UNIT NO.101,GROUNDFLOOR,TOWER-A,SIGNATURETOWER SOUTH CITY-1,GURUGRAM, HARYANA-122001
911244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
https://www.signatureglobal.in
XXXX807M
L70100DL2000PLC104787
SIGNATUREGLOBAL CLOVERDALE SPR
VILLAGE - FAIZALPUR JHARSA, SECTOR-71, GURUGRAM, HARYANA
BADSHAHPUR ST
GURUGRAM
911244908200
9810899381 (Number Shared by Promoter in Public)
compliance@sigantureglobal.in
RAVI AGGARWAL
911244908200
9520785681 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
32025052000000221
20-05-2025
1282785
INDUSIND BANK
HRERA Gurugram
2
32025040400828152
04-04-2025
4049263
INDUSIND BANK
HRERA Gurugram
3
32025040400828157
04-04-2025
1286362
INDUSIND BANK
HRERA Gurugram
8.12 (Acre)
3.15
3.15
22.50 (Acre)
09 of 2010 Dated 23.01.2010 Renewed up to 22.01.2030
Yes
222812.94 Lakhs
48713.66 Lakhs
129373.58 Lakhs
1597.35 Lakhs
43128.35 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.9857
3
CONSTRUCTION OF ROADS
2.3167
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
3.711
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0.1638
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0.254
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.500
12
ANY OTHER
0.1081
13
COMMERCIAL
0.0807
Total
8.12
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
GMDA (CONNECTED)
No
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
No
STORM WATER DRAINAGE
GMDA (OWN ARRANGEMENT)
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
299.74
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
516.40
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
150.06
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
241.85
YET TO BE PREPARED
6
STREET LIGHTING
31.16
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
26.66
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MS CHARGES
331.48
SUBMITTED TO TOWN & COUNTRY PLANNING
NA (date)
21-05-2025 (date)
01-06-2025
31-05-2031
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
167.834
70
1
Apartment/Shops/Other Buildings
118.523
280
2
Apartment/Shops/Other Buildings
108.523
420
3
Apartment/Shops/Other Buildings
29.237
2
1
Apartment/Shops/Other Buildings
219.502
22
2
Apartment/Shops/Other Buildings
18.638
43
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
1500.00
3500.00
3500.00
Shops
0
0
0
Plots
0
0
0
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
3500.00
5000.00
5000.00
5000.00
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
7500.00
7500.00
7500.00
2500.00
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
4000.00
4000.00
4000.00
6000.00
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
6000.00
4000.00
4000.00
4000.00
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
5000.00
5000.00
8000.00
8000.00
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
9000.00
6373.58
0
Shops
0
0
0
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
31.708
Water Supply System
0
0
0
130.38
Sewerage treatment & garbage disposal
0
0
0
61.062
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
37.887
Parks and Playgrounds
0
0
0
4.486
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Light
5.245
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
58.635
58.635
100.904
31.708
Water Supply System
155.646
155.646
59.094
15.634
Sewerage treatment & garbage disposal
72.895
72.895
27.676
7.322
Electricity Supply System
0
0
0
0
Storm Water Drainage
45.229
45.229
17.172
4.543
Parks and Playgrounds
8.032
8.032
4.486
0.807
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Light
6.096
6.096
7.132
3.296
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
18.15
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0.817
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Light
3.296
Ms Charges
331.48
Yes
No
STANDARD CHARTERED BANK LIMITED, DLF GURGAON BUILDING NO. 7A, GROUND FLOOR, DLF CYBER CITY, PHASE-3, SECTOR 24/25/25A, GURUGRAM, HARYANA-122002
53105138376
SCBL0036025
110036006
036025
Master collection account namely "SIGNATUREGLOBAL INDIA LTD SIGNATURE GLOBAL CLOVERDALE SPR A/C" will be operated by Mr. Mr.Pradeep Kumar Aggarwal andLalit Aggarwal R/oAashirwad, Palam Farm 6, Salahapur,Bijwasan,South West Delhi-110061
ATTACHED
No
No
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. TRANSFER OF LICENSE
ALREADY BEEN OBTAINED
29-04-2024
II. ENVIRONMENTAL CLEARANCE
ALREADY BEEN OBTAINED
03-01-2025
III. AIRPORT HEIGHT CLEARANCE
ALREADY BEEN OBTAINED
09-03-2024
IV. POWER ASSURANCE
ALREADY BEEN OBTAINED
23-05-2024
V. SEWERAGE ASSURANCE
ALREADY BEEN OBTAINED
26-04-2024
VI. STP ASSURANCE
ALREADY BEEN OBTAINED
26-04-2024
VII. WATER ASSURANCE
ALREADY BEEN OBTAINED
26-04-2024
VIII. BR-III
ALREADY BEEN OBTAINED
21-05-2025
Yes
Yes
Attached
SIGNATURE GLOBAL IMPERIAL,SECTOR88A, GURUGRAM
8.93125
1141
0
1141
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
23392.40
0
12500.67
Cost of the apartments
17929.10
0
8770.09
Cost of the infrastructure
200
0
0
Others costs
5263.3
0
3730.58
16870.88 Lakhs
305644 Lakhs
0 Lakhs
0 Lakhs
No
28-02-2026
28-02-2026
SIGNATURE GLOBAL PRIME,SECTOR 63A, GURUGRAM
5.74375
817
0
817
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
17567.70
0
17280.41
Cost of the apartments
11825.26
0
12334.9
Cost of the infrastructure
599.25
0
28.13
Others costs
5143.19
0
4917.38
21158.91 Lakhs
556430 Lakhs
0 Lakhs
0 Lakhs
No
28-04-2025
28-04-2025
GOLF GREEN 79, SECTOR79,GURUGRAM
5.9125
934
0
934
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
16816.27
0
17131.02
Cost of the apartments
10290
0
10537.50
Cost of the infrastructure
500
0
500
Others costs
6026.27
0
6093.52
20293.87 Lakhs
5689.66 Lakhs
0 Lakhs
0 Lakhs
No
31-07-2024
31-07-2024
SIGNATURE GLOBAL SCO-36SOHNA,SECTOR 36, SOHNA,GURUGRAM
5.21875
0
84
0
84
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6590.41
0
5398.68
Cost of the apartments
0
0
0
Cost of the infrastructure
823
0
823.02
Others costs
5767.41
0
4575.66
9971.02 Lakhs
3953.13 Lakhs
0 Lakhs
0 Lakhs
No
28-06-2025
28-06-2025
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
MARBLE/VITRIFIED TILES/ PORCELEIN TILES
2
WALL FINISHING DETAILS
ACRYLIC EMULSION PAINT/OBD
3
KITCHEN DETAILS
MARBLE/VITRIFIED TILES/ PORCELEIN TILES
4
BATHROOM FITTINGS
AS PER INDIAN STANDARD/ HINDWARE/ PARRYWARE EQUIVALENT
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT