9090336000 (Number Shared by Promoter in Public)
info@yashvibuilders.com
XXXX794P
U45203HR2022PTC100375
GOLDEN GATE RESIDENCY- II
SECTOR-3 , FARRUKHNAGAR
FARRUKHNAGAR
GURUGRAM
7056200765 (Number Shared by Promoter in Public)
info@yashvibuilders.com
MUKAL RAO
7056200765 (Number Shared by Promoter in Public)
mukulyadav5may1998@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
6637
28-11-2024
352000
IDBI BANK
HRERA Gurugram
5.7188 (Acre)
1
1
5.7188 (Acre)
136 of 2024 dated 04.11.2024
No
Address H.NO- 549, NEAR DR. YADAV CLINIC, JHARSA, GURUGRAM, HARYANA-122001
Address H.NO- 549, NEAR DR. YADAV CLINIC, JHARSA, GURUGRAM, HARYANA-122001
Annexure-B- COLLABORATION
YES
Yes
COLLABORATION AGREEMENT ATTACHED
No
Yes
Yes
5962.23 Lakhs
3317.85 Lakhs
0 Lakhs
911.06 Lakhs
1733.32 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.4884
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
0.9962
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.4333
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.5721
12
ANY OTHER
0
13
COMMERCIALBLOCK
0.2287
Total
5.7187
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
139.66
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
181.82
YET TO BE PREPARED
3
STORM WATER DRAINAGE
85.56
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
200
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
YET TO BE PREPARED
6
STREET LIGHTING
21.94
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
5.43
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
162.51
YET TO BE PREPARED
06-11-2024 (date)
NA (date)
01-01-2025
31-07-2029
Plot Area(In Square Meter)
Number of plots in the project
144.200
7
124.100
9
114.273
1
141.462
14
140.820
1
132.936
8
118.878
8
95.154
16
150.00
2
142.800
40
873.43
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)