HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1588-2024
Submission Date : 23-12-2024 10:09:24 AM
Applicant Type : Company
Project Type: NEW




M/S JMK BUILDCON PVT LTD
UNIT NO 912, TOWER B, EMAAR DIGITAL GREENS, SECTOR - 61, GURUGRAM, HARYANA - 122011
01244488063
8178464761 (Number Shared by Promoter in Public)
admin@jmkbuild.in
https://www.jmkbuild.in
XXXX458L
U70109HR2010PTC041267
 
 


 
 


 
 


 
 


 
 







GREEHAA FLOORS PHASE III
POCKET L, SECTOR 8, MODEL ECONOMIC TOWNSHIP (MET CITY), VILLAGE YAKUBPUR
BADLI
JHAJJAR
8052331298 (Number Shared by Promoter in Public)
admin@jmkbuild.in
SUNIL KUMAR YADAV
8052331298 (Number Shared by Promoter in Public)
admin@jmkbuild.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151564712-12-202410000ICICI BANKHRERA Panchkula
251566326-11-202430000ICICI BANK HRERA Panchkula







0.27 (Acre)
2.64
2.63
1016.10 (Acre)
LICENSE NO 16 OF 2018 DATED 23.02.2018 VALID UPTO 22.02.2028, LICENSE NO. 11 OF 2021 DATED 12.03.2021 VALID UPTO 11.03.2025, LICENSE NO. 06 OF 2012 DATED 01.02.2012 VALID UPTO 31.01.2025 ISSUED BY DTCP HARYANA
Yes







1476.66 Lakhs
340.66 Lakhs
1050 Lakhs
0 Lakhs
126 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1094.80
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total1094.8




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSPWDYes
WATER SUPPLYMETLYes
ELECTRICITYUHBVNYes
SEWAGE DISPOSALIRRIGATION DEPARTMENT HARYANAYes
STORM WATER DRAINAGEIRRIGATION DEPARTMENT HARYANAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0YET TO BE PREPARED
2WATER SUPPLY SYSTEM0YET TO BE PREPARED
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


21-10-2024 (date)
21-10-2024 (date)
15-01-2025
31-07-2026
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings64.20400





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
LAND COST340.66

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments150150150150
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments150150150
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2026)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
ICICI BANK SHOP NO 19,20 AND 21 VIPUL ORCHID PLAZA SECTOR 54, GURUGRAM - 122002
777705007745
ICIC0000399
110229060
00399
DIPAK CHARABORTY R/O KALKA PUBLIC SCHOOL, 59, GANGA APARTMENTS, 2ND FLOOR, ALAKNANDA, NEW DELHI AND PANKAJ KUMAR R/O APARTMENT NO 803, TOWER F, BPTP PARK PRIME, SECTOR 66, SOUTH CITY II, GURUGRAM - 122018
UPLOADED











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. BUILDING PLANS FROM DTP JHAJJARALREADY BEEN OBTAINED21-10-2024








Yes


Yes


ANNEXED AS PER THE RERA ACT, 2016 AND RULES MADE THEREUNDER







GREEHAA FLOORS PHASE I, POCKET L, SECTOR 8, MODEL ECONOMIC TOWNSHIP TEHSIL BADLI JHAJJAR
1094.80
40
10
40
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1034.221034.221034.22
Cost of the apartments800800800
Cost of the infrastructure000
Others costs234.22234.22234.22


1547.68 Lakhs
59.10 Lakhs
0 Lakhs
0 Lakhs
No
14-01-2024
14-01-2025




GREEHAA FLOORS PHASE II, POCKET L, SECTOR 8, MODEL ECONOMIC TOWNSHIP TEHSIL BADLI JHAJJAR
1254.69
30
10
30
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1254.691254.69964.34
Cost of the apartments772772481.58
Cost of the infrastructure000
Others costs234.22234.22161.28


809.84 Lakhs
315.15 Lakhs
0 Lakhs
0 Lakhs
No
17-05-2025
17-05-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITIRIFIED GLAZED TILES
2WALL FINISHING DETAILSTEXTURED PAINT WEATHER RESISTENT AND PLASTIC PAINT
3KITCHEN DETAILSCOUNTER TOP FOR KITCHEN, SINGLE BOWL, STAINLESS STEEL SINK (AS PER SPACE), CERAMIC TILES (2FT ABOVE COUNTER AND 5 FT ABOVE FLOOR ON NON COUNTER WALLS
4BATHROOM FITTINGSKEROVIT BY KAJARIA AND THE LIKES, COUNTER TOP FOR BASIN.
5WOOD WORK ETCWOOD WORK BOTH UNDER AND ABOVE COUNTER, WARDROBE IN TWO OF THE BEDROOMS
6DOORS AND WINDOS FRAMES32 MM THICK FLUSH DOOR WITH BOTH SIDE LAMINATION-FLUSH DOOR, COMMERCIAL FLUSH DOOR PAINTED WITH ENAMEL PAINT AND UPVC WINDOWS
7GLASS WORKUPVC
8ELECTRIC FITTINGSCOPPER ELECTRIC WIRING IN CONDUIT
9CONDUCTING AND WIRING DETAILSPOWER POINTS, TV AND PHONE SOCKETS WITH MCBS, MODULAR SWITCHES INCLUDING 16 AMP SWITCH/SOCKET IN EACH ROOM, AC SOKET IN BEDROOMS AND LIVING ROOM
10CUPBOARD DETAILSWARDROBE IN TWO BEDROOMS
11WATER STORAGEPVC TANK
12LIFT DETAILSECE INDUSTRIES LTD
13EXTERNAL GLAZINGSNIL
13.1WINDOWS/GLAZINGSUPVC
14DOORSWOODEN FLUSH DOOR
14.1MAIN DOORSWOODEN FLUSH DOOR
14.2INTERNAL DOORSWOODEN FLUSH DOOR
15AIR CONDITIONINGNIL
16ELECTRICAL FITTINGSLED BULBS, MODULAR FANS, EXHAUST FANS, CHIMNEY, GAS STOVE, GEYSER, ETC
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYNIL
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURED PAINT WEATHER RESISTENT
20INTERNAL FINISHINGPLASTIC PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED GLAZED TILES
1 . 2 WALLSPLASTIC PAINT
1 . 3 CEILINGPLASTIC PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED GLAZED TILES
2 . 2 WALLSPLASTIC PAINT
2 . 3 CEILINGPLASTIC PAINT
2 . 4 MODULAR WARDROBESYES
3 . MASTER TOILET
3 . 1 FLOORANTI SKID WITH CERAMIC TILES
3 . 2 WALLSPLASTIC PAINT
3 . 3 CEILINGPLASTIC PAINT
3 . 4 COUNTERSCOUNTER TOP FOR BASIN
3 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS SUCH AS WATER TAP, BASIN MIXER, WALL MIXER AND SHOWER HEAD
3 . 6 FITTING/FIXTURESCP FITTINGS SUCH AS WATER TAP, BASIN MIXER, WALL MIXER AND SHOWER HEAD
4 . BED ROOMS
4 . 1 FLOORVITRIFIED GLAZED TILES
4 . 2 WALLSPLASTIC PAINT
4 . 3 CEILINGPLASTIC PAINT
4 . 4 WARDROBESYES
5 . TOILET
5 . 1 FLOORANTI SKID WITH CERAMIC TILES
5 . 2 WALLSPLASTIC PAINT
5 . 3 CEILINGPLASTIC PAINT
5 . 4 COUNTERSCOUNTER TOP FOR BASIN
5 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS SUCH AS WATER TAP, BASIN MIXER, WALL MIXER AND SHOWER HEAD
5 . 6 FIXTURESCP FITTINGS SUCH AS WATER TAP, BASIN MIXER, WALL MIXER AND SHOWER HEAD
6 . KITCHEN
6 . 1 FLOORANTI SKID WITH CERAMIC TILES
6 . 2 WALLSPLASTIC PAINT
6 . 3 CEILINGPLASTIC PAINT
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESCERAMIC TILES 2 FT AND ABOVE COUNTER AND 5 FT ABOVE FLOOR ON NON COUNTER WALLS
6 . 6 KITCHEN APPLIANCESGAS STOVE, CHIMNEY, EXHAUST FANS, LED BULBS
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI SKID WITH CERAMIC TILES
7 . 2 WALLS & CEILINGTEXTURED PAINT WEATHER RESISTENT
7 . 3 TOILETNIL
7 . 4 BALCONYSS RAILING IN FRONT OF BALCONY AND MS RAILING IN BACK BALCONY
8 . SIT-OUTS
8 . 1 FLOORNIL
8 . 2 WALLS & CEILINGNIL
8 . 3 RAILINGSNIL
8 . 4 FIXTURESNIL












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN17-12-2024 View Document
2PROPOSED BUILDING PLAN PLOT NO-55721-12-2024 ------
3PROPOSED BUILDING PLAN PLOT NO-54921-12-2024 ------
4PROPOSED BUILDING PLAN PLOT NO-55621-12-2024 ------
5PROPOSED BUILDING PLAN PLOT NO-55321-12-2024 ------
6IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN17-12-2024 View Document
7COPY OF LICENSE ALONG WITH SCHEDULE OF LAND20-12-2024 View Document
8PROPOSED BUILDING PLAN PLOT NO-55521-12-2024 ------
9NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT19-12-2024 View Document
10A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS20-12-2024 View Document
11PROPOSED BUILDING PLAN PLOT NO-54821-12-2024 ------
12PROPOSED BUILDING PLAN PLOT NO-55121-12-2024 ------
13DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.20-12-2024 View Document
14CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT19-12-2024 View Document
15PROPOSED BUILDING PLAN PLOT NO-55021-12-2024 ------
16PROPOSED BUILDING PLAN PLOT NO-55221-12-2024 ------
17PROPOSED BUILDING PLAN PLOT NO-55421-12-2024 ------