HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1957-2025
Submission Date : 17-05-2025 05:51:07 PM
Applicant Type : Company
Project Type: NEW




NBSAM CONSTRUCTION PRIVATE LIMITED
F-136, JAWAHAR PARK, KHANPUR, DELHI, INDIA, 110062
8800393306
8800393306 (Number Shared by Promoter in Public)
info@nbsamc.com
https://nbsamc.com
XXXX862A
U45201DL2005PTC143267
 
 


 
 


 
 







NAMAH
SECTOR - 11 SOHNA GURUGRAM
SOHNA
GURUGRAM
8800393306
8800393306 (Number Shared by Promoter in Public)
info@nbsamc.com
SANJAY
8800393306
8800393306 (Number Shared by Promoter in Public)
info@nbsamc.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
187192509-05-2025610000FEDERAL BANKHRERA Gurugram







7.3875 (Acre)
100
100
7.3875 (Acre)
28 of 2023 dated 09/02/2023.
No
Address     W4D, 204/5, KESHAV KUNJ CARIAPPA MARG, WESTERN AVENUE, SAINIK FARM, SOUTH DELHI, INDIA 110062
Annexure-B- COLLABORATION AGREEMENT
YES
Yes
COLLABORATION AGREEMENT ATTACHED
No
Yes
Yes







13128.69 Lakhs
6500 Lakhs
0 Lakhs
2010.00 Lakhs
4618.69 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 4.8020
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.5699
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total5.3719




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTED Yes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS250.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM150.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE150.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM175.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL150.00AS PER PROJECT REPORT
6STREET LIGHTING150.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS75.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM50.00AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15PARKING OPEN25.00AS PER PROJECT REPORT
16STP100.00AS PER PROJECT REPORT
17UNDERGROUND WATER TANK85.00AS PER PROJECT REPORT
18RAIN WATER HARVESTING50.00AS PER PROJECT REPORT
19ELECTRICAL SUB STATION150.00AS PER PROJECT REPORT
20SITE ESTABLISHMENT AND INFRASTRUCTURE COST 450.00AS PER PROJECT REPORT


10-02-2023 (date)
NA (date)
01-06-2025
31-12-2029
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 149 9
2 108.5 36
3 122.714 6
4 100.050 43
5 90 1
6 99.75 1
7 99.75 1
8 119 5
9 125.609 14
10 105 9
11 105.87 1
12 83.820 1
13 145.580 6
14 123.360 6
15 104.775 4
16 134 1
17 1190.70 1
Total145


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements25.0025.0025.00
Water Supply System15.0015.0015.00
Sewerage treatment & garbage disposal15.0015.0015.00
Electricity Supply System000
Storm Water Drainage15.0015.0015.00
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
Site Establishment and Infrastructure Cost45.0045.0022.50

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements25.0025.0025.0025.00
Water Supply System15.0015.0015.0015.00
Sewerage treatment & garbage disposal15.0015.0015.0015.00
Electricity Supply System0000
Storm Water Drainage15.0015.0015.0015.00
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Site Establishment and Infrastructure Cost22.5022.5022.5022.50

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements25.0025.0012.5012.50
Water Supply System15.0015.007.507.50
Sewerage treatment & garbage disposal15.0015.007.507.50
Electricity Supply System17.5017.5017.5017.50
Storm Water Drainage15.0015.007.507.50
Parks and Playgrounds7.507.507.507.50
Clubhouse/community centres0000
Shopping area0000
Other0000
Street lighting15.0015.0015.0015.00
Rain Water Harvesting5.005.005.005.00
Underground Water Tank8.508.508.508.50
Parking open2.502.502.502.50
Site Establishment and Infrastructure Cost22.5022.5022.5022.50

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System17.5017.5035.0035.00
Storm Water Drainage0000
Parks and Playgrounds7.507.5015.0015.00
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting5.005.0010.0010.00
Street lighting15.0015.0030.0030.00
Underground Water Tank8.508.5017.0017.00
Site Establishment and Infrastructure Cost22.5022.5022.5022.50
Parking open2.502.505.005.00

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
STP40.0040.0020.00
Electrical Sub Station60.0060.0030.00
Renewable energy system20.0020.0010.00
Site Establishment and Infrastructure Cost22.5022.5022.50












Yes
Yes
FEDERAL BANK, ADDRESS - MALVIYA NAGAR, NEW DELHI - 110017
16770200005221
FDRL0001677
110049025
001677
NAYAN N RAHEJA ADDRESS C/o - REGUS CENTRE SAKET PRIVATE LIMITED, RECTANGLE NO. - 1, D - 4, DISTRICT CENTRE, COMMERCIAL COMPLEX, SAKET, NEW DELHI - 110017
YES











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LOIALREADY BEEN OBTAINED21-10-2022
II. LICENSE ALREADY BEEN OBTAINED09-02-2023
III. LAYOUT PLANALREADY BEEN OBTAINED10-02-2023
IV. FOREST NOC ALREADY BEEN OBTAINED28-03-2025
V. ASSURANCE OF SEWERAGEALREADY BEEN OBTAINED21-03-2025
VI. ASSURANCE OF WATER SUPPLYALREADY BEEN OBTAINED21-03-2025
VII. ASSURANCE FOR STORM WATERALREADY BEEN OBTAINED21-03-2025
VIII. SERVICE ESTIMATE PLANAPPLIED FOR BUT YET TO RECEIVE03-02-2025








Yes


Yes


As per Norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 ELECTRICAL LOAD AVAILABILITY CONNECTION 13-05-2025 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 09-05-2025 View Document
3 AKS-SHAJRA 13-05-2025 View Document
4 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 16-05-2025 View Document
5 NCZ UNDERTAKING 17-05-2025 View Document
6 ZONING PLAN 13-05-2025 View Document
7 MUTATION 13-05-2025 View Document
8 JAMABANDI 13-05-2025 View Document
9 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 16-05-2025 View Document
10 ROC 13-05-2025 View Document
11 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 14-05-2025 View Document
12 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 09-05-2025 View Document
13 INFORMATION TO REVENUE DEPARTMENT 13-05-2025 View Document
14 DEMARCATION PLAN 16-05-2025 View Document
15 SEWERAGE ASSURANCE 13-05-2025 View Document
16 DEMAND DRAFT 14-05-2025 View Document
17 BALANCE SHEET 2023 14-05-2025 View Document
18 LICENSE 13-05-2025 View Document
19 BALANCE SHEET 2022 14-05-2025 View Document
20 NON-ENCUMBRANCE CERTIFICATE 13-05-2025 View Document
21 FOREST NOC 13-05-2025 View Document
22 WATER ASSURANCE 13-05-2025 View Document
23 STROM ASSURANCE 13-05-2025 View Document
24 BALANCE SHEET 2021 13-05-2025 View Document
25 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 16-05-2025 View Document
26 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 17-05-2025 View Document
27 LC-IV 13-05-2025 View Document
28 SERVICE PLANS AND ESTIMATES APPROVAL / SANCTION LETTER ONLY 13-05-2025 View Document
29 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 16-05-2025 View Document
30 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 16-05-2025 View Document
31 AFFIDAVIT 4(2)(L)(D) 17-05-2025 View Document
32 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 16-05-2025 View Document
33 LOI 13-05-2025 View Document