HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1781-2024
Submission Date : 08-05-2025 01:04:50 PM
Applicant Type : Company
Project Type: NEW




DLF LIMITED
3RD FLOOR, SHOPPINGMALL, ARJUN MARG, DLF PHASE 1, GURUGRAM 122001 HARYANA
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in
XXXX494N
L70101HR1963PLC2484
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







DLF PRIVANA NORTH
SECTOR 76/77
MANESAR
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
YUDHVEER SINGH
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
152471516-04-202510127000ICICI BANKHRERA Gurugram







17.701 (Acre)
2.62
1.89
116.29625 (Acre)
219 of 2023 granted by DTCP valid till 24.10.2028
No
Address     3RD FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR DLF GATEWAY TOWER R BLOCK DLF CITY PHASE - III DLF QE GURUGRAM-122002, HARYANA
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE KHERKIDHAULA TEHSIL MANESAR DISTRICT GURUGRAM
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     SUMMERLEAS NO. 19 GADAIPUR BANDH ROAD NEW DELHI 110030
Address     416 4TH FLOOR DLF QUTUB PLAZA COMPLEX DLFCITY PHASE-I GURUGRAM 122002
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     416 4TH FLOOR DLF QUTUB PLAZA COMPLEX DLFCITY PHASE-I GURUGRAM 122002
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Address     VILLAGE SHIKOHPUR TEHSIL MANESAR DISTRICT GURUGRAM
Address     VILLAGE WAZIRABAD TEHSIL DISTRICT GURUGRAM
Address     1ST FLOOR ARJUN MARG SHOPPING MALL COMPLEX DLF CITY DLF PHASE-1 GURUGRAM, HARYANA
Annexure-B- ANNEXURE B
YES
Yes
ANNEXURE B
No
Yes
Yes







545734.69 Lakhs
62708.52 Lakhs
425227.57 Lakhs
22380.40 Lakhs
35418.20 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2.89
3CONSTRUCTION OF ROADS3.138
4PAVEMENTS2.851
5PARKS AND PLAYGROUNDS2.523
6GREEN BELTS0
7VEHICLE PARKINGS0.25
8ELECTRICITY SUB-STATION0.62
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.22
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER4.989
13UGT0.22
Total17.701




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYGMDAYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS3357.06AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM1119.02AS PER PROJECT REPORT
3STORM WATER DRAINAGE1119.02AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM4028.47AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL1119.02AS PER PROJECT REPORT
6STREET LIGHTING447.61AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS4252.28AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER1566.63AS PER PROJECT REPORT
15EARTH WORK1119.02AS PER PROJECT REPORT
16SEWERAGE SYSTEM2238.04AS PER PROJECT REPORT
17UGT1119.02AS PER PROJECT REPORT
18RAIN WATER HARVESTING895.22AS PER PROJECT REPORT


NA (date)
07-05-2025 (date)
01-07-2025
31-03-2034
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings207.70311526
Apartment/Shops/Other Buildings450.333126





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0935.501403.25
Shops000
Plots000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2338.752338.753274.254677.50
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments8504.5512799.3515605.8512714.30
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments19347.8521261.3821261.3817476.85
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments21729.1321729.1322196.8815605.85
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments20325.8819858.1317519.3813734.85
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments17519.3817519.3816031.089865.28
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments15138.1011353.58113547569
Shops0000
Plots0000

ParticularsYear-2033
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments7059565647633274
Shops0000
Plots0000

ParticularsYear-2034
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1488
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System000168
Sewerage treatment & garbage disposal00168168
Electricity Supply System0403403403
Storm Water Drainage000168
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other00313313
Earth Work00280280
Sewerage System000336
UGT00168168
Rain Water Harvesting134134134134

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements671671671671
Water Supply System168168168168
Sewerage treatment & garbage disposal168168168168
Electricity Supply System403403403403
Storm Water Drainage168168168168
Parks and Playgrounds850850850850
Clubhouse/community centres0000
Shopping area0000
Other3133133130
Sewerage System336336336336
Street Light90909090
Rain Water Harvesting13413490
Earth Work280280
UGT168168168168

ParticularsYear-2033
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements671000
Water Supply System112565656
Sewerage treatment & garbage disposal112000
Electricity Supply System403201201201
Storm Water Drainage112565656
Parks and Playgrounds850000
Clubhouse/community centres0000
Shopping area0000
Other0000
UGT112000
Sewerage System224112112112
Street Light90000

ParticularsYear-2034
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System201
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Yes
No
VATIKA ATRIUM, BLOCK A, GOLF COURSE ROAD, SECTOR 53 GURGRAON
57500001683356
HDFC0000572
110240093
572
Mr. Badal Bagri 148, Birch Court, Nirvana Country, Sector 50 Gurgaon, Mr. Sanjay Goenka F-222, Park Place, DLF5, DLF Golf Course Sector 54 Gurgaon, Mr. Puneet Rakheja H.No. 386, Sector 31, Faridabad, Haryana 121003, Mr. Pankaj Kumar Jain C-701, Apex Acacia Valley, Near Shoppix Mall, Sector 3, Vaishali, Ms. Sandhya Singla Neelanchal Apartments, Plot No. 3, Sector 4, Dwarka, Delhi 110075, Mr. Gaurav Arora A-33, Near Mehfil Banquet Hall, Mahendru Enclave, GT Karnal Road, Delhi 110009, Mr. Ashok Nanda A255, Surya Nagar, Chander Nagar, Ghaziabad, Uttar Pradesh 201011, Mr. Sujeet Kumar Sinha C-061, DLF New Town Heights, IMT Manesar, Sector 91, Gurgaon, Haryana 122505, Mr. Pankaj Kumar A-3, Rajcottage 1/18. Rajendra Nagar Ganga banquet Hall, Sahibabad, UP 201005, Mr. Sunil Sharma C-28, Second Floor, WZ-62-A/2, Near Ring Road, Sharda Puri, Ramesh Nagar, West Delhi, Delhi-110015, Mr. Himanshu Garg E-301 Block E, Ardee City Gate No. 2, Sector 52, Wazirabad, Gurgaon,
Attached in Folder D











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LETTER OF INTENTALREADY BEEN OBTAINED08-09-2023
II. LICENSEALREADY BEEN OBTAINED25-10-2023
III. ELECTRIC LOAD ASSURANCEALREADY BEEN OBTAINED10-01-2024
IV. WATER ASSURANCEALREADY BEEN OBTAINED06-10-2023
V. STROM WATER ASSURANCEALREADY BEEN OBTAINED11-10-2024
VI. SEWERAGE ASSURANCEALREADY BEEN OBTAINED11-10-2024
VII. WATER FOR CONSTRUCTIONALREADY BEEN OBTAINED18-12-2024
VIII. ENVIROMENTAL CLERANCE ALREADY BEEN OBTAINED20-02-2025
IX. REVISED PHASING PLANALREADY BEEN OBTAINED06-05-2025
X. REVISED DEMARCATION CUM ZONINGALREADY BEEN OBTAINED06-05-2025
XI. BUILDING PLAN APPROVALALREADY BEEN OBTAINED07-05-2025








Yes


Yes


As per RERA Act







GARDENCITY ARCADE, GURGAON
1.42
99
1
99
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6309.1962234950.19
Cost of the apartments4162.2846673709.83
Cost of the infrastructure000
Others costs2146.9115561240.36


6935.16 Lakhs
2537.40 Lakhs
0 Lakhs
5881 Lakhs
No
29-04-2025
29-04-2025




DLF GARDENCITY ENCLAVE, GURGAON
26.91875
0
367
0
119
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1199951972705.91
Cost of the apartments473832411240
Cost of the infrastructure000
Others costs726119561465.91


11164.63 Lakhs
2648.09 Lakhs
0 Lakhs
2871.84 Lakhs
No
29-03-2024
28-03-2025




INDEPENDENT FLOORS AT DLFGARDENCITY ENCLAVE, GURGAON
3.5698
388
97
388
97
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
234682892616618.59
Cost of the apartments183452661415086.26
Cost of the infrastructure136700
Others costs375623121532.33


20622.65 Lakhs
34805.50 Lakhs
0 Lakhs
17409.39 Lakhs
No
19-08-2027
19-08-2027




DLF GARDENCITY ENCLAVE PH2, GURGAON
5.0105
544
136
536
134
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
406063884414802.81
Cost of the apartments338923603012671.98
Cost of the infrastructure000
Others costs671428142130.83


31080.10 Lakhs
54192.41 Lakhs
0 Lakhs
15967.74 Lakhs
No
30-10-2028
30-10-2028




SUMMIT PLAZA SECTOR-54, GURUGRAM, HARYANA
2.65
311
1
311
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
23537.963471219947
Cost of the apartments15098.333228617859
Cost of the infrastructure000
Others costs8439.6324262088


5735 Lakhs
5329 Lakhs
0 Lakhs
20615 Lakhs
No
30-06-2026
30-06-2026




THE GROVE DLF 5, SECTOR-54, GURUGRAM, HARYANA
5.3073
292
73
292
73
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
47346.175435035593
Cost of the apartments38532.095247834143
Cost of the infrastructure000
Others costs8814.0818721450


143502 Lakhs
133888.48 Lakhs
0 Lakhs
54829 Lakhs
No
31-12-2025
31-12-2025




DLF PRIVANA SOUTH, SECTOR-77, GURGAON, HARYANA
25.148
1113
0
1113
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
341550.0934758232873.54
Cost of the apartments319728.9931399317001.18
Cost of the infrastructure000
Others costs21821.103358915872.36


257431 Lakhs
668186.28 Lakhs
0 Lakhs
43659 Lakhs
No
30-06-2031
30-06-2031




DLF PRIVANA WEST, SECTOR-77, GURGAON, HARYANA
12.572
795
0
795
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
27930025824323910
Cost of the apartments25208923007712573
Cost of the infrastructure000
Others costs272112816611337


146569 Lakhs
507573.69 Lakhs
0 Lakhs
30503 Lakhs
No
31-12-2031
31-12-2031




DLF CLUB ARCADE, SECTOR 91, GURGAON, HARYANA
0.89
72
0
49
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
44274549.28190.75
Cost of the apartments25752704.50181.70
Cost of the infrastructure000
Others costs18521844.789.05


580.86 Lakhs
4642.86 Lakhs
0 Lakhs
191 Lakhs
No
31-03-2028
31-03-2028




THE DAHLIAS, GURGAON, HARYANA
16.489
420
0
173
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
61334262415424368
Cost of the apartments60835361914419635
Cost of the infrastructure000
Others costs498950104733


132959 Lakhs
1227542.79 Lakhs
0 Lakhs
28799 Lakhs
No
31-12-2031
31-12-2031










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILES/MARBLE/GRANITE/LAMINATED WOODEN
2WALL FINISHING DETAILSOBD/SEMI ACRYLIC/ACRYLIC EMULSION/TILES
3KITCHEN DETAILSMODULAR KICTHEN WITH APPLIANCES ASPERPOINT 6.6 CABINETRY AND SS SINK
4BATHROOM FITTINGSCP FITTINGS, WASH BASIN, FLOOR MOUNTED /WALL HUNG WCS
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESMS/UPVC/ALWOOD/COMPOSITION MATERIAL
7GLASS WORKFROSTED / CLEAR GLASS
8ELECTRIC FITTINGSSWITCH BOX AND SOCKETS
9CONDUCTING AND WIRING DETAILSPVC CONDUCTS, FR WIRING
10CUPBOARD DETAILSMODULAR WARDROBES
11WATER STORAGEOHT & UGT WATER TANKS
12LIFT DETAILSBRANDED MAKE
13EXTERNAL GLAZINGSUPVC/ALUMUNIUM
13.1WINDOWS/GLAZINGSSAME AS POINT 13
14DOORSMAIN DOOR INTERNAL DOORS
14.1MAIN DOORSWOODEN FIRE RESISTANT FLUSH DOOR
14.2INTERNAL DOORSWOODEN FLUSH DOOR
15AIR CONDITIONINGIN LIVING, DINING & BEDROOMS
16ELECTRICAL FITTINGSSAME AS POINT 8
17CNG PIPE LINEGAS PIPE LINE PROVISION ONLY
18PROVISION OF WIFI AND BROADBAND FACILITYPROVISION ONLY
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR GRADED PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORMARBLE /TILES
1 . 2 WALLSACRYLIC EMULSION / OBD
1 . 3 CEILINGACRYLIC EMULSION / OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING/MARBLE /TILES
2 . 2 WALLSACRYLIC EMULSION / OBD
2 . 3 CEILINGACRYLIC EMULSION / OBD
2 . 4 MODULAR WARDROBESMODULAR WARDROBES
3 . MASTER TOILET
3 . 1 FLOORTILES / MARBLE / GRANITE
3 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSIONPAINT &MIRROR;
3 . 3 CEILINGACRYLIC EMULSION PAINT
3 . 4 COUNTERSMARBLE / GRANITE / SYNTHETIC STONE
3 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, WC, TOWELRAIL/RING,TOILET PAPER HOLDER
3 . 6 FITTING/FIXTURESEXHAUST FAN, GEYSER
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING/MARBLE/TILE
4 . 2 WALLSACRYLIC EMULSION PAINT / OBD
4 . 3 CEILINGACRYLIC EMULSION PAINT / OBD
4 . 4 WARDROBESMODULAR WARDROBES
5 . TOILET
5 . 1 FLOORMARBLE / GRANITE / TILES
5 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSIONPAINT
5 . 3 CEILINGACRYLIC EMULSION PAINT
5 . 4 COUNTERSGRANITE / MARBLE / SYNTHETIC STONE
5 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, WC, TOWELRAIL/RING,TOILET PAPER HOLDER
5 . 6 FIXTURESEXHAUST FAN, GEYSER
6 . KITCHEN
6 . 1 FLOORTILES/GRANITE
6 . 2 WALLSTILES UP-TO 2’ ABOVE COUNTER & EMULSIONPAINTIN BALANCE AREA
6 . 3 CEILINGACRYLIC EMULSION PAINT
6 . 4 COUNTERSMARBLE / GRANITE /SYNTHETIC STONE
6 . 5 FIXTURESCP FITTINGS, SS SINK, EXHAUST FAN
6 . 6 KITCHEN APPLIANCESHOB, CHIMNEY,OVEN,MICROWAVE,DISHWASHER,REFRIDGERATOR,GEYSER,WASHING MACHINE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGOBD/SEMI ACRYLIC/TILES
7 . 3 TOILETCP FITTINGS, WASH BASIN, WC
7 . 4 BALCONYTILES/CEMENT BASED EXTERIOR GRADE PAINT
8 . SIT-OUTS
8 . 1 FLOORTILES
8 . 2 WALLS & CEILINGEXTERIOR GRADE PAINTS
8 . 3 RAILINGSMS/SS/AL/GLASS
8 . 4 FIXTURESCEILLING LIGHTS












Sr. No.Document DescriptionDate of Document UploadView Document
1DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.08-04-2025 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND08-04-2025 View Document
3SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN08-04-2025 View Document
4DEMARCATION PLAN08-04-2025 View Document
5A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS08-04-2025 View Document
6IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN08-04-2025 View Document
7DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD08-04-2025 View Document
8ZONING PLAN08-04-2025 View Document
9FINAL NO CHARGE CERTIFICATE04-06-2025 View Document
10TYPICAL RAIN WATER HARVESTING PLAN04-06-2025 View Document
1150TH PENTH HOUSE FLOOR (TOWER B&D)04-06-2025 View Document
12SECTION 1-1 (TOWER B AND D)04-06-2025 View Document
13ASSURANCE CERTIFICATE - STORM WATER CONNECTION04-06-2025 View Document
14BR-III04-06-2025 View Document
1517TH,35TH & 44TH REFUGE PLAN (TOWER A&C)04-06-2025 View Document
16DLF PRIVANA ACCOUNTS LETTER_08.05.202504-06-2025 View Document
17DA NO 3998 DT 23.06.2023 -14.06 ACS KHERKI DAULA (NADISH TO DLF LTD) PRIVANA04-06-2025 View Document
18COST INCURRED CERTIFICATE04-06-2025 View Document
19LETTER ZP AND PHASING04-06-2025 View Document
20PHASING PLAN04-06-2025 View Document
21CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT29-04-2025 View Document
22TYPICAL FLOOR PLAN (TOWER E)04-06-2025 View Document
23NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT29-04-2025 View Document
24CASH FLOW STATEMENT OF THE PROPOSED PROJECT29-04-2025 View Document
25DA NO 3999 DT 23.06.2023 -6.25 ACS KHERKI DAULA (NAJA ESTATES TO DLF LTD) PRIVANA04-06-2025 View Document
26ARAVALI NOC FOR 113.696 ACRES LAND04-06-2025 View Document
27ASSURANCE CERTIFICATE - WATER SUPPLY04-06-2025 View Document
28BASEMENT 2 AREA CALULATION04-06-2025 View Document
29CONSTRUCTION PERT CHART04-06-2025 View Document
30AAI NOC- POCKET 1 - POCKET 704-06-2025 View Document
31ELEVATION 03 (TOWER A,C&E)04-06-2025 View Document
32BASEMENT AREA 3 CALCULATION04-06-2025 View Document
33DRAFT APPLICATION FORM - PRIVANA NORTH04-06-2025 View Document
34LETTER OF INTENT (LC-III)04-06-2025 View Document
35GROUND COVERAGE AREA (TOWER B&D), GROUND COVERAGE TOWER F04-06-2025 View Document
36BASEMENT 204-06-2025 View Document
37TREE FELLING PERMISSION04-06-2025 View Document
38LEGAL SEARCH - PRIVANA NORTH04-06-2025 View Document
39SECTION 2-2 (TOWER B AND D)04-06-2025 View Document
40ELEVATION 02 (TOWER A,C&E)04-06-2025 View Document
41TYPICAL FLOOR PLAN TOWER F04-06-2025 View Document
42BASEMENT 1 ONLY FOR SERVICES04-06-2025 View Document
43ROOF PLAN TOWER F04-06-2025 View Document
44BASEMENT 104-06-2025 View Document
45REFUGEE FLOOR PLAN TOWER F04-06-2025 View Document
46ELEVATION 03 (TOWER F)04-06-2025 View Document
47NEC04-06-2025 View Document
48ASSURANCE CERTIFICATE - SEWERAGE04-06-2025 View Document
49NO DUES CERTIFICATE04-06-2025 View Document
50GROUND FLOOR PLAN (TOWER C)04-06-2025 View Document
51BASEMENT 1 AREA CALCULATION04-06-2025 View Document
52IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN04-06-2025 View Document
53SCHEMATIC TOWER A-F04-06-2025 View Document
5450TH PENTH HOUSE (TOWER A&C)04-06-2025 View Document
55STILT GF PLAN (TOWER D)04-06-2025 View Document
56ESTIMATE COST INCURRED CERTIFICATE04-06-2025 View Document
57TYPICAL FLOOR PLAN (TOWER B & D)04-06-2025 View Document
58STILT & GF PLAN (TOWER B)04-06-2025 View Document
5917TH,35TH & 44TH REFUGE PLAN (TOWER E)04-06-2025 View Document
60CTE PRIVANA NORTH04-06-2025 View Document
61ELEVATION 01 (TOWER A,C &E)04-06-2025 View Document
62ELEVATION 1(TOWER B AND D)04-06-2025 View Document
63SECTION 02 (TOWER A,B&C)04-06-2025 View Document
64GF AREA (TOWER D), GF AREA CALCULATION (TOWER B), GF AREA PLAN (TOWER E)04-06-2025 View Document
65SERVICES PERT CHART04-06-2025 View Document
66BASEMENT 304-06-2025 View Document
67DRAFT AGREEMENT FOR SALE04-06-2025 View Document
68SA NO 4240 DT 28.06.2023 -6.97 ACS KHERKI DAULA (VIKRAM TO DLF LTD) PRIVANA04-06-2025 View Document
69STILT AND GROUND FLOOR AREA TOWER F04-06-2025 View Document
70TERRACE PLAN AREA -TOWER A&C, TOWER B&D, TOWER E,TOWER F04-06-2025 View Document
7117TH, 35TH & 44 REFUGE FLOOR (TOWER B&D)04-06-2025 View Document
7226TH REFUGE FLOOR (TOWER B&D)04-06-2025 View Document
7326TH REFUGE FLOOR (TOWER E)04-06-2025 View Document
7426TH REFUGE PLAN (TOWER A&C)04-06-2025 View Document
7550TH PENTH HOUSE FLOOR (TOWER E)04-06-2025 View Document
76ARAVALI NOC FOR 15.67 ACRES LAND04-06-2025 View Document
77CONSTRUCTION WATER NOC04-06-2025 View Document
78DA NO 4397 DT 03.07.2023 -0.43 ACS KHERKI DAULA (MILDA TO DLF LTD) PRIVANA04-06-2025 View Document
79DRAFT DLF PRIVANA NORTH - PAYMENT RECEIPT04-06-2025 View Document
80DRAFT CONVEYANCE DEED - PRIVANA NORTH04-06-2025 View Document
81ELEVATION 2& 4 (TOWER B AND D)04-06-2025 View Document
82ELEVATION 3 (TOWER B AND D)04-06-2025 View Document
83ELECTRIC LOAD04-06-2025 View Document
84ELEVATION 01 (TOWER F)04-06-2025 View Document
85ELEVATION 2&4 (TOWER F)04-06-2025 View Document
86FOREST NOC CONSOLIDATE04-06-2025 View Document
87GREEN AREA & SURFACE CAR PARKING CALCULATION04-06-2025 View Document
88GROUND FLOOR AREA (TOWER A)04-06-2025 View Document
89PENTH HOUSE TOWER F04-06-2025 View Document
90REFUGEE FLOOR 2 TOWER F04-06-2025 View Document
91STILT FLOOR PLAN TOWER F04-06-2025 View Document
92LMR PLAN WATER TANK ROOF PLAN -TOWER B&D, TOWER E, TOWER A&C04-06-2025 View Document
93SECTION 01 (TOWER A,B&C)04-06-2025 View Document
94SECTION 2 (TOWER F)04-06-2025 View Document
95SECTION 2-2 (TOWER F)04-06-2025 View Document
96STILT GF PLAN (TOWER E)04-06-2025 View Document
97STILT GROUND FLOOR PLAN (TOWER C)04-06-2025 View Document
98STILT_GF PLAN (TOWER A)04-06-2025 View Document
99SURFACE PARKING AREA04-06-2025 View Document
100TYPICAL FLOOR PLAN (TOWER A & C)04-06-2025 View Document