HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1612-2024
Submission Date : 11-04-2024 06:52:59 PM
Applicant Type : Company
Project Type: NEW




ST. PATRICKS REALTY PVT. LTD.
THE MEDIAN, CENTRAL PARK RESORTS, OFF SOHNA ROAD, SECTOR 48, GURUGRAM, HARYANA-122018
1244928164
9871640340 (Number Shared by Promoter in Public)
contact@centralpark.in
https://www.centralpark.in/
XXXX877J
U45200HR2008PTC037964
 
 


 
 


 
 







GROUP HOUSING COLONY- BIGNONIA TOWERS
VILLAGE DHUNELA, SECTOR-32 SOHNA- GURUGRAM, HARYANA
GURGAON
GURUGRAM
1244928164
9871640340 (Number Shared by Promoter in Public)
contact@centralpark.in
CHIRAG GEHLOT
1244928164
9871640340 (Number Shared by Promoter in Public)
contact@centralpark.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
145487129-03-20241480000INDUSLND BANK LTD.HRERA Gurugram







7.3563 (Acre)
1.87
1.85
7.3563 (Acre)
136 of 2023
No
Address     THE MEDIAN, CENTRAL PARK RESORTS, OFF SOHNA ROAD, SECTOR 48, GURUGRAM, HARYANA-122018
Address     RZ-D-17-C, MAHAVIR VIHAR, NEW DELHI- 110045
Address     RZ-D-17-C, MAHAVIR VIHAR, NEW DELHI- 110045
Annexure-B- COLLABORATOR
BEFORE RECEIVING THE LICENSE
Yes
COLLABORATION AGREEMENT IS ANNEXED IN PART-A OF ANNEXURES.
No
Yes
Yes







105959.37 Lakhs
6654.16 Lakhs
70683.83 Lakhs
4584.72 Lakhs
24036.66 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.644
3CONSTRUCTION OF ROADS 1.2
4PAVEMENTS 0.2
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 1.058
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0.37
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.33
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 1.3
Total5.102




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS425.05YET TO BE PREPARED
2WATER SUPPLY SYSTEM85.01YET TO BE PREPARED
3STORM WATER DRAINAGE141.68YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM850.09YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL113.35YET TO BE PREPARED
6STREET LIGHTING85.01YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING340.04YET TO BE PREPARED
8PLAYGROUNDS AND PARKS141.68YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER70.84YET TO BE PREPARED
15SEWERAGE SYSTEM141.68YET TO BE PREPARED
16UNDERGROUND WATER TANK127.51YET TO BE PREPARED
17RAIN WATER HARVESTING28.34YET TO BE PREPARED
18ELECTRICAL SUB STATION283.36YET TO BE PREPARED


NA (date)
NA (date)
01-04-2024
30-06-2028
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings157.47701
Apartment/Shops/Other Buildings211.26351
Apartment/Shops/Other Buildings203.92881





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1693.512308.943540.20
Shops1.731.801.94
Plots000
Land Cost142.44309.24298.80
EDC408.360391.77
Others302.381836.622071.88
IDC000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4121.344296.283935.793935.79
Shops1.940.984.094.09
Plots0000
IDC0000
Land Cost22.8429.7040.7466
EDC0374.640358.60
Others614.57714.57839.571000.04

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4158.314158.314303.814879.12
Shops4.094.094.096.05
Plots0000
Others1295.981434.071407.391438.54
Land Cost112.33113.32102.52212.81
EDC0341.650325.43
IDC0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments5317.774382.044365.424805.23
Shops7.167.237.237.23
Plots0000
EDC0308.660292.26
Land Cost210.84301.09343.07226.48
IDC0000
Others1176.08977.38909.88842.38

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4470.344241.71884.96884.96
Shops3.753.750.500.50
Plots0000
IDC0000
Land Cost419.70449.71986.48272.85
EDC0000
Others1024.88957.38889.88552.38




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Construction of Circulation Road0
Electrical Substation0
Parking0
Rain Water Harvesting0
Renewable Energy System0
Security and Fire Fighting0
Sewerage System0
Street Lighting0
Underground Water Tank0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other01.421.421.42
Construction of Circulation Road000
Sewerage System0000
Electrical Sub Station000
Street Lighting and Fire Fighting0
Rnewable Energy System0
Parking0000
Underground Water Tank000
Rain Water Harvesting000
Renewable Energy System0
Security and Fire Fighting0
Street Lighting000
Rain water harvesting0
Construction of circulation road0
Underground water tank0
Security and fire fighting0
Renewable energy system0
Electrical sub station0
Renewal Energy System0
Security and Fire fighting0

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other1.422.832.832.83
security and fire fighting0
Sewerage System0
Parking0000
underground water tank0
Rain water harvesting0000
Electrical Sub Station00
Construction of circulation road0000
Renewable energy system000
Street Lighting0000
Underground water tank000
Security and fire fighting00
Sewerage system00
Electrical sub station00
Renewable energy System0
Security and Fire fighting0
Sewerag System0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements051.0151.0151.01
Water Supply System008.5015.30
Sewerage treatment & garbage disposal00011.33
Electricity Supply System0085.01153.02
Storm Water Drainage0014.1725.50
Parks and Playgrounds0014.1714.17
Clubhouse/community centres0000
Shopping area0000
Other2.835.675.675.67
Parking0000
Sewerage System014.1725.50
Street Lighting008.5015.30
Security and Fire Fighting034.00
Renewable Energy System000
Underground Water Tank0012.75
Rain Water Harvesting02.835.10
Electrical Sub Station028.3451.01
Construction of Circulation Road000
Security and Fire fighting0
Security and fire fighting0
Underground water tank0
Construction of circulation road0
Electrical sub station0
Rain water harvesting0
Sewerage system0
Renewable energy system0

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements51.0151.0151.0151.01
Water Supply System15.3015.3015.3015.30
Sewerage treatment & garbage disposal20.4020.4020.4020.40
Electricity Supply System153.02153.02153.02153.02
Storm Water Drainage25.5025.5025.5025.50
Parks and Playgrounds25.5025.5025.5025.50
Clubhouse/community centres0000
Shopping area0000
Other5.675.675.675.67
Security and Fire Fighting61.2161.21
Parking0000
Street Lighting15.3015.3015.3015.30
Sewerage System25.5025.5025.5025.50
Rain Water Harvesting5.105.105.105.10
Construction of Circulation Road000
Electrical Sub Station51.0151.0151.0151.01
Underground Water Tank25.5038.2538.2512.75
Renewable Energy System000
Construction of circulation road0
Renewable energy system0
Security and Fire fighting51.01
Security and fire fighting61.21

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements51.010
Water Supply System00
Sewerage treatment & garbage disposal20.400
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds11.330
Clubhouse/community centres00
Shopping area00
Other5.678.50
Electrical Sub Station00
Rain Water Harvesting00
Underground Water Tank00
Parking00
Renewable Energy System00
Security and Fire fighting0
Construction of circulation road0
Street Lighting00
Sewerage System00
Construction of Circulation Road0
Security and Fire Fighting61.21












No
No
INDUSIND BANK, BARAKHAMBA ROAD, NEW DELHI
251310202302
INDB0000005
110234002
000005
St. Patricks Realty Private Limited











No
No
Yes
No
No
No
No
No
No
No


No
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. ZONING ALREADY BEEN OBTAINED30-06-2023
II. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED30-01-2024
III. LICENCEALREADY BEEN OBTAINED30-06-2024
IV. BUILDING PLAN APPLIED FOR BUT YET TO RECEIVENA








Yes


Yes









COMMERCIAL PLOTTED COLONY "MAG MILE"
5.0
0
59
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6194.116194.1126.37
Cost of the apartments00212.47
Cost of the infrastructure227.64227.64702.02
Others costs5966.475966.470


0 Lakhs
0 Lakhs
2500 Lakhs
0 Lakhs
No
26-03-2028
26-03-2028










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEITALIAN MARBLE, RECON WOODEN, VINYL FLOOR(GYM), RUBBER FLOORING (GYM), EPOXY FLOOR, DECK IPE ( FOR OUTDOOR AREAS), TILE ( UTILITY AND SERVICE AREAS)
2WALL FINISHING DETAILSITALIAN WALL CLADDING, VENEER PANELING, MIRROR, METAL PROFILES, SANDWICH GLASS, PAINT
3KITCHEN DETAILSTILE CLADDING, SS EQPT., GAS BANK, INDUSTRIAL EXHAUST
4BATHROOM FITTINGSSS/PWD COATED FF&E, SANITARYWARE
5WOOD WORK ETCBWP GRADE PLY/HDHMR
6DOORS AND WINDOS FRAMESFLUSHED DOORS/ FIRE RATED DOORS
7GLASS WORKSANDWICH GLASS, FLOAT GLASS, LACQUER
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSFRLSH, PCV, MS CONDUIT, BX METAL SPUN FLEXIBLE
10CUPBOARD DETAILSFRLSH, PCV, MS CONDUIT, BX METAL SPUN FLEXIBLE
11WATER STORAGEUGT/SWP- TILED, OHT- CPVC
12LIFT DETAILSITALIAN STONE,VENEER, METAL PROFILES
13EXTERNAL GLAZINGSDGU- ALUMINIUM FRAME
13.1WINDOWS/GLAZINGSDGU- ALUMINIUM FRAME
14DOORSFLUSHED- VENEER
14.1MAIN DOORSFLUSHED- VENEER
14.2INTERNAL DOORSFLUSHED- VENEER/ AL WITH SANDWICH GLASS
15AIR CONDITIONINGDAIKEN/SAMGSUNG/MITSUBISHI/KONE
16ELECTRICAL FITTINGSSWITCHES/SOCKETS AND SWITCHGEARS
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMERECON STONE/STONE/PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORMARBLE
1 . 2 WALLSPOP PUNNING WITH ACRYLIC EMULSION PAINT
1 . 3 CEILINGOIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING / MARBLE
2 . 2 WALLSPOP PUNNING WITH ACRYLIC EMULSION PAINT
2 . 3 CEILINGOIL BOUND DISTEMPER
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI SKID TILES / MARBLE
3 . 2 WALLSHIGH QUALITY DESIGNER CERAMIC TILES / MARBLE
3 . 3 CEILINGOIL BOUND DISTEMPER
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSCPVC / PVC
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING / MARBLE
4 . 2 WALLSPOP PUNNING WITH ACRYLIC EMULSION PAINT
4 . 3 CEILINGOIL BOUND DISTEMPER
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI SKID TILES / MARBLE
5 . 2 WALLSHIGH QUALITY DESIGNER CERAMIC TILES / MARBLE
5 . 3 CEILINGOIL BOUND DISTEMPER
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSCPVC / PVC
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORANTI SKID /VITRIFIED TILES / MARBLE
6 . 2 WALLSTILES UPTO 2 FT ABOVE THE COUNTER
6 . 3 CEILINGOIL BOUND DISTEMPER
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGOIL BOUND DISTEMPER
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 10-04-2024 View Document
2 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 11-04-2024 View Document
3 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 10-04-2024 View Document
4 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 10-04-2024 View Document
5 DEMARCATION PLAN 11-04-2024 View Document
6 ZONING PLAN 11-04-2024 View Document
7 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 11-04-2024 View Document
8 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 11-04-2024 View Document
9 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 11-04-2024 View Document
10 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 11-04-2024 View Document