HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1548-2024
Submission Date : 30-09-2024 03:52:30 PM
Applicant Type : Individual
Project Type: NEW




RAJ DEVELOPERS THROUGH PROPRIETOR RAJ KUMARI
MUKHTAR SINGH
 (Number Shared by Promoter in Public)
makinfra.rtk@gmail.com
XXXX941R
_______________









MAK GREEN - TWIN TOWERS
PLOT NO. 2, GH-2, SECTOR-4 EXTENSION
ROHTAK
ROHTAK
9991256696
9050430289 (Number Shared by Promoter in Public)
makinfra.rtk@gmail.com
HARVINDER
9050430289 (Number Shared by Promoter in Public)
makinfra.rtk@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1021-09-202431000ONLINE PAYMENT THROUGH VIDE REF. NO. 1706492520 FROM ICICI BANK LTD. HRERA Panchkula







2016.00 (Acre)
1.75 FAR
1.75
2016.00 (Acre)
HSVP ALLOTMENT OF SITE VIDE MEMO NO. ZO005/EO010/UE018/GALOT/0000001226,Dated 10.01.2024.
Yes







2108.00 Lakhs
808.00 Lakhs
1150.00 Lakhs
150.00 Lakhs
0.00 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS705.60
3CONSTRUCTION OF ROADS547.52
4PAVEMENTS0
5PARKS AND PLAYGROUNDS322.30
6GREEN BELTS0
7VEHICLE PARKINGS440.58
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total2016




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS33.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM24.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE18.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM39.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL21.50AS PER PROJECT REPORT
6STREET LIGHTING4.50AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS10.50AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
12-09-2024 (date)
15-09-2024
31-12-2028
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings115.005231
Apartment/Shops/Other Buildings123.64311
Apartment/Shops/Other Buildings116.6031
Apartment/Shops/Other Buildings126.83331
Apartment/Shops/Other Buildings000
Apartment/Shops/Other Buildings000
Apartment/Shops/Other Buildings000
Apartment/Shops/Other Buildings000
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments67.65
Shops0
Plots0

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments67.6567.6567.6567.65
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments67.6567.6567.6567.65
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments67.6567.6567.6567.65
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments67.6567.6567.6567.65
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.94
Water Supply System1.41
Sewerage treatment & garbage disposal1.06
Electricity Supply System2.29
Storm Water Drainage1.24
Parks and Playgrounds0.62
Clubhouse/community centres0
Shopping area0
Other0.26

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.941.941.941.94
Water Supply System1.411.411.411.41
Sewerage treatment & garbage disposal1.061.061.061.06
Electricity Supply System2.292.292.292.29
Storm Water Drainage1.241.241.241.24
Parks and Playgrounds0.620.620.620.62
Clubhouse/community centres0000
Shopping area0000
Other0.260.260.260.26

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.941.941.941.94
Water Supply System1.411.411.411.41
Sewerage treatment & garbage disposal1.061.061.061.06
Electricity Supply System2.292.292.292.29
Storm Water Drainage1.241.241.241.24
Parks and Playgrounds0.620.620.620.62
Clubhouse/community centres0000
Shopping area0000
Other0.260.260.260.26

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.941.941.941.94
Water Supply System1.411.411.411.41
Sewerage treatment & garbage disposal1.061.061.061.06
Electricity Supply System2.292.292.292.29
Storm Water Drainage1.241.241.241.24
Parks and Playgrounds0.620.620.620.62
Clubhouse/community centres0000
Shopping area0000
Other0.260.260.260.26

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.941.941.941.94
Water Supply System1.411.411.411.41
Sewerage treatment & garbage disposal1.061.061.061.06
Electricity Supply System2.292.292.292.29
Storm Water Drainage1.241.241.241.24
Parks and Playgrounds0.620.620.620.62
Clubhouse/community centres0000
Shopping area0000
Other0.260.260.260.26












No
No
INDUSIND BANK LTD, SHEELA BYE PASS ROAD, ROHTAK
259991256696
INDB0001464
124234004
001464
Sh. Raj Kumari R/o E-58, Sec36, Suncity, Rohtak, Haryana-124001
Uploaded in upload section











No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. SITE ALLOTMENT LETTER FROM HSVPALREADY BEEN OBTAINED10-01-2024
II. POSSESSION LETTER FROM HSVPALREADY BEEN OBTAINED26-02-2024
III. BUILDING PLANS APPROVAL LETTERALREADY BEEN OBTAINED12-09-2024








Yes


Yes


The provision of RERA Act andRules shall be incorporated in thedraft RERA Agreements













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE"INTERNAL FLOORING OF THE FLAT LIVING/DINNING/BEDROOMS/PASSAGES VITRIFIED TILES."
2WALL FINISHING DETAILS"INTERNAL WALLS/CEILINGS OF THE FLAT OBD FINISH "
3KITCHEN DETAILS"1. GRANITE MARBLE COUNTER MOUNTED ON FRAME OR SLAB 2. SS SINGLE BOWL SINK 3. CP FITTINGS 4. CERAMIC TILES UPTO TWO TO TWO AND A HALF FEET ABOVE COUNTER. "
4BATHROOM FITTINGS"1. TAPS FITTINGS PROVIDED 2. WC'S AND WASH BASINS"
5WOOD WORK ETCNOT PROVIDED (CLIENT'S SCOPE)
6DOORS AND WINDOS FRAMESNOT PROVIDED (CLIENT'S SCOPE)
7GLASS WORKGLASS WORK OR EQUIVALENT
8ELECTRIC FITTINGS"ISI APPROVED SWITCHES AND PLATES OTHER FIXTURES LIKE LIGHTS, FANS ETC. - NOT PROVIDED (CLIENT'S SCOPE)"
9CONDUCTING AND WIRING DETAILSDISTRIBUTION BOX,CONDUTING,WIRING (AS PER I.S. CODE)
10CUPBOARD DETAILSNOT PROVIDED (CLIENT'S SCOPE)
11WATER STORAGE"RCC UNDER GROUND WATER TANK OF ADEQUATE CAPACITY OVERHEAD STORAGE TANKS AS PER HSVP RULES. "
12LIFT DETAILSPASSENGER LIFT WILL BE PROVIDED OF REPUTED MAKE LIKE KONE, JOHNSONS OR EQUIVALENT.
13EXTERNAL GLAZINGSGLASS WORK OR EQUIVALENT
13.1WINDOWS/GLAZINGSGLASS WORK OR EQUIVALENT
14DOORSFLUSH DOOR WITH WOODEN FRAME
14.1MAIN DOORSFLUSH DOOR WITH WOODEN FRAME
14.2INTERNAL DOORSFLUSH DOORS WITH PAINT OR EQUIVALENT
15AIR CONDITIONINGNOT PROVIDED (CLIENT'S SCOPE)
16ELECTRICAL FITTINGSNOT PROVIDED (CLIENT'S SCOPE)
17CNG PIPE LINEOPTIONAL
18PROVISION OF WIFI AND BROADBAND FACILITYNOT PROVIDED (CLIENT'S SCOPE)
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR PAINT
20INTERNAL FINISHINGOBD FINISH PAINT.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD FINISH
1 . 3 CEILINGOBD FINISH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSOBD FINISH
2 . 3 CEILINGOBD FINISH
2 . 4 MODULAR WARDROBESNOT PROVIDED (CLIENT'S SCOPE)
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES
3 . 2 WALLSCERAMIC TILES UPTO DOOR SIL LEVEL
3 . 3 CEILINGOBD FINISH
3 . 4 COUNTERSGRANITE MARBLE COUNTER
3 . 5 SANITARY WARE/CP FITTINGS"1. CP FITTINGS 2. SANITARY WARE "
3 . 6 FITTING/FIXTURESNOT PROVIDED (CLIENT'S SCOPE)
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOBD FINISH
4 . 3 CEILINGOBD FINISH
4 . 4 WARDROBESNOT PROVIDED (CLIENT'S SCOPE)
5 . TOILET
5 . 1 FLOORCERAMIC TILES
5 . 2 WALLSCERAMIC TILES
5 . 3 CEILINGOBD FINISH
5 . 4 COUNTERSNOT PROVIDED
5 . 5 SANITARY WARE/CP FITTINGS"1. CP FITTINGS 2. SANITARY WARE "
5 . 6 FIXTURESNOT PROVIDED (CLIENT'S SCOPE)
6 . KITCHEN
6 . 1 FLOORCERAMIC TILES
6 . 2 WALLSCERAMIC TILES
6 . 3 CEILINGOBD FINISH
6 . 4 COUNTERSGRANITE MARBLE COUNTER MOUNTED
6 . 5 FIXTURES"1. CP FITTINGS 2. SANITARY WARE "
6 . 6 KITCHEN APPLIANCESNOT PROVIDED (CLIENT'S SCOPE)
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGOBD FINISH
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYCERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN30-09-2024 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND25-09-2024 View Document
3A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS30-09-2024 View Document
4NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT25-09-2024 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN30-09-2024 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.30-09-2024 View Document
7ZONING PLAN30-09-2024 View Document