HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1451-2024
Submission Date : 17-05-2024 04:12:25 PM
Applicant Type : Company
Project Type: NEW




DAA HOME REALTORS PRIVATE LIMITED
458-R, MODEL TOWN, PANIPAT-132103
9896253992 (Number Shared by Promoter in Public)
daahome21@gmail.com
XXXX311Q
U70101HR2021PTC094309
 
 


 
 


 
 







DAA HOME PALM DRIVE
VILLAGE PHOOSGARH AND INDRI SECTOR 7
INDRI
KARNAL
9896253992 (Number Shared by Promoter in Public)
daahome21@gmail.com
GORAV KUMAR
9896253992 (Number Shared by Promoter in Public)
daahome21@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1246416-03-2024541500CENTRAL BANK OF INDIAHRERA Panchkula







25.0125 (Acre)
1.00 FOR PLOTTED AND 1.5 FOR COMMERCIAL
1.00
25.0125 (Acre)
LICENSE NO. 33 OF 2024 DATED 29.02.2024 (VALID UPTO 28.02.2029)
No
Address     H. NO. 1135, NEW HOUSING BOARD COLONY, KARNAL
Address     H. NO. 1135, NEW HOUSING BOARD COLONY, KARNAL
Annexure-B- COLLABORATION AGREEMENT AND SPECIFIC POWER OF ATTORNEY EXECUTED
YES, AGREEMENTS ARE REGISTERED BEFORE GRANT OF LICENSE.
Yes
COLLABORATION AGREEMENT REGD. VIDE VASIKA NO. 404 DATED 15.05.2023, ADDENDUM AGREEMENT EXECUTED VIDE VASIKA NO. 793 DATED 28.06.2023 & ADDENDUM AGREEMENT EXECUTED VIDE VASIKA NO. 113 DATED 23.04.2024. COLLABORATION AGREEMENT REGD. VIDE VASIKA NO. 404 DATED 15.05.2023, ADDENDUM AGREEMENT EXECUTED VIDE VASIKA NO. 793 DATED 28.06.2023 & ADDENDUM AGREEMENT EXECUTED VIDE VASIKA NO. 113 DATED 23.04.2024. THE BELOW HAS BEEN ENTERED BETWEEN THE PARTIES: CLAUSE- 13 OF ADDENDUM STATED THAT: 50% SHARE OF THE TOTAL DEVELOPED AREA INCLUDING RESIDENTIAL AND COMMERCIAL SHALL BE ENTITLED IN FAVOUR OF THE LAND OWNER. AND THE DEVELOPER SHALL HAVE RIGHTS TO BOOK, MARKET, RECEIVED SALE CONSIDERATION, SELL AND TO EXECUTE THE SALE/ CONVEYANCE DEED IN FAVOUR OF PROSPECTIVE BUYERS OF THE PROJECT. CLAUSE NO.43 OF ADDENDUM STATED THAT: THE AGREEMENT IS IRREVOCABLE. SPA EXECUTED VIDE VASIKA NO. 26 DATED 15.05.2023 CLAUSE NO. 9 & 12 -RIGHTS GIVEN FOR SIGNING OF AGREEMENT TO SALE AND TO EXECUTE THE SALE DEED/ CONVEYANCE DEEDS. CLAUSE NO. 33- THE SPA IS IRREVOCABLE. GIST IS ENCLOSED.
No
No
Yes







4803.00 Lakhs
2400.00 Lakhs
0.00 Lakhs
1975.000 Lakhs
428.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD14.371
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.00
3CONSTRUCTION OF ROADS5.72250
4PAVEMENTS0.00
5PARKS AND PLAYGROUNDS1.9100
6GREEN BELTS0.00
7VEHICLE PARKINGS0.00
8ELECTRICITY SUB-STATION0.00
9CLUB HOUSE0.0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.00
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES2.51
12ANY OTHER0.00
13COMMERCIAL0.49900
Total25.0125




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS395.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM316.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE276.50AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM493.75AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL296.25AS PER PROJECT REPORT
6STREET LIGHTING59.25AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS133.73AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


29-02-2024 (date)
NA (date)
15-04-2024
28-02-2029
Plot Area(In Square Meter)Number of plots in the project
139.534
147.0612
133.312
146.1232
149.3434
111.6332
111.3516
81.066
133.793
145.5618
132.6420
127.1820
128.9344
126.0322
139.6510
130.342
139.3910
128.2440
143.329
128.2212
125.6324
118.2910
121.445
90.482
112.352
125.7215
135.906
74.606
93.6911
78.231
98.0023
145.901
128.7061
135.9971
57.471


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.7519.7519.75
Water Supply System15.8015.8018.80
Sewerage treatment & garbage disposal14.8114.8114.81
Electricity Supply System24.6924.6924.69
Storm Water Drainage13.8313.8313.83
Parks and Playgrounds6.696.696.69
Clubhouse/community centres000
Shopping area000
Other2.962.962.96

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.7519.7519.7519.75
Water Supply System15.8015.8015.8015.80
Sewerage treatment & garbage disposal14.8114.8114.8114.81
Electricity Supply System24.6924.6924.6924.69
Storm Water Drainage13.8313.8313.8313.83
Parks and Playgrounds6.696.696.696.69
Clubhouse/community centres0000
Shopping area0000
Other2.962.962.962.96

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.7519.7519.7519.75
Water Supply System15.8015.8015.8015.80
Sewerage treatment & garbage disposal14.8114.8114.8114.81
Electricity Supply System24.6924.6924.6924.69
Storm Water Drainage13.8313.8313.8313.83
Parks and Playgrounds6.696.696.696.69
Clubhouse/community centres0000
Shopping area0000
Other2.962.962.962.96

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.7519.7519.7519.75
Water Supply System15.8015.8015.8015.80
Sewerage treatment & garbage disposal14.8114.8114.8114.81
Electricity Supply System24.6924.6924.6924.69
Storm Water Drainage13.8313.8313.8313.83
Parks and Playgrounds6.696.696.696.69
Clubhouse/community centres0000
Shopping area0000
Other2.962.962.962.96

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.7519.7519.7519.85
Water Supply System15.8015.8015.8015.80
Sewerage treatment & garbage disposal14.8114.8114.8114.81
Electricity Supply System24.6924.6924.6924.69
Storm Water Drainage13.8313.8313.8313.81
Parks and Playgrounds6.696.696.696.69
Clubhouse/community centres0000
Shopping area0000
Other2.962.962.962.96

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.85
Water Supply System15.80
Sewerage treatment & garbage disposal14.81
Electricity Supply System24.69
Storm Water Drainage13.83
Parks and Playgrounds6.69
Clubhouse/community centres0
Shopping area0
Other2.96












No
No
HDFC BANK LTD, INDRI
50200087550911
HDFC0002185
132240152
2185
Sh. Dhiraj Kumar Malik R/o 458-R, Model Town Panipat Haryana-132103
Uploaded in Upload Section.











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 33 OF 2024 ALREADY BEEN OBTAINED29-02-2024
II. APPROVAL OF DEMARCATION-CUM-ZONING PLAN ALREADY BEEN OBTAINED17-05-2024








Yes


Yes


THE PROVISIONS OF RERA ACT AND RULES SHALL BE INCORPORATED IN THE DRAFT AGREEMENT TO SELL.







DAA HOME RESIDNECY
7.0875
0
131
0
65
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
633.850633.85
Cost of the apartments000
Cost of the infrastructure283.500200.50
Others costs350.3520350.352


1139.81 Lakhs
23.30 Lakhs
0 Lakhs
0 Lakhs
No
09-12-2026
09-12-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED COLONY
2WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
3KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED COLONY
4BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5WOOD WORK ETCNOT APPLICABLE BEING PLOTTED COLONY
6DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED COLONY
7GLASS WORKNOT APPLICABLE BEING PLOTTED COLONY
8ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
10CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED COLONY
11WATER STORAGENOT APPLICABLE BEING PLOTTED COLONY
12LIFT DETAILSNOT APPLICABLE BEING PLOTTED COLONY
13EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
13.1WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
14DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.1MAIN DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.2INTERNAL DOORSNOT APPLICABLE BEING PLOTTED COLONY
15AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED COLONY
16ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
17CNG PIPE LINENOT APPLICABLE BEING PLOTTED COLONY
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED COLONY
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED COLONY
20INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED COLONY
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
1 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
1 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
2 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
2 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . 4 MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
3 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
3 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
3 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
3 . 6 FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
4 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
4 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
4 . 4 WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
5 . TOILET
5 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
5 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
5 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
5 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5 . 6 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
6 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
6 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
6 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
6 . 5 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED COLONY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
7 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
7 . 3 TOILETNOT APPLICABLE BEING PLOTTED COLONY
7 . 4 BALCONYNOT APPLICABLE BEING PLOTTED COLONY
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
8 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
8 . 3 RAILINGSNOT APPLICABLE BEING PLOTTED COLONY
8 . 4 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN18-04-2024 View Document
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT18-04-2024 View Document
3COPY OF LICENSE ALONG WITH SCHEDULE OF LAND18-04-2024 View Document
4DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.25-04-2024 View Document
5DEMARCATION PLAN17-05-2024 View Document
6ZONING PLAN17-05-2024 View Document
7IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN17-05-2024 View Document