9311081515 (Number Shared by Promoter in Public)
achievers_blds@rediffmail.com
https://achieversbuilders.com/
XXXX265M
U36911HR1999PTC034186
ACHIEVERS ELITE ENCLAVE
OWNERSHIP NO 20(PART) AND 21(PART) KALINDI HILLS SECTOR 49
BADKHAL
FARIDABAD
7678651542 (Number Shared by Promoter in Public)
vijaybhardwaj1313@gmail.com
CHANDER PRAKASH NARAIN
9910041104 (Number Shared by Promoter in Public)
achievers_blds@rediffmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
568156
10-05-2025
33929
STATE BANK OF INDIA
HRERA Panchkula
3392.916 (Sqr/mtrs)
2.64
2.64
3392.916 (Sqr/mtrs)
MCF/CTP/2025/137
Yes
169.65 Lakhs
0 Lakhs
0 Lakhs
61.94 Lakhs
107.71 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
1997.445
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1129.07
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
266.4
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
3392.915
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
No
WATER SUPPLY
No
ELECTRICITY
No
SEWAGE DISPOSAL
No
STORM WATER DRAINAGE
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
14.61
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
2.44
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
3.16
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
31.52
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
3.31
AS PER PROJECT REPORT
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
6.9
YET TO BE PREPARED
09-09-2024 (date)
NA (date)
01-06-2025
30-11-2025
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
154.08
1
2
143.38
1
3
142.53
1
4
144.89
1
5
147.56
1
6
93.48
1
7
108.31
1
8
213.96
1
9
183.96
1
10
176.69
1
11
169.86
1
12
163.02
1
13
156.19
1
Total
13
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
1.46
7.31
5.84
Water Supply System
0
0.24
1.22
0.98
Sewerage treatment & garbage disposal
0
0.33
1.66
1.32
Electricity Supply System
0
3.15
15.76
12.61
Storm Water Drainage
0
0.32
1.58
1.26
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0.69
3.45
2.76
Yes
Yes
STATE BANK OF INDIA PLOT NO 91 IDC FIRST FLOOR MG ROAD GURGAON 122001
0000044083949646
SBIN0050933
110002777
50933
Vijay Bhardwaj House No 1123 Sector 14 Faridabad
Prepared
Yes
Yes
Yes
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LAYOUT PLAN
ALREADY BEEN OBTAINED
09-09-2024
II. DEMARCATION PLAN
ALREADY BEEN OBTAINED
01-04-2025
III. LETTER OF INTENT
ALREADY BEEN OBTAINED
29-01-2025
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.