5TH FLOOR, BMG CITY CENTRE, ELEGANT CITY, SECTOR - 26, GARHI BOLNI ROAD, REWARI - 123 401, HARYANA
01274298005
9812301020 (Number Shared by Promoter in Public)
ecity@bmggroupindia.com
http://www.bmggroupindia.com
XXXX204B
U45400HR2008PTC103627
BMG ANTRIKSH COMMERCIAL C1(FIRST FLOOR)
VILLAGE DHAMLAKA, SECTOR - 26, REWARI - 123401, HARYANA
REWARI
REWARI
01274298005
9812301020 (Number Shared by Promoter in Public)
ecity@bmggroupindia.com
ARPIT GUPTA
01274298005
9812301020 (Number Shared by Promoter in Public)
arpit@bmggroupindia.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
0
29-04-2025
1270
ICICI BANK LIMITED
HRERA Panchkula
0.239 (Acre)
175 for Commercial
175
5.975 (Acre)
73 of 2014 dated 01-08-2014 renewed up to 26-09-2025 against which RERA Registration No 89 of 2017 dated 23-08-2017 hranted by HRERA Panchkula for which OC has been received from DTCP Haryana and new RERA Registration applied for Commercial C1 (FF) for which additional FAR approved by DTCP Haryana
Yes
956.54 Lakhs
0.00 Lakhs
327.96 Lakhs
583.03 Lakhs
45.55 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0.00
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1692.66
3
CONSTRUCTION OF ROADS
0.00
4
PAVEMENTS
0.00
5
PARKS AND PLAYGROUNDS
0.00
6
GREEN BELTS
0.00
7
VEHICLE PARKINGS
0.00
8
ELECTRICITY SUB-STATION
0.00
9
CLUB HOUSE
0.00
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.00
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.00
12
ANY OTHER
0.00
Total
1692.66
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
Yes
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
0
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
0
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
0
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
0
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
AS PER PROJECT REPORT
6
STREET LIGHTING
0
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
0
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
04-05-2023 (date)
04-05-2023 (date)
01-11-2022
25-06-2028
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
18.00
1
1
Apartment/Shops/Other Buildings
18.48
2
1
Apartment/Shops/Other Buildings
18.52
1
1
Apartment/Shops/Other Buildings
20.89
2
1
Apartment/Shops/Other Buildings
20.92
2
1
Apartment/Shops/Other Buildings
21.54
2
1
Apartment/Shops/Other Buildings
21.61
2
1
Apartment/Shops/Other Buildings
21.67
2
1
Apartment/Shops/Other Buildings
25.94
1
1
Apartment/Shops/Other Buildings
26.94
1
1
Apartment/Shops/Other Buildings
27.06
1
1
Apartment/Shops/Other Buildings
27.82
1
1
Apartment/Shops/Other Buildings
27.83
1
1
Apartment/Shops/Other Buildings
30.79
1
1
Apartment/Shops/Other Buildings
31.00
1
1
Apartment/Shops/Other Buildings
31.08
1
1
Apartment/Shops/Other Buildings
32.10
1
1
Apartment/Shops/Other Buildings
32.35
1
1
Apartment/Shops/Other Buildings
33.00
2
1
Apartment/Shops/Other Buildings
36.18
1
1
Apartment/Shops/Other Buildings
37.21
1
1
Apartment/Shops/Other Buildings
37.40
2
1
Apartment/Shops/Other Buildings
37.52
1
1
Apartment/Shops/Other Buildings
37.60
1
1
Apartment/Shops/Other Buildings
37.79
1
1
Apartment/Shops/Other Buildings
38.24
2
1
Apartment/Shops/Other Buildings
38.27
1
1
Apartment/Shops/Other Buildings
38.47
1
1
Apartment/Shops/Other Buildings
38.52
1
1
Apartment/Shops/Other Buildings
38.53
1
1
Apartment/Shops/Other Buildings
31.59
1
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
327.96
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
105.92
80.08
50.84
Plots
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
58.30
Plots
0
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
58.30
58.30
58.30
58.30
Plots
0
0
0
0
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
58.30
58.30
58.30
58.30
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
Shops
29.15
29.15
Plots
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
6.56
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
12.76
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
2.92
2.92
2.92
2.92
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
2.92
2.92
2.92
2.92
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
1.45
1.45
Yes
No
ICICI BANK, SCO 114 AND 115, BRASS MARKET, SECTOR 1, REWARI, 123401
777705975405
ICIC0000626
400485111
000626
1. Radhey Shyam Gupta 2. Vijay Kumar Gupta 3. Ripu Dama Gupta 4. Ravi Shanker Gupta 5. Ankit Gupta 6. Arpit Gupta C/o 5th Floor, BMG City Centre, Elegant City Sector-26, Garhi Bolni Road, Rewari - 123401
CA AAKASH S PARKASH & COMPANY Certificate Uploaded
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
No
Yes
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 73 OF 2014
ALREADY BEEN OBTAINED
01-08-2014
II. ELECTRIFICATION PLAN
ALREADY BEEN OBTAINED
13-05-2021
III. SERVICE PLAN ESTIMATE VIDE MEMO NO. 21218
ALREADY BEEN OBTAINED
20-07-2022
IV. OCCUPANCY CERTIFICATE FOR TOWER-01, TOWER-02, TOWER-03 & 04 AND BASEMENT VIDE MEMO NO. 31254
ALREADY BEEN OBTAINED
14-10-2022
V. REVISED BUILDING PLAN OF COMMERCIAL C1 & C2 VIDE MEMO NO. 12868
ALREADY BEEN OBTAINED
04-05-2023
VI. PART OCCUPANCY CERTIFICATE FOR COMMERCIAL C1 (GROUND FLOOR) & C2 VIDE MEMO NO. 31512
ALREADY BEEN OBTAINED
21-09-2023
Yes
Yes
EDC and IDC is included in the Basic Cost, Interest Free Maintenance Charges to be charged extra
BMG ASPIRE (ELEGANT HEIGHTS - PHASE II)
4865.62
27
0
14
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
3492.31
0
3039.98
Cost of the apartments
2337.03
0
1957.41
Cost of the infrastructure
245.77
0
184.11
Others costs
909.51
0
898.46
1825.96 Lakhs
974.04 Lakhs
800 Lakhs
664 Lakhs
No
10-07-2023
31-12-2025
BMG NIRVAAN (AFFORDABLE RESIDENTIAL PLOTTED COLONY UNDER DDJAY-2016)
12.198
0
197
0
84
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1452.89
0
1374.89
Cost of the apartments
0
0
0
Cost of the infrastructure
823.37
0
771.56
Others costs
629.52
0
603.33
1629.28 Lakhs
270.67 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2022
31-12-2023
BMG ELEGANT CITY (ADDITIONAL)
4.8125
0
44
0
8
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1412.62
0
226.88
Cost of the apartments
0
0
0
Cost of the infrastructure
418.72
0
33.89
Others costs
993.90
0
192.99
231.64 Lakhs
104.36 Lakhs
0 Lakhs
0 Lakhs
No
25-06-2028
25-06-2028
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT