HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1661-2024
Submission Date : 11-06-2024 11:43:22 AM
Applicant Type : Firm
Project Type: NEW


ADORE BUILDCON LLP
A-43, F/F, FRONT SIDE SHERA MOHALLA, GARHI, EAST OF KAILASH, NEW DELHI
01292265143
9313930668 (Number Shared by Promoter in Public)
adorerealtech@gmail.com
ACB1526
ACBFA9616K













PROSPERITY HOMES
VILLAGE SOHNA, SECTOR 02 & 35
SOHNA
GURUGRAM
01292265143
8130999376 (Number Shared by Promoter in Public)
adorerealtech@gmail.com
DILSHAD
01292265143
8130999376 (Number Shared by Promoter in Public)
adorerealtech@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
12674310-05-20241363000IDBI BANK HRERA Gurugram
22663815-05-2024413685IDBI BANK HRERA Gurugram







6.76875 (Acre)
2.28
227.97
6.76875 (Acre)
License No 51 of 2024 dated 15 03 2024
Yes







21667 Lakhs
6104.53 Lakhs
9900 Lakhs
1493.01 Lakhs
4169.46 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2.87745
3CONSTRUCTION OF ROADS2.566
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.988
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.1033
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0.234
Total6.76875




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS150AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM110AS PER PROJECT REPORT
3STORM WATER DRAINAGE98AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM200AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL102AS PER PROJECT REPORT
6STREET LIGHTING62AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING50AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS78AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE6.99AS PER PROJECT REPORT
10SHOPPING AREA136.70AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM50AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER600AS PER PROJECT REPORT


NA (date)
27-05-2024 (date)
01-10-2024
14-06-2029
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings56.72742
Apartment/Shops/Other Buildings56.8485869
Apartment/Shops/Other Buildings43.83888
Apartment/Shops/Other Buildings30.26741
Apartment/Shops/Other Buildings30.351011





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6.19
Shops0
Plots0

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6.196.196.196.19
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6.196.196.196.19
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6.196.196.196.19
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6.196.196.15
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.6919.6919.69
Water Supply System13.1313.1313.13
Sewerage treatment & garbage disposal15.7515.7515.75
Electricity Supply System32.8232.8232.82
Storm Water Drainage10.5010.5010.50
Parks and Playgrounds10.5010.5010.50
Clubhouse/community centres6.576.576.57
Shopping area6.576.576.57
Other15.7515.7515.75

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.6919.6919.6919.69
Water Supply System13.1313.1313.1313.13
Sewerage treatment & garbage disposal15.7515.7515.7515.75
Electricity Supply System32.8232.8232.8232.82
Storm Water Drainage10.5010.5010.5010.50
Parks and Playgrounds10.5010.5010.5010.50
Clubhouse/community centres6.576.576.576.57
Shopping area6.576.576.576.57
Other15.7515.7515.7515.75

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.6919.6919.6919.69
Water Supply System13.1313.1313.1313.13
Sewerage treatment & garbage disposal15.7515.7515.7515.75
Electricity Supply System32.8232.8232.8232.82
Storm Water Drainage10.5010.5010.5010.50
Parks and Playgrounds10.5010.5010.5010.50
Clubhouse/community centres6.576.576.576.57
Shopping area6.576.576.576.57
Other15.7515.7515.7515.75

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.6919.6919.6919.69
Water Supply System13.1313.1313.1313.13
Sewerage treatment & garbage disposal15.7515.7515.7515.75
Electricity Supply System32.8232.8232.8232.82
Storm Water Drainage10.5010.5010.5010.50
Parks and Playgrounds10.5010.5010.5010.50
Clubhouse/community centres6.576.576.576.57
Shopping area6.576.576.576.57
Other15.7515.7515.7515.75

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.65
Water Supply System13.05
Sewerage treatment & garbage disposal15.75
Electricity Supply System32.70
Storm Water Drainage10.50
Parks and Playgrounds10.50
Clubhouse/community centres6.45
Shopping area6.45
Other15.75












Yes
No
ICICI BANK UNIT NO 3 GROUND FLOOR GOOD EARTH BUSINESS BAY SECTOR 58 GURGAON 122098
777705160426
ICIC0004603
110229377
004603
jetaish Kumar Gupta R/o 247, Sector 28, FAridabad Kaptan Singh R/o 64 Village Budena, Sector 86, Faridabad
yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO 51 OF 2024ALREADY BEEN OBTAINED15-03-2024
II. ZONING PLANALREADY BEEN OBTAINED15-03-2024
III. DEMARCATION PLANALREADY BEEN OBTAINED16-02-2024
IV. BUILDING PLANALREADY BEEN OBTAINED27-05-2024
V. ENVIRONMENTAL CLEARANCEAPPLIED FOR BUT YET TO RECEIVE08-07-2024








Yes


Yes


Important Provision of RERA have been incorporated in the draft agreements













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES/CERAMIC TILES
2WALL FINISHING DETAILSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
3KITCHEN DETAILSCOUNTER TOP - MARBLE TOP/ KOTA STONE, TILE UP TO 2 FEET HEIGHT ABOVE THE COUNTER
4BATHROOM FITTINGSPPR PIPES/ CPVC PIPES, CP FITTING OD ISI MARKED
5WOOD WORK ETCFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
6DOORS AND WINDOS FRAMESMS Z SECTION / PRESS STEEL/ POWER COATED ALUMINUM
7GLASS WORK5 MM PLAIN GLASS ISI MARKED
8ELECTRIC FITTINGSISI MARKED
9CONDUCTING AND WIRING DETAILSISI MARKED
10CUPBOARD DETAILSNA
11WATER STORAGEWATER TREATMENT PLANT
12LIFT DETAILS2 LIFT IN EACH TOWER
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSAS MENTIONED BELOW
14.1MAIN DOORSFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
14.2INTERNAL DOORSFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEPLAIN TEXTURE PAINT
20INTERNAL FINISHINGCOLOUR WASH/ DRY DISTEMPER/ OIL BOUND DISTEMPER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES/CERAMIC TILES
1 . 2 WALLSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
1 . 3 CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES/CERAMIC TILES
2 . 2 WALLSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
2 . 3 CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILES
3 . 2 WALLSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
3 . 3 CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSISI MARKED
3 . 6 FITTING/FIXTURESISI MARKED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES/CERAMIC TILES
4 . 2 WALLSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
4 . 3 CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILES
5 . 2 WALLSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
5 . 3 CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSISI MARKED
5 . 6 FIXTURESISI MARKED
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES/CERAMIC TILES
6 . 2 WALLSCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
6 . 3 CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
6 . 4 COUNTERSNA
6 . 5 FIXTURESISI MARKED
6 . 6 KITCHEN APPLIANCESISI MARKED
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES/CERAMIC TILES
7 . 2 WALLS & CEILINGCOLOUR WASH/DRY DISTEMPER/ OIL BOUND DISTEMPER (OBD)
7 . 3 TOILETNA
7 . 4 BALCONYCERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN11-06-2024 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN11-06-2024 View Document
3TERRACE PLAN 202-08-2024 ------
4UNIT PLAN 102-08-2024 ------
5CERTIFICATE COST INCURED02-08-2024 ------
6STROM WATER LINE ASSURANCE02-08-2024 ------
7AIRPORT NOC02-08-2024 ------
8BR-III02-08-2024 ------
9JAMABANDI02-08-2024 ------
10IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN02-08-2024 View Document
11TOWER 5 ELEVATION02-08-2024 ------
12UNIT PLAN02-08-2024 ------
13NOC DHBVN02-08-2024 ------
14NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT02-08-2024 View Document
15BASEMENT PLAN 202-08-2024 ------
16DEMARCATION PLAN02-08-2024 View Document
17NOC FROM LENDER02-08-2024 ------
18CA CERTIFICATE PROJECT COST NEW02-08-2024 ------
19NON- ENCUMBRANCE CERTIFICATE02-08-2024 ------
20COPY OF LICENSE ALONG WITH SCHEDULE OF LAND02-08-2024 View Document
21COI - ACB1526 - ADORE BUILDCON LLP02-08-2024 ------
22PERT CHART AND FUND FLOW02-08-2024 ------
23PERT CHART02-08-2024 ------
24CA CERTIFICATE INVENTORY02-08-2024 ------
25FRESH WATER ASSURANCE02-08-2024 ------
26ELEVATION TOWER 1002-08-2024 ------
27LOI02-08-2024 ------
28BASEMENT PLAN 102-08-2024 ------
29BASEMENT PLAN 302-08-2024 ------
30COMMERCIAL BLOCK A_ELEVATION02-08-2024 ------
31COMMERCIAL TERRACE PLAN02-08-2024 ------
32FOREST NOC02-08-2024 ------
33DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD02-08-2024 View Document
34GROUND AND TERRACE PLAN02-08-2024 ------
35SECTION ELEVATION02-08-2024 ------
36ELEVATION TOWER 502-08-2024 ------
37TITLE SEARCH REPORT02-08-2024 ------
38STP TREATED WATER ASSURANCE02-08-2024 ------
39BOARD RESOLUTION02-08-2024 ------
40ELEVATION 302-08-2024 ------
41LC IV02-08-2024 ------
42DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.02-08-2024 View Document
43CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT02-08-2024 View Document
44SERVICE ESTIMATE APPLICATION02-08-2024 ------
45SEWERAGE CONNECTION ASSURANCE02-08-2024 ------
46ZONING PLAN02-08-2024 View Document
47ELEVATION 402-08-2024 ------