HRERA GurugramTemp Project Id : RERA-GRG-PROJ-120-2018
Submission Date : 27-12-2018 02:04:02 AM
Applicant Type : Company
Project Type: NEW




HERITAGE MAX REALTECH PVT. LTD.
K1-GREEN PARK MAIN , NEW DELHI-10016
0124280300
9810030178 (Number Shared by Promoter in Public)
aditya.arora@conscient.com
http://yettobecreated.com
XXXX172E
U70200DL2015PTC286008
 
 


 
 


 
 


 
 


 
 


 
 







ELEVATE PHASE I
SECTOR-59, GURUGRAM
SOHNA
GURUGRAM
01242803000
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in
SANJAY RASTOGI
01242803428
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11536308-03-2018421383HDFC BANK LTD. GLOBAL BUSINESS PARK, MG ROAD, GURUGRAM-122002HRERA Gurugram
21578108-06-2018316056HDFC BANK LTD. GLOBAL BUSINESS PARK, MG ROAD, GURUGRAM-122002HRERA Gurugram
31666725-01-2019421382HDFC BANK LTD. GLOBAL BUSINESS PARK, MG ROAD, GURUGRAM-122002HRERA Gurugram







5.95 (Acre)
1.75
1.75
8.91875 (Acre)
1. 16 of 2018 2. 28 of 2008 3. 44 of 2011
No
Address     304, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     304, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     A-11, 1ST FLOOR, NEETI BAGH, NEW DELHI-110049
Address     304, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI-110017
Address     A-11, 1ST FLOOR, NEETI BAGH, NEW DELHI-110049
Address     A-11, 1ST FLOOR, NEETI BAGH, NEW DELHI-110049
Address     A-11, 1ST FLOOR, NEETI BAGH, NEW DELHI-110049
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     A-11, 1ST FLOOR, NEETI BAGH, NEW DELHI-110049
Annexure-B- "COLLABORATOR/ DEVELOPER" COLLABORATION AGREEMENT AND POA ARE ANNEXED AS ANNEXURE-B-2
AFTER GRANT OF LICENSE
Yes
COLLABORATION AGREEMENT DATED MARCH 2, 2016 DULY REGISTERED WITH SUB REGISTRAR SOHNA VIDE REGN. NO. 3687 DATED MARCH 2, 2016.
No
Yes
Yes







42721 Lakhs
12300 Lakhs
16411 Lakhs
2489 Lakhs
11518 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.71665
3CONSTRUCTION OF ROADS0.46482
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.12874
6GREEN BELTS1.23026
7VEHICLE PARKINGS0.12874
8ELECTRICITY SUB-STATION0.01347
9CLUB HOUSE0.21883
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER3.04856
Total5.95007




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYDAKSHIN HARYANA BIJLI VITRAN NIGAMNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS181SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM192SUBMITTED TO HUDA
3STORM WATER DRAINAGE52SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM596SUBMITTED TO HUDA
5SEWAGE TREATMENT & GARBAGE DISPOSAL106SUBMITTED TO HUDA
6STREET LIGHTING14SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING36SUBMITTED TO HUDA
8PLAYGROUNDS AND PARKS14SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE876SUBMITTED TO HUDA
10SHOPPING AREA0SUBMITTED TO HUDA
11RENEWABLE ENERGY SYSTEM23SUBMITTED TO HUDA
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15STP125SUBMITTED TO HUDA
16RAIN WATER HARVESTING28SUBMITTED TO HUDA
17UNDERGROUND TANK105SUBMITTED TO HUDA
18ELECTRICAL SUB STATION141SUBMITTED TO HUDA


14-03-2018 (date)
14-03-2018 (date)
28-02-2019
31-12-2024
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings107.68291
Apartment/Shops/Other Buildings118.33301
Apartment/Shops/Other Buildings133.03621
Apartment/Shops/Other Buildings181.0511
Apartment/Shops/Other Buildings87.1511
Apartment/Shops/Other Buildings167.36142
Apartment/Shops/Other Buildings167.36143
Apartment/Shops/Other Buildings20.129274





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments96.2811491149.0821
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments821.0821821821
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments821821821821
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments821821821821
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments821821821164
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments164164164164
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.812.612.69.0
Water Supply System1.913.413.49.6
Sewerage treatment & garbage disposal1.17.47.45.3
Electricity Supply System6.041.741.729.8
Storm Water Drainage0.53.73.72.6
Parks and Playgrounds0.11.01.00.7
Clubhouse/community centres8.861.361.343.8
Shopping area0000
Other0000
Rain water harvesting0.32.02.01.4
Electrical Substation1.49.99.97.1
Streetlighting0.11.01.00.7
Renewal energy System0.21.61.60.2
Security and fire fighting services0.42.52.51.8
STP1.38.88.86.3
Underground tank1.17.47.45.3

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements9.09.19.09.0
Water Supply System9.69.69.69.6
Sewerage treatment & garbage disposal5.35.35.35.3
Electricity Supply System29.829.829.829.8
Storm Water Drainage2.62.62.62.6
Parks and Playgrounds0.70.70.70.7
Clubhouse/community centres43.843.843.843.8
Shopping area0000
Other0000
Rain water harvesting1.41.41.41.4
STP6.36.36.36.3
Renewal energy System1.21.21.21.2
Streetlighting0.70.70.70.7
Security and fire fighting services1.81.81.81.8
Underground tank5.35.35.35.3
Electrical Substation7.17.17.17.1

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements9.09.09.09.0
Water Supply System9.69.69.69.6
Sewerage treatment & garbage disposal5.35.35.35.3
Electricity Supply System29.829.829.829.8
Storm Water Drainage2.62.62.62.6
Parks and Playgrounds0.70.70.70.7
Clubhouse/community centres43.843.843.843.8
Shopping area0000
Other0000
Streetlighting0.70.70.70.7
Renewal energy System1.21.21.21.2
Security and fire fighting services1.81.81.81.8
Electrical Substation7.17.17.17.1
Rain water harvesting1.41.41.41.4
Underground tank5.35.35.35.3
STP6.36.36.36.3

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements9.19.09.09.0
Water Supply System9.69.69.69.6
Sewerage treatment & garbage disposal5.35.35.35.3
Electricity Supply System29.829.829.829.8
Storm Water Drainage2.62.62.62.6
Parks and Playgrounds0.70.70.70.7
Clubhouse/community centres43.843.843.843.8
Shopping area0000
Other0000
Underground tank5.35.35.35.3
Streetlighting0.70.70.70.7
Renewal energy System1.21.21.21.2
Security and fire fighting services1.81.81.81.8
STP6.36.36.36.3
Rain water harvesting1.41.41.41.4
Electrical Substation7.17.17.17.1

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements9.09.09.01.8
Water Supply System9.69.69.61.9
Sewerage treatment & garbage disposal5.35.35.31.1
Electricity Supply System29.829.829.86.0
Storm Water Drainage2.62.62.60.5
Parks and Playgrounds0.70.70.70.1
Clubhouse/community centres43.843.843.88.8
Shopping area-2000
Other0000
Streetlighting0.70.70.30.1
Electrical Substation7.17.17.11.4
Rain water harvesting1.41.41.40.1
Underground tank5.35.35.31.1
STP6.36.36.31.3
Security and fire fighting services1.81.81.80.4
Renewal energy System1.21.21.20.2

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.81.81.81.8
Water Supply System1.91.91.91.9
Sewerage treatment & garbage disposal1.11.11.11.1
Electricity Supply System6.06.06.06.0
Storm Water Drainage0.50.50.50.5
Parks and Playgrounds0.10.10.10.1
Clubhouse/community centres8.88.88.88.8
Shopping area0000
Other0000
STP1.31.31.31.3
Security and fire fighting services0.40.40.40.4
Renewal energy System0.20.20.20.2
Streetlighting0.10.10.10.1
Rain water harvesting0.30.30.30.3
Electrical Substation1.41.41.41.4
Underground tank1.11.11.11.1












Yes
No
HDFC BANK LIMITED TOWER-A, GLOBAL BUSINESS PARK, MG ROAD, GURUGRAM-122002
50200028383815
HDFC0001203
110240182
001203
1. Mr Lalit Jain R/o 12 Sultanpur Farms, Mehrauli, New Delhi-110030 2. Mr Sumeet Kumar R/o H.No.-62, Zone-H 4/5 Suvidha Kunj, Pitampura, Delhi-110034 3. Mr Ajay Kumar Agrawal R/o H.No. 32, Sector-16A, Faridabad 4. Mr Amit Diwan R/o D-181, Westend Heights, Near Paras Hospital DLF Phase - 5, Galleria DLF -IV Farrukhnagar, Gurgaon - 122009 5. Mrs Tina Rawla R/o B-51, Pinnacle Apartments, DLF Phase-5, , Galleria DLF IV, Gurgaon-122009 6. Mr Prachish Vasudeva R/o 2 AB Sainik Farms, New Delhi-110062
Enclosed











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ARAVALI NOCALREADY BEEN OBTAINED24-08-2016
II. FOREST NOCALREADY BEEN OBTAINED21-04-2016
III. BENEFICIAL INTEREST – FINAL APPROVALALREADY BEEN OBTAINED27-04-2017
IV. POWER ASSURANCEALREADY BEEN OBTAINED05-05-2017
V. WATER ASSURANCEALREADY BEEN OBTAINED05-07-2016
VI. AIRPORTS AUTHORITY APPROVALALREADY BEEN OBTAINED10-08-2017
VII. FINAL BUILDING PLANS APPROVALALREADY BEEN OBTAINED14-03-2018
VIII. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED13-07-2018
IX. SERVICE PLAN ESTIMATEAPPLIED FOR BUT YET TO RECEIVE07-05-2018
X. CONSENT TO ESTABLISHYET TO FILE FOR APPROVALNA








Yes


Yes


Clause 1 : Terms Clause 5: Time is of Essence Clause 6: Construction of the Real Estate Project/ Apartment Clause 7: Possession of the Apartment Clause 9: Events of defaults and consequences including termination Clause 10: Conveyance of the Apartment Clause 17: Compliance of Laws, Notifications, other Obligations etc. by the parties Clause 19: Mortgage or Creation of Charge Clause 22: Binding Effect Clause 32: Dispute Resolution













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILES
2WALL FINISHING DETAILSPAINT SURFACE
3KITCHEN DETAILSFLOOR TILES PAINT ON CEILING
4BATHROOM FITTINGSSTANDARD CP FITTING + WC + WASH BASIN
5WOOD WORK ETCFLUSH DOOR
6DOORS AND WINDOS FRAMESDOUBLE/SINGLE GLASS
7GLASS WORKNA
8ELECTRIC FITTINGSLED FIXTURES
9CONDUCTING AND WIRING DETAILSFRLSH INSULATED COPPER CONDUCTOR WIRE.
10CUPBOARD DETAILSNA
11WATER STORAGERAW WATER TANK : 340KL TREATED WATER TANK : 340KL
12LIFT DETAILSHIGH RISE : 4 NO.S – 13 PASSENGER LIFT & 1 NO.S – 15 PASSENGER SERVICE/FIREMAN LIFT MID RISE : 2 NO.S – 10 PASSENGER LIFT & 1 NO.S – 15 PASSENGER SERVICE/FIREMAN LIFT EWS : 1 NO.S – 15 PASSENGER SERVICE/FIREMAN LIFT COMMUNITY BUILDING : 1 NO.S - 13 PASSENGER LIFT & 1 NO.S – 13 PASSENGER SERVICE LIFT COMMERCIAL BLOCK: 1 NO.S - 10 PASSENGER LIFT HEALTH CLUB : 1 NO.S - 10 PASSENGER LIFT
13EXTERNAL GLAZINGSDOUBLE/ SINGLE GLASS + CLEAR/ TENTED GLASS WITH UPVC FRAMES IN ALL HABITABLE AREAS
13.1WINDOWS/GLAZINGSDOUBLE/ SINGLE GLASS + CLEAR/ TENTED GLASS
14DOORSNA
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSBOTH SIDE LAMINATED FLUSH DOO
15AIR CONDITIONINGVRV SYSTEM
16ELECTRICAL FITTINGSLED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURES & PAINT AND GRC JALI
20INTERNAL FINISHINGPAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORSTONE/ TILES
1 . 2 WALLSPAINT
1 . 3 CEILINGPAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN/ TILE
2 . 2 WALLSPAINT
2 . 3 CEILINGPAINT SURFACE
2 . 4 MODULAR WARDROBESDETAILS NOT FINALIZED YET
3 . MASTER TOILET
3 . 1 FLOORTILES
3 . 2 WALLSTILES
3 . 3 CEILINGPAINT
3 . 4 COUNTERSSTONE
3 . 5 SANITARY WARE/CP FITTINGSSTANDARD CP FITTINGS
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORWOODEN/ TILE
4 . 2 WALLSPAINT SURFACE
4 . 3 CEILINGPAINT SURFACE
4 . 4 WARDROBESDETAILS NOT FINALIZED YET
5 . TOILET
5 . 1 FLOORTILES
5 . 2 WALLSTILES AND MIRROR
5 . 3 CEILINGPAINT SURFACE
5 . 4 COUNTERSMARBLE / GRANITE / SYNTHETIC STONE
5 . 5 SANITARY WARE/CP FITTINGSSTANDARD CP FITTINGS
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORTILES
6 . 2 WALLSTILES
6 . 3 CEILINGPAINT SURFACE
6 . 4 COUNTERSMARBLE / GRANITE / SYNTHETIC STONE
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESSTANDERED MODULAR KITCHEN WITH HOB AND CHIMNEY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGPAINT SURFACE
7 . 3 TOILETCP FITTINGS & SANITARY WARE
7 . 4 BALCONY TILES / PAINT
8 . SIT-OUTS
8 . 1 FLOORPAVER/ SAND STONE
8 . 2 WALLS & CEILINGNOT AVAILABLE
8 . 3 RAILINGSNOT AVAILABLE
8 . 4 FIXTURESNOT AVAILABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN27-12-2018 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN27-12-2018 View Document
3NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT27-12-2018 View Document
4DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD16-02-2019 View Document
5SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN16-02-2019 View Document
6DEMARCATION PLAN16-02-2019 View Document
7COPY OF LICENSE ALONG WITH SCHEDULE OF LAND18-02-2019 View Document
8ZONING PLAN16-02-2019 View Document
9A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS16-02-2019 View Document
10CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT16-02-2019 View Document
11CASH FLOW STATEMENT OF THE PROPOSED PROJECT16-02-2019 View Document
12DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.16-02-2019 View Document