9891157743 (Number Shared by Promoter in Public)
vanessa.developers@gmail.com
XXXX842L
U70109HR2022PTC101674
SIRSA GREENS
VILLAGE KANGANPUR, SECTOR - 1
SIRSA
SIRSA
0000000000
9891157743 (Number Shared by Promoter in Public)
vanessa.developers@gmail.com
VIRENDRA KUMAR
0000000000
9891157743 (Number Shared by Promoter in Public)
vanessa.developers@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
COLLABORATION AGREEMENT AND GENERAL POWER OF ATTORNEY MADE BEFORE GRANT OF LICENSE.
Yes
ALL IMPORTANT DETAILS ARE COVERED IN THE AGREEMENT.
No
Yes
Yes
1436.46 Lakhs
18.63 Lakhs
0 Lakhs
1267.83 Lakhs
150.00 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
22328.914
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
10008.07
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
4338.59
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
COMMUNITY
4185.068
14
COMMERCIAL
998.00
Total
41858.642
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
296.38
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
252.41
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
164.36
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
62.25
SUBMITTED TO TOWN & COUNTRY PLANNING
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
88.40
SUBMITTED TO TOWN & COUNTRY PLANNING
6
STREET LIGHTING
55.20
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
25.00
SUBMITTED TO TOWN & COUNTRY PLANNING
8
PLAYGROUNDS AND PARKS
12.31
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO TOWN & COUNTRY PLANNING
10
SHOPPING AREA
0
SUBMITTED TO TOWN & COUNTRY PLANNING
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO TOWN & COUNTRY PLANNING
12
SCHOOL
0
SUBMITTED TO TOWN & COUNTRY PLANNING
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO TOWN & COUNTRY PLANNING
14
ANY OTHER
0
SUBMITTED TO TOWN & COUNTRY PLANNING
15
SEWERAGE
176.85
SUBMITTED TO TOWN & COUNTRY PLANNING
16
ELECTRIFICATION
79.53
SUBMITTED TO TOWN & COUNTRY PLANNING
17
UNDERGROUND TANK
37.15
SUBMITTED TO TOWN & COUNTRY PLANNING
18
RAIN WATER HARVESTING
18.00
SUBMITTED TO TOWN & COUNTRY PLANNING
03-11-2023 (date)
NA (date)
01-12-2023
29-10-2028
Plot Area(In Square Meter)
Number of plots in the project
22328.914
185
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
35.00
35.00
35.00
Water Supply System
35.00
35.00
35.00
Sewerage treatment & garbage disposal
8.00
8.00
8.00
Electricity Supply System
7.00
7.00
5.00
Storm Water Drainage
25.000
25.00
20.00
Parks and Playgrounds
2.00
2.00
2.00
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Electrification
7.00
7.00
7.00
Rain Water Harvesting
2.00
2.00
2.00
Underground Tank
5.00
4.00
3.00
Street Lights
6.00
6.00
6.00
Security and Firefighting Services
2.50
2.50
2.50
Sewerage
25.00
25.00
20.00
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
30.00
30.00
30.00
25.00
Water Supply System
30.00
0
15.00
10.00
Sewerage treatment & garbage disposal
7.00
7.00
7.00
7.00
Electricity Supply System
5.00
4.00
4.00
4.00
Storm Water Drainage
16.00
15.00
8.00
8.00
Parks and Playgrounds
1.00
1.00
1.00
0.56
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Underground Tank
3.00
2.00
2.00
2.00
Electrification
6.00
6.00
6.00
6.00
Street Lights
5.00
5.00
4.00
4.00
Security and Firefighting Services
2.00
2.00
2.00
2.00
Sewerage
20.00
15.00
15.00
15.00
Rain Water Harvesting
1.50
1.50
1.50
1.50
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
25.00
15.00
10.00
5.00
Water Supply System
9.00
9.00
9.00
9.00
Sewerage treatment & garbage disposal
5.00
5.00
5.00
5.00
Electricity Supply System
4.00
3.00
3.00
3.00
Storm Water Drainage
6.00
6.00
6.00
6.00
Parks and Playgrounds
0.50
0.35
0.35
0.35
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Lights
4.00
3.00
2.50
2.00
Underground Tank
2.00
2.00
2.00
2.00
Electrification
5.00
4.00
4.00
4.00
Security and Firefighting Services
1.50
1.50
1.25
1.25
Rain Water Harvesting
1.00
1.00
1.00
1.00
Sewerage
8.00
8.00
8.00
5.00
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5.00
5.00
5.00
4.00
Water Supply System
8.00
8.00
5.00
5.00
Sewerage treatment & garbage disposal
4.00
4.00
4.00
3.00
Electricity Supply System
3.00
2.50
2.50
2.50
Storm Water Drainage
5.00
5.00
5.00
5.00
Parks and Playgrounds
0.25
0.25
0.25
0.25
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Security and Firefighting Services
1.00
1.00
1.00
0.50
Electrification
4.00
3.00
3.00
3.00
Underground Tank
1.50
1.50
1.50
1.50
Street Lights
1.50
1.50
1.50
1.50
Rain Water Harvesting
0.50
0.50
0.25
0.25
Sewerage
4.00
2.00
2.00
2.00
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.00
0.38
Water Supply System
3.00
2.41
Sewerage treatment & garbage disposal
1.00
0.40
Electricity Supply System
2.00
0.75
Storm Water Drainage
2.00
1.36
Parks and Playgrounds
0.20
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Underground Tank
1.50
0.65
Electrification
3.00
1.53
Security and Firefighting Services
0.50
0
Street Lights
1.00
0.70
Sewerage
2.00
0.85
Rain Water Harvesting
0.25
0.25
Yes
No
IDBI BANK LTD. VILLAGE-BITHWANA, REWARI, HARYANA-123401
1879102000003889
IBKL0001879
123259003
1879
Mr. Rakesh Kumar, 3126108C, Company Bagh, Rewari, Haryana-123401.
Uploaded
Yes
Yes
Yes
No
No
No
No
No
No
Yes
Yes
No
Yes
Yes
Yes
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. I. LICENSE NO. 231 OF 2023
ALREADY BEEN OBTAINED
30-10-2023
II. II. ZONING PLAN (DRG. NO. DTCP 10069)
ALREADY BEEN OBTAINED
16-02-2024
III. III. FOREST NOC
ALREADY BEEN OBTAINED
19-09-2023
IV. IV. SERVICE PLAN AND ESTIMATE
APPLIED FOR BUT YET TO RECEIVE
03-11-2023
Yes
Yes
Provided
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT