HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1781-2024
Submission Date : 08-05-2025 01:04:50 PM
Applicant Type : Company
Project Type: NEW




DLF LIMITED
3RD FLOOR, SHOPPINGMALL, ARJUN MARG, DLF PHASE 1, GURUGRAM 122001 HARYANA
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in
XXXX494N
L70101HR1963PLC2484
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







DLF PRIVANA NORTH
SECTOR 76/77
MANESAR
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
YUDHVEER SINGH
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
152471516-04-202510127000ICICI BANKHRERA Gurugram







17.701 (Acre)
2.62
1.89
116.29625 (Acre)
219 of 2023 granted by DTCP valid till 24.10.2028
No
Address     3RD FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR DLF GATEWAY TOWER R BLOCK DLF CITY PHASE - III DLF QE GURUGRAM-122002, HARYANA
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     SUMMERLEAS NO. 19 GADAIPUR BANDH ROAD NEW DELHI 110030
Address     416 4TH FLOOR DLF QUTUB PLAZA COMPLEX DLFCITY PHASE-I GURUGRAM 122002
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     416 4TH FLOOR DLF QUTUB PLAZA COMPLEX DLFCITY PHASE-I GURUGRAM 122002
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     VILLAGE SHIKOHPUR TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE WAZIRABAD TEHSIL DISTRICT GURUGRAM
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Annexure-B- ANNEXURE B
YES
Yes
ANNEXURE B
No
Yes
Yes







545734.69 Lakhs
62708.52 Lakhs
425227.57 Lakhs
22380.40 Lakhs
35418.20 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 2.89
3CONSTRUCTION OF ROADS 3.138
4PAVEMENTS 2.851
5PARKS AND PLAYGROUNDS 2.523
6GREEN BELTS 0
7VEHICLE PARKINGS 0.25
8ELECTRICITY SUB-STATION 0.62
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.22
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 4.989
13UGT 0.22
Total17.701




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYGMDAYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS3357.06AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM1119.02AS PER PROJECT REPORT
3STORM WATER DRAINAGE1119.02AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM4028.47AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL1119.02AS PER PROJECT REPORT
6STREET LIGHTING447.61AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS4252.28AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER1566.63AS PER PROJECT REPORT
15EARTH WORK1119.02AS PER PROJECT REPORT
16SEWERAGE SYSTEM2238.04AS PER PROJECT REPORT
17UGT1119.02AS PER PROJECT REPORT
18RAIN WATER HARVESTING895.22AS PER PROJECT REPORT


NA (date)
07-05-2025 (date)
01-07-2025
31-03-2034
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings207.70311526
Apartment/Shops/Other Buildings450.333126





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0935.501403.25
Shops000
Plots000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2338.752338.753274.254677.50
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments8504.5512799.3515605.8512714.30
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments19347.8521261.3821261.3817476.85
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments21729.1321729.1322196.8815605.85
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments20325.8819858.1317519.3813734.85
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments17519.3817519.3816031.089865.28
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments15138.1011353.58113547569
Shops0000
Plots0000

ParticularsYear-2033
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments7059565647633274
Shops0000
Plots0000

ParticularsYear-2034
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1488
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System000168
Sewerage treatment & garbage disposal00168168
Electricity Supply System0403403403
Storm Water Drainage000168
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other00313313
Sewerage System000336
Rain Water Harvesting134134134134
Earth Work00280280
UGT00168168

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements671671671671
Water Supply System168168168168
Sewerage treatment & garbage disposal168168168168
Electricity Supply System403403403403
Storm Water Drainage168168168168
Parks and Playgrounds850850850850
Clubhouse/community centres0000
Shopping area0000
Other3133133130
Earth Work280280
Street Light90909090
Rain Water Harvesting13413490
UGT168168168168
Sewerage System336336336336

ParticularsYear-2033
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements671000
Water Supply System112565656
Sewerage treatment & garbage disposal112000
Electricity Supply System403201201201
Storm Water Drainage112565656
Parks and Playgrounds850000
Clubhouse/community centres0000
Shopping area0000
Other0000
UGT112000
Sewerage System224112112112
Street Light90000

ParticularsYear-2034
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System201
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Yes
No
VATIKA ATRIUM, BLOCK A, GOLF COURSE ROAD, SECTOR 53 GURGRAON
57500001683356
HDFC0000572
110240093
572
Mr. Badal Bagri 148, Birch Court, Nirvana Country, Sector 50 Gurgaon, Mr. Sanjay Goenka F-222, Park Place, DLF5, DLF Golf Course Sector 54 Gurgaon, Mr. Puneet Rakheja H.No. 386, Sector 31, Faridabad, Haryana 121003, Mr. Pankaj Kumar Jain C-701, Apex Acacia Valley, Near Shoppix Mall, Sector 3, Vaishali, Ms. Sandhya Singla Neelanchal Apartments, Plot No. 3, Sector 4, Dwarka, Delhi 110075, Mr. Gaurav Arora A-33, Near Mehfil Banquet Hall, Mahendru Enclave, GT Karnal Road, Delhi 110009, Mr. Ashok Nanda A255, Surya Nagar, Chander Nagar, Ghaziabad, Uttar Pradesh 201011, Mr. Sujeet Kumar Sinha C-061, DLF New Town Heights, IMT Manesar, Sector 91, Gurgaon, Haryana 122505, Mr. Pankaj Kumar A-3, Rajcottage 1/18. Rajendra Nagar Ganga banquet Hall, Sahibabad, UP 201005, Mr. Sunil Sharma C-28, Second Floor, WZ-62-A/2, Near Ring Road, Sharda Puri, Ramesh Nagar, West Delhi, Delhi-110015, Mr. Himanshu Garg E-301 Block E, Ardee City Gate No. 2, Sector 52, Wazirabad, Gurgaon,
Attached in Folder D











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LETTER OF INTENTALREADY BEEN OBTAINED08-09-2023
II. LICENSEALREADY BEEN OBTAINED25-10-2023
III. ELECTRIC LOAD ASSURANCEALREADY BEEN OBTAINED10-01-2024
IV. WATER ASSURANCEALREADY BEEN OBTAINED06-10-2023
V. STROM WATER ASSURANCEALREADY BEEN OBTAINED11-10-2024
VI. SEWERAGE ASSURANCEALREADY BEEN OBTAINED11-10-2024
VII. WATER FOR CONSTRUCTIONALREADY BEEN OBTAINED18-12-2024
VIII. ENVIROMENTAL CLERANCE ALREADY BEEN OBTAINED20-02-2025
IX. REVISED PHASING PLANALREADY BEEN OBTAINED06-05-2025
X. REVISED DEMARCATION CUM ZONINGALREADY BEEN OBTAINED06-05-2025
XI. BUILDING PLAN APPROVALALREADY BEEN OBTAINED07-05-2025








Yes


Yes


As per RERA Act







GARDENCITY ARCADE, GURGAON
1.42
99
1
99
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6309.1962234950.19
Cost of the apartments4162.2846673709.83
Cost of the infrastructure000
Others costs2146.9115561240.36


6935.16 Lakhs
2537.40 Lakhs
0 Lakhs
5881 Lakhs
No
29-04-2025
29-04-2025




DLF GARDENCITY ENCLAVE, GURGAON
26.91875
0
367
0
119
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1199951972705.91
Cost of the apartments473832411240
Cost of the infrastructure000
Others costs726119561465.91


11164.63 Lakhs
2648.09 Lakhs
0 Lakhs
2871.84 Lakhs
No
29-03-2024
28-03-2025




INDEPENDENT FLOORS AT DLFGARDENCITY ENCLAVE, GURGAON
3.5698
388
97
388
97
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
234682892616618.59
Cost of the apartments183452661415086.26
Cost of the infrastructure136700
Others costs375623121532.33


20622.65 Lakhs
34805.50 Lakhs
0 Lakhs
17409.39 Lakhs
No
19-08-2027
19-08-2027




DLF GARDENCITY ENCLAVE PH2, GURGAON
5.0105
544
136
536
134
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
406063884414802.81
Cost of the apartments338923603012671.98
Cost of the infrastructure000
Others costs671428142130.83


31080.10 Lakhs
54192.41 Lakhs
0 Lakhs
15967.74 Lakhs
No
30-10-2028
30-10-2028




SUMMIT PLAZA SECTOR-54, GURUGRAM, HARYANA
2.65
311
1
311
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
23537.963471219947
Cost of the apartments15098.333228617859
Cost of the infrastructure000
Others costs8439.6324262088


5735 Lakhs
5329 Lakhs
0 Lakhs
20615 Lakhs
No
30-06-2026
30-06-2026




THE GROVE DLF 5, SECTOR-54, GURUGRAM, HARYANA
5.3073
292
73
292
73
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
47346.175435035593
Cost of the apartments38532.095247834143
Cost of the infrastructure000
Others costs8814.0818721450


143502 Lakhs
133888.48 Lakhs
0 Lakhs
54829 Lakhs
No
31-12-2025
31-12-2025




DLF PRIVANA SOUTH, SECTOR-77, GURGAON, HARYANA
25.148
1113
0
1113
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
341550.0934758232873.54
Cost of the apartments319728.9931399317001.18
Cost of the infrastructure000
Others costs21821.103358915872.36


257431 Lakhs
668186.28 Lakhs
0 Lakhs
43659 Lakhs
No
30-06-2031
30-06-2031




DLF PRIVANA WEST, SECTOR-77, GURGAON, HARYANA
12.572
795
0
795
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
27930025824323910
Cost of the apartments25208923007712573
Cost of the infrastructure000
Others costs272112816611337


146569 Lakhs
507573.69 Lakhs
0 Lakhs
30503 Lakhs
No
31-12-2031
31-12-2031




DLF CLUB ARCADE, SECTOR 91, GURGAON, HARYANA
0.89
72
0
49
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
44274549.28190.75
Cost of the apartments25752704.50181.70
Cost of the infrastructure000
Others costs18521844.789.05


580.86 Lakhs
4642.86 Lakhs
0 Lakhs
191 Lakhs
No
31-03-2028
31-03-2028




THE DAHLIAS, GURGAON, HARYANA
16.489
420
0
173
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
61334262415424368
Cost of the apartments60835361914419635
Cost of the infrastructure000
Others costs498950104733


132959 Lakhs
1227542.79 Lakhs
0 Lakhs
28799 Lakhs
No
31-12-2031
31-12-2031










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILES/MARBLE/GRANITE/LAMINATED WOODEN
2WALL FINISHING DETAILSOBD/SEMI ACRYLIC/ACRYLIC EMULSION/TILES
3KITCHEN DETAILSMODULAR KICTHEN WITH APPLIANCES ASPERPOINT 6.6 CABINETRY AND SS SINK
4BATHROOM FITTINGSCP FITTINGS, WASH BASIN, FLOOR MOUNTED /WALL HUNG WCS
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESMS/UPVC/ALWOOD/COMPOSITION MATERIAL
7GLASS WORKFROSTED / CLEAR GLASS
8ELECTRIC FITTINGSSWITCH BOX AND SOCKETS
9CONDUCTING AND WIRING DETAILSPVC CONDUCTS, FR WIRING
10CUPBOARD DETAILSMODULAR WARDROBES
11WATER STORAGEOHT & UGT WATER TANKS
12LIFT DETAILSBRANDED MAKE
13EXTERNAL GLAZINGSUPVC/ALUMUNIUM
13.1WINDOWS/GLAZINGSSAME AS POINT 13
14DOORSMAIN DOOR INTERNAL DOORS
14.1MAIN DOORSWOODEN FIRE RESISTANT FLUSH DOOR
14.2INTERNAL DOORSWOODEN FLUSH DOOR
15AIR CONDITIONINGIN LIVING, DINING & BEDROOMS
16ELECTRICAL FITTINGSSAME AS POINT 8
17CNG PIPE LINEGAS PIPE LINE PROVISION ONLY
18PROVISION OF WIFI AND BROADBAND FACILITYPROVISION ONLY
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR GRADED PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORMARBLE /TILES
1 . 2 WALLSACRYLIC EMULSION / OBD
1 . 3 CEILINGACRYLIC EMULSION / OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING/MARBLE /TILES
2 . 2 WALLSACRYLIC EMULSION / OBD
2 . 3 CEILINGACRYLIC EMULSION / OBD
2 . 4 MODULAR WARDROBESMODULAR WARDROBES
3 . MASTER TOILET
3 . 1 FLOORTILES / MARBLE / GRANITE
3 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSIONPAINT &MIRROR;
3 . 3 CEILINGACRYLIC EMULSION PAINT
3 . 4 COUNTERSMARBLE / GRANITE / SYNTHETIC STONE
3 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, WC, TOWELRAIL/RING,TOILET PAPER HOLDER
3 . 6 FITTING/FIXTURESEXHAUST FAN, GEYSER
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING/MARBLE/TILE
4 . 2 WALLSACRYLIC EMULSION PAINT / OBD
4 . 3 CEILINGACRYLIC EMULSION PAINT / OBD
4 . 4 WARDROBESMODULAR WARDROBES
5 . TOILET
5 . 1 FLOORMARBLE / GRANITE / TILES
5 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSIONPAINT
5 . 3 CEILINGACRYLIC EMULSION PAINT
5 . 4 COUNTERSGRANITE / MARBLE / SYNTHETIC STONE
5 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, WC, TOWELRAIL/RING,TOILET PAPER HOLDER
5 . 6 FIXTURESEXHAUST FAN, GEYSER
6 . KITCHEN
6 . 1 FLOORTILES/GRANITE
6 . 2 WALLSTILES UP-TO 2’ ABOVE COUNTER & EMULSIONPAINTIN BALANCE AREA
6 . 3 CEILINGACRYLIC EMULSION PAINT
6 . 4 COUNTERSMARBLE / GRANITE /SYNTHETIC STONE
6 . 5 FIXTURESCP FITTINGS, SS SINK, EXHAUST FAN
6 . 6 KITCHEN APPLIANCESHOB, CHIMNEY,OVEN,MICROWAVE,DISHWASHER,REFRIDGERATOR,GEYSER,WASHING MACHINE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGOBD/SEMI ACRYLIC/TILES
7 . 3 TOILETCP FITTINGS, WASH BASIN, WC
7 . 4 BALCONYTILES/CEMENT BASED EXTERIOR GRADE PAINT
8 . SIT-OUTS
8 . 1 FLOORTILES
8 . 2 WALLS & CEILINGEXTERIOR GRADE PAINTS
8 . 3 RAILINGSMS/SS/AL/GLASS
8 . 4 FIXTURESCEILLING LIGHTS












Sr. No.Document DescriptionDate of Document UploadView Document
1 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 08-04-2025 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 08-04-2025 View Document
3 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 08-04-2025 View Document
4 DEMARCATION PLAN 08-04-2025 View Document
5 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 08-04-2025 View Document
6 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 08-04-2025 View Document
7 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 08-04-2025 View Document
8 ZONING PLAN 08-04-2025 View Document
9 FINAL NO CHARGE CERTIFICATE 04-06-2025 ------
10 TYPICAL RAIN WATER HARVESTING PLAN 04-06-2025 ------
11 50TH PENTH HOUSE FLOOR (TOWER B&D) 04-06-2025 ------
12 SECTION 1-1 (TOWER B AND D) 04-06-2025 ------
13 ASSURANCE CERTIFICATE - STORM WATER CONNECTION 04-06-2025 ------
14 BR-III 04-06-2025 ------
15 17TH,35TH & 44TH REFUGE PLAN (TOWER A&C) 04-06-2025 ------
16 DLF PRIVANA ACCOUNTS LETTER_08.05.2025 04-06-2025 ------
17 DA NO 3998 DT 23.06.2023 -14.06 ACS KHERKI DAULA (NADISH TO DLF LTD) PRIVANA 04-06-2025 ------
18 COST INCURRED CERTIFICATE 04-06-2025 ------
19 LETTER ZP AND PHASING 04-06-2025 ------
20 PHASING PLAN 04-06-2025 ------
21 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 29-04-2025 View Document
22 TYPICAL FLOOR PLAN (TOWER E) 04-06-2025 ------
23 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 29-04-2025 View Document
24 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 29-04-2025 View Document
25 DA NO 3999 DT 23.06.2023 -6.25 ACS KHERKI DAULA (NAJA ESTATES TO DLF LTD) PRIVANA 04-06-2025 ------
26 ARAVALI NOC FOR 113.696 ACRES LAND 04-06-2025 ------
27 ASSURANCE CERTIFICATE - WATER SUPPLY 04-06-2025 ------
28 BASEMENT 2 AREA CALULATION 04-06-2025 ------
29 CONSTRUCTION PERT CHART 04-06-2025 ------
30 AAI NOC- POCKET 1 - POCKET 7 04-06-2025 ------
31 ELEVATION 03 (TOWER A,C&E) 04-06-2025 ------
32 BASEMENT AREA 3 CALCULATION 04-06-2025 ------
33 DRAFT APPLICATION FORM - PRIVANA NORTH 04-06-2025 ------
34 LETTER OF INTENT (LC-III) 04-06-2025 ------
35 GROUND COVERAGE AREA (TOWER B&D), GROUND COVERAGE TOWER F 04-06-2025 ------
36 BASEMENT 2 04-06-2025 ------
37 TREE FELLING PERMISSION 04-06-2025 ------
38 LEGAL SEARCH - PRIVANA NORTH 04-06-2025 ------
39 SECTION 2-2 (TOWER B AND D) 04-06-2025 ------
40 ELEVATION 02 (TOWER A,C&E) 04-06-2025 ------
41 TYPICAL FLOOR PLAN TOWER F 04-06-2025 ------
42 BASEMENT 1 ONLY FOR SERVICES 04-06-2025 ------
43 ROOF PLAN TOWER F 04-06-2025 ------
44 BASEMENT 1 04-06-2025 ------
45 REFUGEE FLOOR PLAN TOWER F 04-06-2025 ------
46 ELEVATION 03 (TOWER F) 04-06-2025 ------
47 NEC 04-06-2025 ------
48 ASSURANCE CERTIFICATE - SEWERAGE 04-06-2025 ------
49 NO DUES CERTIFICATE 04-06-2025 ------
50 GROUND FLOOR PLAN (TOWER C) 04-06-2025 ------
51 BASEMENT 1 AREA CALCULATION 04-06-2025 ------
52 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 04-06-2025 View Document
53 SCHEMATIC TOWER A-F 04-06-2025 ------
54 50TH PENTH HOUSE (TOWER A&C) 04-06-2025 ------
55 STILT GF PLAN (TOWER D) 04-06-2025 ------
56 ESTIMATE COST INCURRED CERTIFICATE 04-06-2025 ------
57 TYPICAL FLOOR PLAN (TOWER B & D) 04-06-2025 ------
58 STILT & GF PLAN (TOWER B) 04-06-2025 ------
59 17TH,35TH & 44TH REFUGE PLAN (TOWER E) 04-06-2025 ------
60 CTE PRIVANA NORTH 04-06-2025 ------
61 ELEVATION 01 (TOWER A,C &E) 04-06-2025 ------
62 ELEVATION 1(TOWER B AND D) 04-06-2025 ------
63 SECTION 02 (TOWER A,B&C) 04-06-2025 ------
64 GF AREA (TOWER D), GF AREA CALCULATION (TOWER B), GF AREA PLAN (TOWER E) 04-06-2025 ------
65 SERVICES PERT CHART 04-06-2025 ------
66 BASEMENT 3 04-06-2025 ------
67 DRAFT AGREEMENT FOR SALE 04-06-2025 ------
68 SA NO 4240 DT 28.06.2023 -6.97 ACS KHERKI DAULA (VIKRAM TO DLF LTD) PRIVANA 04-06-2025 ------
69 STILT AND GROUND FLOOR AREA TOWER F 04-06-2025 ------
70 TERRACE PLAN AREA -TOWER A&C, TOWER B&D, TOWER E,TOWER F 04-06-2025 ------
71 17TH, 35TH & 44 REFUGE FLOOR (TOWER B&D) 04-06-2025 ------
72 26TH REFUGE FLOOR (TOWER B&D) 04-06-2025 ------
73 26TH REFUGE FLOOR (TOWER E) 04-06-2025 ------
74 26TH REFUGE PLAN (TOWER A&C) 04-06-2025 ------
75 50TH PENTH HOUSE FLOOR (TOWER E) 04-06-2025 ------
76 ARAVALI NOC FOR 15.67 ACRES LAND 04-06-2025 ------
77 CONSTRUCTION WATER NOC 04-06-2025 ------
78 DA NO 4397 DT 03.07.2023 -0.43 ACS KHERKI DAULA (MILDA TO DLF LTD) PRIVANA 04-06-2025 ------
79 DRAFT DLF PRIVANA NORTH - PAYMENT RECEIPT 04-06-2025 ------
80 DRAFT CONVEYANCE DEED - PRIVANA NORTH 04-06-2025 ------
81 ELEVATION 2& 4 (TOWER B AND D) 04-06-2025 ------
82 ELEVATION 3 (TOWER B AND D) 04-06-2025 ------
83 ELECTRIC LOAD 04-06-2025 ------
84 ELEVATION 01 (TOWER F) 04-06-2025 ------
85 ELEVATION 2&4 (TOWER F) 04-06-2025 ------
86 FOREST NOC CONSOLIDATE 04-06-2025 ------
87 GREEN AREA & SURFACE CAR PARKING CALCULATION 04-06-2025 ------
88 GROUND FLOOR AREA (TOWER A) 04-06-2025 ------
89 PENTH HOUSE TOWER F 04-06-2025 ------
90 REFUGEE FLOOR 2 TOWER F 04-06-2025 ------
91 STILT FLOOR PLAN TOWER F 04-06-2025 ------
92 LMR PLAN WATER TANK ROOF PLAN -TOWER B&D, TOWER E, TOWER A&C 04-06-2025 ------
93 SECTION 01 (TOWER A,B&C) 04-06-2025 ------
94 SECTION 2 (TOWER F) 04-06-2025 ------
95 SECTION 2-2 (TOWER F) 04-06-2025 ------
96 STILT GF PLAN (TOWER E) 04-06-2025 ------
97 STILT GROUND FLOOR PLAN (TOWER C) 04-06-2025 ------
98 STILT_GF PLAN (TOWER A) 04-06-2025 ------
99 SURFACE PARKING AREA 04-06-2025 ------
100 TYPICAL FLOOR PLAN (TOWER A & C) 04-06-2025 ------