STP civil work5.67
External Plumbing Work0.00
Featured Wall Guard Meter Room2.39
Retaining Wall3.41












Yes
No
HDFC BANK ,PEERAGARHI, , DELHI
50200111893487
HDFC0001127
110240131
001127
NEERAJ RUHIL, R/O 1177 NEAR SECTOR 6 SHOPPING CENTER SECTOR 6 BAHADURGARH JHAJJAR HARYANA 124507
NON DEFAULTED CERTIFICATE UPLOADED IN DOCUMENT UPLOAD SECTION











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. DEMARCATION CUM ZONING PLANALREADY BEEN OBTAINED12-05-2025
II. LAYOUT PLANALREADY BEEN OBTAINED15-01-2025








Yes


Yes


The provision of RERA Act and Rules shall be incorporated in the draft agreements.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.01-07-2025 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN27-06-2025 View Document
3COPY OF LICENSE ALONG WITH SCHEDULE OF LAND26-06-2025 View Document
4IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN27-06-2025 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT27-06-2025 View Document