HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1591-2024
Submission Date : 22-03-2024 01:20:59 PM
Applicant Type : Company
Project Type: NEW




UNION BUILDMART PRIVATE LIMITED
41ST FLOOR, TOWER-1, M3M, INTERNATIONAL FINANCIAL CENTER, SECTOR-66, BADSHAHPUR, GURGAON, HARYANA
01244732000
9711348349 (Number Shared by Promoter in Public)
unionbuildmart0207@gmail.com
http://unionbuildmart.in
XXXX843M
U70100HR2012PTC089615
 
 


 
 


 
 


 
 







M3M CAPITAL PHASE-3
SECTOR-113, VILLAGE CHAUMA, GURUGRAM, HARYANA
GURGAON
GURUGRAM
01244732000
9711348349 (Number Shared by Promoter in Public)
Unionbuildmart0207@gmail.com
VIMAL SAROHA
01244732000
9711348349 (Number Shared by Promoter in Public)
Unionbuildmart0207@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150647722-03-20242042000ICICI BANK LIMITEDHRERA Gurugram
250647822-03-2024432600ICICI BANK LIMITEDHRERA Gurugram







0.91875 (Acre)
4.456
0.712
15.0625 (Acre)
106 OF 2021 DATED 16.12.2021 214 OF 2023 DATED 20.10.2023
No
Address     CABIN-2,LGF,F-22,SUSHANT SHOPPING ARCADE, SUSHANT LOK PHASE-1,GURUGRAM-122002 HARYANA
Address     CABIN-2,LGF,F-22,SUSHANT SHOPPING ARCADE, SUSHANT LOK PHASE-1,GURUGRAM-122002 HARYANA
Address     41ST FLOOR,TOWER-1,M3M INTERNATIONAL FINANCIAL CENTER, SECTOR 66,GURUGRAM,HARYANA
Annexure-B- COLLABORATOR VIDE DEVELOPMENT RIGHTSAGREEMENT 7322 DATED 07.10.2019
BEFORE GRANT OF LICENCE
Yes
AS ATTACHED IN FOLDER A
No
Yes
Yes







51928.22 Lakhs
14082.52 Lakhs
21907.53 Lakhs
1205.18 Lakhs
14732.99 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.91875
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total0.91875




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS114.12AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM39.43AS PER PROJECT REPORT
3STORM WATER DRAINAGE17.12AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM131.24AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL28.53AS PER PROJECT REPORT
6STREET LIGHTING11.41AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING73.15AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS72.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0.00YET TO BE PREPARED
10SHOPPING AREA0.00YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0.00YET TO BE PREPARED
12SCHOOL0.00YET TO BE PREPARED
13HOSPITAL/DISPENSARY0.00YET TO BE PREPARED
14ANY OTHER0.00YET TO BE PREPARED
15BOUNDARY WALL21.75AS PER PROJECT REPORT
16STP36.80AS PER PROJECT REPORT
17UNDERGROUND WATER TANK43.71AS PER PROJECT REPORT
18RAIN WATER HARVESTING2.85AS PER PROJECT REPORT
19ELECTRICAL SUB STATION196.90AS PER PROJECT REPORT
20SWITCHING STATION85.59AS PER PROJECT REPORT
21CONSULTANCY154.07AS PER PROJECT REPORT
22INFRA ESTABLISHMENTS114.13AS PER PROJECT REPORT
23HARDSCAPE AND SOFTSCAPE57.06AS PER PROJECT REPORT
24PARKING5.30AS PER PROJECT REPORT


19-02-2024 (date)
19-02-2024 (date)
01-03-2024
31-03-2027
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings34690.462682





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments506.291179.301367.96
Shops000
Plots000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1408.201837.392017.032411.83
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2181.042722.41979.50906.27
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1015.31
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0006.85
Water Supply System003.942.37
Sewerage treatment & garbage disposal002.851.71
Electricity Supply System0000
Storm Water Drainage001.711.03
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Consultancy0030.810
Infra Establishments05.7111.415.71
Rain water harvesting000.290.17












Yes
No
ICICI BANK LIMITED AND EMAAR EMERALD PLAZA
777705004541
ICIC0005885
5885
5885
1) Mr. Vyom Shakti Nigam-D3/103 Paras city E3 Arera Colony Bhopal M.P. 462016 2) Ms. Amarjot Kaur Sahni-3/66 Subhash Nagar West Delhi 110027 3) Ms. Shubhra Bakshi- House No 10/6, DLF Phase-1, Sikanderpur Ghosi, Gurgaon, Haryana- 122002 4) Ms. Surbhi- Flat No-3-905, 9th floor, Sector-103, grandiva, Daultabad, Gurgaon, Haryana-122006 5) Mr. Vidya Sagar-3G-208, Faridabad, NIT Faridabad, Haryana- 121001 6) Mr. Pratap Singh-10A Pocket 2 Mayur Vihar East Delhi 110096 7) Mr. Pradeep Kumar Katiyar- 357, Bakhothi Purwa, Thana Bilaur, Kanpur- 209202, Uttar Pradesh
UPLOADED











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE APPROVALALREADY BEEN OBTAINED16-12-2021
II. LICENSE APPROVALALREADY BEEN OBTAINED20-12-2023
III. ASSURANCE- SEWERAGEALREADY BEEN OBTAINED04-03-2024
IV. ASSURANCE- STORM WATERALREADY BEEN OBTAINED28-02-2024
V. ASSURANCE- DRINKING WATERALREADY BEEN OBTAINED29-02-2024
VI. CONSTRUCTION WATER NOCALREADY BEEN OBTAINED04-03-2024
VII. BR-IIIALREADY BEEN OBTAINED19-02-2024
VIII. AAI NOCALREADY BEEN OBTAINED13-12-2023
IX. ASSURANCE- ELECTRICAL LOADALREADY BEEN OBTAINED17-11-2021
X. FOREST NOCALREADY BEEN OBTAINED30-09-2016








Yes


Yes


AS PER THE RULES AND REGULATIONS OF HARERA







M3M CAPITAL
5.004
750
0
706
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
47692.3447193.320
Cost of the apartments24779.9330624.50
Cost of the infrastructure2266.193531.730
Others costs20646.2113037.090


53863 Lakhs
67686 Lakhs
600 Lakhs
600 Lakhs
No
30-06-2026
30-06-2026




M3M CAPITAL PHASE-2
7.7139
1760
0
1656
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
100838.26100838.260
Cost of the apartments71820.3871820.380
Cost of the infrastructure3897.823897.820
Others costs25120.0625120.060


100832.82 Lakhs
181254.36 Lakhs
600 Lakhs
600 Lakhs
No
31-12-2026
31-12-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSERETAIL (TYPICAL FLOOR)- RCC BASE SLAB OFFICE (LOBBY)FINISHED GRND FLOOR LOBBY & RCC BASE SLAB FOR TYPICLFLOOR LOBBIES. OFFICE (UNIT FLOOR FINISH) RCC BASE SLAB
2WALL FINISHING DETAILSRAW WALL/ PARTITIONS
3KITCHEN DETAILSN.A.
4BATHROOM FITTINGSRETAIL- FINISHED COMMON TOILETS WITH MODERN FITTING &FIXTURES; OFFICE : PROVISION OF SERVICES WILL BEPROVIDED AND TO BE FINISHED BY ALLOTTEE(S).
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESALUMINIUM FRAME
7GLASS WORKGLASS THICKNESS VARIES FROM 6 TO 10 MM
8ELECTRIC FITTINGSCOMMON AREAS & TOILETS TO BE PROVIDED WITH LED LIGHTFIXTURES.
9CONDUCTING AND WIRING DETAILSISI APPROVED CONDUITS & WIRES
10CUPBOARD DETAILS N.A.
11WATER STORAGERCC TANK
12LIFT DETAILSSTANDARD MAKE ELEVATORS
13EXTERNAL GLAZINGSALUMINIUM GLAZING WITH GLASS OF 5-12 MM THICK GLASS
13.1WINDOWS/GLAZINGSALUMINIUM GLAZING WITH GLASS OF 5-12 MM THICK GLASS
14DOORSALUMINIUM / GLASS DOORS
14.1MAIN DOORSALUMINIUM / GLASS DOORS
14.2INTERNAL DOORSMS/ ALUMINIUM/ WOODEN DOORS
15AIR CONDITIONINGCHILLED WATER AC SYSTEM FOR OFFICE & PROVISION FORWATER COOLED DX SYSTEM UPTO TAP OFF INSIDE SHOP
16ELECTRICAL FITTINGSPROVISION OF CABLE UP TO DISTRIBUTION BOARD ISI /BIS APPROVED
17CNG PIPE LINEN.A.
18PROVISION OF WIFI AND BROADBAND FACILITYN.A.
19EXTERNAL FINISHING/COLOUR SCHEMEN.A.
20INTERNAL FINISHINGPAINT/GLASS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOOR VITRIFIED TILES
1 . 2 WALLS PLASTER OBD
1 . 3 CEILING OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES/LAMINATE WOODEN FLOORING
2 . 2 WALLS PLASTER & OBD
2 . 3 CEILING OBD
2 . 4 MODULAR WARDROBES N.A.
3 . MASTER TOILET
3 . 1 FLOOR ANTISKID CERAMIC TILES
3 . 2 WALLSPLASTER & DADO
3 . 3 CEILING GRID FALSE CEILING/OBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGS AS PER APPROVED MAKE
3 . 6 FITTING/FIXTURES AS PER APPROVED MAKE
4 . BED ROOMS
4 . 1 FLOOR VITRIFIED TILES/LAMINATE WOODEN FLOORING
4 . 2 WALLS PLASTER & OBD
4 . 3 CEILING OBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTISKID CERAMIC TILES
5 . 2 WALLSPLASTER & DADO
5 . 3 CEILINGGRID FALSE CEILING/OBD
5 . 4 COUNTERS N.A
5 . 5 SANITARY WARE/CP FITTINGS AS PER APPROVED MAKE
5 . 6 FIXTURES AS PER APPROVED MAKE
6 . KITCHEN
6 . 1 FLOOR VITRIFIED TILES
6 . 2 WALLS PLASTER & DADO
6 . 3 CEILING OBD
6 . 4 COUNTERS STONE/MARBLE
6 . 5 FIXTURES AS PER APPROVED MAKE
6 . 6 KITCHEN APPLIANCES N.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOOR ANTISKID VITRIFIED TILES
7 . 2 WALLS & CEILING PLASTER & PAINT
7 . 3 TOILET ANTISKID CERAMIC TILES
7 . 4 BALCONY ANTISKID CERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 22-03-2024 View Document
2 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 22-03-2024 View Document
3 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 22-03-2024 View Document
4 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 22-03-2024 View Document
5 ZONING PLAN 22-03-2024 View Document
6 DEMARCATION PLAN 22-03-2024 View Document
7 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 24-05-2024 View Document
8 WATER SUPPLY LAYOUT 24-05-2024 View Document
9 T-6B- SECTIONS BB 24-05-2024 View Document
10 T-6C- ELEVATIONS 3 & 4 24-05-2024 View Document
11 T-6B- 2ND TO 5TH LEVEL LAYOUT & AREA DETAILS 24-05-2024 View Document
12 T-6B- 20TH & 30TH FLOOR PLAN & AREA DETAILS 24-05-2024 View Document
13 T-6B- ELEVATIONS 3 & 4 24-05-2024 View Document
14 COMMERCIAL- ELEVATION PLAN 24-05-2024 View Document
15 LOWER BASEMENT AREA DIAGRAM 24-05-2024 View Document
16 T-6B- 1ST LEVEL LAYOUT & AREA DETAILS 24-05-2024 View Document
17 T-6C- TYPICAL LEVEL LAYOUT & AREA DETAILS 24-05-2024 View Document
18 TOWER-6B&C ZP 24-05-2024 View Document
19 ROAD LAYOUT 24-05-2024 View Document
20 T-6C- 1ST LEVEL LAYOUT & AREA DETAILS 24-05-2024 View Document
21 T-6C- 2ND TO 5TH LEVEL LAYOUT & AREA DETAILS 24-05-2024 View Document
22 PARKING PLAN-1 24-05-2024 View Document
23 STRUCTURAL PLAN-1 24-05-2024 View Document
24 T-6C- TERRACE, MUMTY LAYOUT & AREA DETAILS 24-05-2024 View Document
25 T-6C- ELEVATIONS 3&4 24-05-2024 View Document
26 STORM WATER DRAINAGE LAYOUT 24-05-2024 View Document
27 T-6C- 20TH & 30TH FLOOR PLAN & AREA DETAILS 24-05-2024 View Document
28 PARKING PLAN-2 24-05-2024 View Document
29 ELECTRICITY LAYOUT 24-05-2024 View Document
30 T-6B- SECTIONS AA 24-05-2024 View Document
31 T-6C- STILT LEVEL LAYOUT AND AREA DETAILS 24-05-2024 View Document
32 SECTION AA & BB 24-05-2024 View Document
33 COMMERCIAL- SECTION PLAN 24-05-2024 View Document
34 COMMERCIAL- TERRACE FLOOR PLAN 24-05-2024 View Document
35 SEWERAGE LAYOUT 24-05-2024 View Document
36 T-6C- SECTIONS AA 24-05-2024 View Document
37 STRUCTURAL PLAN-2 24-05-2024 View Document
38 T-6B- ELEVATIONS 3&4 24-05-2024 View Document
39 T-6B- STILT LEVEL LAYOUT AND AREA DETAILS 24-05-2024 View Document
40 T-6B&6C;- SITE-TOWER 6C & 6B 24-05-2024 View Document
41 UPPER BASEMENT AREA DIAGRAM 24-05-2024 View Document
42 SHAJRA 11-06-2024 View Document
43 CA CERTIFICATE INVENTORY 11-06-2024 View Document
44 STP TREATED WATER FOR CONSTRUCTION 11-06-2024 View Document
45 LOI 11-06-2024 View Document
46 MUTATIONS 11-06-2024 View Document
47 BR-III 11-06-2024 View Document
48 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 11-06-2024 View Document
49 STORM WATER DRAINAGE ASSURANCE 11-06-2024 View Document
50 JAMABANDI 11-06-2024 View Document
51 SEWERAGE ASSURANCE 11-06-2024 View Document
52 CA CERTIFICATE- NET WORTH 11-06-2024 View Document
53 AAI NOC 11-06-2024 View Document
54 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 11-06-2024 View Document
55 LC-IV & IV-A 11-06-2024 View Document
56 CA CERTIFICATE INCURRED 11-06-2024 View Document
57 DRINKING WATER ASSURANCE 11-06-2024 View Document
58 ENVIRONMENT CLEARANCE 11-06-2024 View Document
59 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 11-06-2024 View Document