HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1698-2024
Submission Date : 02-09-2024 11:35:20 AM
Applicant Type : Company
Project Type: NEW




GODREJ PROJECTS DEVELOPMENT LIMITED
GODREJ ONE, 5TH FLOOR, PIROJSHANAGAR EASTERN EXPRESS HIGHWAY, VIKHROLI (EAST)
01244842300
9599335446 (Number Shared by Promoter in Public)
godrej43.ggn@godrejproperties.com
https://www.godrejproperties.com
XXXX366L
U70102MH2010PLC210227
 
 


 
 


 
 







GODREJ MIRAYA
SECTOR 43, URBAN ESTATE, GURUGRAM II
GURGAON
GURUGRAM
1244842300
1244842300 (Number Shared by Promoter in Public)
godrej43.ggn@godrejproperties.com
KARAN TREHAN
1244842300
1244842300 (Number Shared by Promoter in Public)
karan.trehan@godrejproperties.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1171622-08-20242810000AXIS BANKHRERA Gurugram







5.1575 (Acre)
3.198
3.197
5.1575 (Acre)
HSVP land - e-auction, GH25 at Sector 43, Urban Estate Gurugram II on free hold basis Allotment letter vide memo no. ZO002/EO018/UE029/GALOT/0000001407 dated 20.12.2023
Yes







140316.40 Lakhs
66418.69 Lakhs
50600.69 Lakhs
8269.75 Lakhs
15027.29 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3522.236
3CONSTRUCTION OF ROADS5811.014
4PAVEMENTS3368.385
5PARKS AND PLAYGROUNDS451.6
6GREEN BELTS4174.2
7VEHICLE PARKINGS327.1
8ELECTRICITY SUB-STATION130.478
9CLUB HOUSE1265.77
10SEWAGE AND SOLID WASTE TREATMENT FACILITY547.64
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13WATERBODY1273
Total20871.423




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS346YET TO BE PREPARED
2WATER SUPPLY SYSTEM464YET TO BE PREPARED
3STORM WATER DRAINAGE107YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM2174YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL33YET TO BE PREPARED
6STREET LIGHTING123YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING1241YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE2915YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15SOFTSCAPE321YET TO BE PREPARED
16HARDSCAPE358YET TO BE PREPARED
17ELECTRICAL SUB STATION155YET TO BE PREPARED
18SIGNAGES32YET TO BE PREPARED


30-08-2024 (date)
30-08-2024 (date)
01-10-2024
30-09-2031
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings126.11622
Apartment/Shops/Other Buildings201.23222
Apartment/Shops/Other Buildings207.973602
Apartment/Shops/Other Buildings212.602602
Apartment/Shops/Other Buildings141.13422
Apartment/Shops/Other Buildings146.467582
Apartment/Shops/Other Buildings242.54421
Apartment/Shops/Other Buildings242.54421
Apartment/Shops/Other Buildings242.544601
Apartment/Shops/Other Buildings16.9321
Apartment/Shops/Other Buildings16.9711





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments43.33338.96
Shops00
Plots00
Others195.12130.08

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments372.07607.771364.291382.05
Shops0000
Plots0000
Others130.08130.08390.24390.24

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1404.982268.962823.303050.71
Shops0000
Plots0000
Others390.24390.24520.31520.31

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3597.053637.023676.993676.99
Shops0000
Plots0000
Others520.31520.31520.31520.31

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3637.023637.023676.992597.52
Shops0000
Plots0000
Others520.31520.31546.33546.33

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1326.181117.98853.69853.69
Shops01.324.030
Plots0000
Others546.33546.33546.33546.33

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments835.13844.41853.69853.69
Shops3.953.994.034.03
Plots0000
Others546.33546.33546.33546.33

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments835.13453.85
Shops2.590
Plots00
Others546.33689.42




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Street Lighting0
Signages0
Security and fire fighting system0
Hard scape0
Soft scape0
Electrical sub station0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres47.77146.89146.89
Shopping area000
Other000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0008.35
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System00047.08
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres143.70145.29146.89146.89
Shopping area0000
Other0000
Soft scape007.3421.58

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.6224.6224.8924.89
Water Supply System0014.3143.88
Sewerage treatment & garbage disposal000.953.11
Electricity Supply System158.68158.68160.42160.42
Storm Water Drainage006.419.82
Parks and Playgrounds0000
Clubhouse/community centres145.29145.29146.89146.89
Shopping area0000
Other0000
Hard scape0000.52
Soft scape21.351921.5821.58
Electrical sub station00.1614.2614.26
Street Lighting0003.9
Security and fire fighting system0001.41

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.3524.6224.8924.89
Water Supply System42.9243.4043.8843.88
Sewerage treatment & garbage disposal3.043.083.113.11
Electricity Supply System156.93158.68160.42160.42
Storm Water Drainage9.619.729.829.82
Parks and Playgrounds0000
Clubhouse/community centres143.7145.29146.89146.89
Shopping area0000
Other0000
Soft scape21.1121.3521.5820
Signages0001.78
Electrical sub station13.9514.8214.2614.26
Hard scape36.6337.0437.4537.45
Street Lighting12.5412.6812.8212.82
Security and fire fighting system126.13128.30129.71129.71

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.3524.6224.8924.89
Water Supply System42.9243.4043.8843.88
Sewerage treatment & garbage disposal3.043.083.113.11
Electricity Supply System156.93158.68160.42160.42
Storm Water Drainage9.619.729.829.82
Parks and Playgrounds0000
Clubhouse/community centres143.70145.29146.89146.89
Shopping area0000
Other0000
Soft scape21.1121.3521.5821.58
Security and fire fighting system126.89128.30129.71129.71
Street Lighting12.5212.6812.8212.82
Signages5.255.315.365.36
Electrical sub station13.9514.1114.2614.26
Hard scape36.6337.0437.4537.45

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.3516.50
Water Supply System42.9214.31
Sewerage treatment & garbage disposal3.041.08
Electricity Supply System156.9359.29
Storm Water Drainage9.613.31
Parks and Playgrounds00
Clubhouse/community centres143.7097.39
Shopping area00
Other00
Street Lighting12.544.60
Soft scape21.1113.84
Hard scape36.6324.01
Signages5.253.56
Electrical sub station13.640
Security and fire fighting system126.8984.60












Yes
No
UNIT 18 C AND 18 D ,SPLENDOR TRADE TOWER,GOLF COURSE EXT ROAD,SECTOR65,GURGAON,122001
50200099402466
HDFC0003676
110240366
003676
Sushil Kumar S/O: Kali Dass, Bah (391), Mandi, Himachal Pradesh, 175049
Yes











No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. ZONING PLANALREADY BEEN OBTAINED01-08-2024
II. NOC FOR HEIGHT CLEARANCEALREADY BEEN OBTAINED09-04-2024
III. SANCTION OF ULTIMATE LOAD ASSURANCEALREADY BEEN OBTAINED29-03-2024
IV. BUILDING PLAN APPROVALALREADY BEEN OBTAINED30-08-2024
V. ASSURANCE OF STP TREATED WATER CONNECTION FOR CONSTRUCTION PURPOSEALREADY BEEN OBTAINED20-03-2024
VI. ASSURANCE OF WATER SUPPLYALREADY BEEN OBTAINED29-03-2024
VII. TREE CUTTING APPROVALALREADY BEEN OBTAINED19-07-2024
VIII. ASSURANCE OF SEWERAGE CONNECTIONALREADY BEEN OBTAINED20-03-2024
IX. ASSURANCE OF STORM WATER CONNECTIONALREADY BEEN OBTAINED20-03-2024
X. EC APPLIED FOR BUT YET TO RECEIVE20-03-2024
XI. FIRE SCHEME APPROVALYET TO FILE FOR APPROVALNA
XII. SERVICE PLAN ESTIMATEYET TO FILE FOR APPROVALNA








Yes


Yes


As per HRERA format







GODREJ PARKLAND ESTATE, KURUKSHETRA
59.9659
0
1070
0
1065
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
21862.7921862.798329.41
Cost of the apartments000
Cost of the infrastructure16424.9516424.956820.07
Others costs5437.845437.841509.34


42038 Lakhs
20562 Lakhs
0 Lakhs
0 Lakhs
No
30-09-2026
30-09-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES/CERAMIC TILES
2WALL FINISHING DETAILSACRYLIC EMULSION PAINT/ OIL BOUND DISTEMPER
3KITCHEN DETAILSFLOOR: VITRIFIED TILES, WALL: CERAMIC TILES 2FT ABOVE COUNTER AND OBD PAINT ON REMAINING AREA, CEILING: OBD PAINT
4BATHROOM FITTINGSALL PROVIDED WITH STANDARD COMPANY MAKE
5WOOD WORK ETCLAMINATED/PAINTED FLUSH DOORS/MOULDED SHUTTER WITH WOODEN FRAME (PRE-HUNG LEVEL WITH LAMINATE)
6DOORS AND WINDOS FRAMESLAMINATED/PAINTED/POWER COATED FRAMES OF WOODEN/ALUMINIUM/UPVC MATERIAL
7GLASS WORK4MM AND ABOVE AS PER SPECIFICATIONS
8ELECTRIC FITTINGSAS PER BUILDING NORMS
9CONDUCTING AND WIRING DETAILSAS PER BUILDING NORMS
10CUPBOARD DETAILSNA
11WATER STORAGEUNDER GROUND WATER TANK & OVERHEAD WATER TANK
12LIFT DETAILSTOWER A & B: 3 PASSENGER LIFT & 1 SERVICE LIFT TOWER C: 4 PASSENGER LIFT & 1 SERVICE LIFT
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSPOWDER COATED/PAINTED ALUMINUM/UPVC WINDOWS WITH 4MM OR ABOVE THICK GLAZING AS PER SPECIFICATIONS
14DOORSLAMINATED/PAINTED FLUSH DOORS/MOULDED SHUTTER WITH WOODEN FRAME (PRE-HUNG LEVEL WITH LAMINATE)
14.1MAIN DOORSVENEER/LAMINATED/PAINTED FLUSH/FIRE DOOR WITH WOODEN FRAME
14.2INTERNAL DOORSLAMINATED/PAINTED FLUSH DOORS/MOULDED SHUTTER WITH WOODEN FRAME (PRE-HUNG LEVEL WITH LAMINATE)
15AIR CONDITIONINGAS PER SPECIFICATION. OF STANDARD MAKE
16ELECTRICAL FITTINGSAS PER SPECIFICATION. OF STANDARD MAKE
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADE PAINTS
20INTERNAL FINISHING10 TO 12MM THICK PLASTER ON BLOCKWORKS AND RCC WALLS AND COLUMNS WITH CEMENT MORTAR OF 1:5
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSACRYLIC EMULSION PAINT/ OIL BOUND DISTEMPER PAINT
1 . 3 CEILINGOIL BOUND DISTEMPER PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSACRYLIC EMULSION PAINT/ OIL BOUND DISTEMPER PAINT
2 . 3 CEILINGOIL BOUND DISTEMPER PAINT
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI-SKID CERAMIC TILES
3 . 2 WALLSCERAMIC TILES UPTO 7FT HEIGHT. OIL BOUND DISTEMPER PAINT ON THE REMAINING AREA.
3 . 3 CEILINGFALSE CEILING/GRID CEILING
3 . 4 COUNTERSGRANITE/STONE
3 . 5 SANITARY WARE/CP FITTINGSALL PROVIDED OF STANDARD COMPANY MAKE
3 . 6 FITTING/FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION PAINT/ OIL BOUND DISTEMPER PAINT
4 . 3 CEILINGOIL BOUND DISTEMPER PAINT
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI-SKID CERAMIC TILES
5 . 2 WALLSACRYLIC EMULSION PAINT/ OIL BOUND DISTEMPER PAINT
5 . 3 CEILINGOIL BOUND DISTEMPER PAINT
5 . 4 COUNTERSGRANITE/STONE
5 . 5 SANITARY WARE/CP FITTINGSALL PROVIDED OF STANDARD COMPANY MAKE
5 . 6 FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSCERAMIC TILES 2FT ABOVE COUNTER AND OBD PAINT ON REMAINING AREA
6 . 3 CEILINGOIL BOUND DISTEMPER PAINT
6 . 4 COUNTERSGRANITE/STONE
6 . 5 FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES
7 . 2 WALLS & CEILINGOIL BOUND DISTEMPER PAINT
7 . 3 TOILETANTI-SKID CERAMIC TILES
7 . 4 BALCONYANTI-SKID CERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORANTI-SKID CERAMIC TILES
8 . 2 WALLS & CEILINGACRYLIC EMULSION PAINT/ OIL BOUND DISTEMPER PAINT
8 . 3 RAILINGSMS RAILINGS
8 . 4 FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE












Sr. No.Document DescriptionDate of Document UploadView Document
1OFFER OF POSSESSION11-08-2024 ------
2NOC FOR HEIGHT CLEARANCE11-08-2024 ------
3LETTER OF INTENT11-08-2024 ------
4IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN11-08-2024 View Document
5ASSURANCE OF SEWERAGE CONNECTION11-08-2024 ------
6ZONING PLAN11-08-2024 View Document
7TREE CUTTING APPROVAL11-08-2024 ------
8ASSURANCE OF STORM WATER11-08-2024 ------
9ASSURANCE OF ULTIMATE LOAD11-08-2024 ------
10NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT16-08-2024 View Document
11ASSURANCE OF TREATED WATER FOR CONSTRUCTION PURPOSE11-08-2024 ------
12POSSESSION LETTER11-08-2024 ------
13COPY OF LICENSE ALONG WITH SCHEDULE OF LAND11-08-2024 View Document
14BASEMENT 2 - FLOOR PLAN30-08-2024 ------
15TOWER C - TERRACE FLOOR PLAN30-08-2024 ------
16SITE PLAN AND SERVICES30-08-2024 ------
17CONVENIENT SHOP30-08-2024 ------
18CASH FLOW STATEMENT OF THE PROPOSED PROJECT30-08-2024 View Document
19TOWER A & B - REAR ELEVATION30-08-2024 ------
20TOWER C - REFUGE FLOOR PLAN30-08-2024 ------
21BASEMENT 2 - AREA CHART AND SERVICE AREAS30-08-2024 ------
22TOWER C (COMMUNITY BUILDING) - GROUND FLOOR PLAN30-08-2024 ------
23TOWER C - SECTION CC30-08-2024 ------
24CLUB DROP OFF, CANOPY AND TOILETS DETAILS30-08-2024 ------
25TOWER A & B (COMMUNITY BUILDING) - GROUND FLOOR PLAN30-08-2024 ------
26TOWER A & B - GROUND COVERAGE30-08-2024 ------
27TOWER B - REFUGE FLOOR PLAN30-08-2024 ------
28SITE PLAN AND AREAS30-08-2024 ------
29BASEMENT 2 - PARKING AREA CALCULATIONS30-08-2024 ------
30BUILDING PLAN APPROVAL30-08-2024 ------
31IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN30-08-2024 View Document
32A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS30-08-2024 View Document
33CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT30-08-2024 View Document
34BASEMENT 1 - AREA CHART AND SERVICE AREAS30-08-2024 ------
35BASEMENT 1 - PARKING AREA CALCULATION30-08-2024 ------
36BASEMENT 1 - FLOOR PLAN30-08-2024 ------
37TOWER A - TYPICAL FLOOR PLAN30-08-2024 ------
38TOWER A - REFUGE FLOOR PLAN30-08-2024 ------
39TOWER A - TERRACE FLOOR PLAN30-08-2024 ------
40TOWER A & B - SECOND FLOOR PLAN30-08-2024 ------
41TOWER C - SIDE ELEVATIONS30-08-2024 ------
42TOWER A - MUMTY & ROOF PLAN30-08-2024 ------
43TOWER A - SECTION AA30-08-2024 ------
44TOWER A & B - FIRST FLOOR PLAN30-08-2024 ------
45TOWER A & B - SECTION BB30-08-2024 ------
46TOWER A & B - FRONT ELEVATION30-08-2024 ------
47TOWER A & B - SIDE ELEVATIONS30-08-2024 ------
48TOWER B - TYPICAL FLOOR PLAN30-08-2024 ------
49TOWER C - FRONT & REAR ELEVATIONS30-08-2024 ------
50TOWER B - TERRACE FLOOR PLAN30-08-2024 ------
51TOWER B - MUMTY & ROOF FLOOR PLAN30-08-2024 ------
52TOWER C - FIRST FLOOR PLAN30-08-2024 ------
53TOWER C - SECOND FLOOR PLAN30-08-2024 ------
54TOWER C - TYPICAL FLOOR PLAN30-08-2024 ------
55TOWER C - GROUND COVERAGE30-08-2024 ------
56TOWER C - MUMTY AND ROOF FLOOR PLAN30-08-2024 ------
57TOWER C - SECTION DD30-08-2024 ------
58TOWER C - CROWN DETAIL30-08-2024 ------
59DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.26-09-2024 View Document
60FOREST CLEARANCE26-09-2024 ------
61NATURAL CONSERVATION ZONE26-09-2024 ------