HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1546-2024
Submission Date : 30-01-2024 12:14:59 PM
Applicant Type : Company
Project Type: NEW




WHITELAND CORPORATION PVT LTD
WORLDMARK GURGAON, UNIT NO 1001, 10TH FLOOR, SECTOR-65, GURGAON
01246690100
9999977704 (Number Shared by Promoter in Public)
rachit.vohra@wlcorp.com
http://www.wlcorp.com
XXXX777B
U70109HR2021PTC092905
 
 


 
 


 
 


 
 







URBAN RESORT
REVENUE ESTATE OF VILLAGE DHANWAPUR, SECTOR-103, GURUGRAM
GURGAON
GURUGRAM
9873627754
9873627754 (Number Shared by Promoter in Public)
Praveen.kumar@wlcorp.com
PRAVEEN KUMAR
9873627754
9873627754 (Number Shared by Promoter in Public)
Praveen.kumar@wlcorp.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151628022-01-20245917830ICICI BANK HRERA Gurugram
251628122-01-20241663670ICICI BANK HRERA Gurugram







9.58125 (Acre)
3.5
3.5
9.58125 (Acre)
Endst. No. LC-5229-PA(VA)-2023/42087 dated 12-12-2023
Yes







280966.81 Lakhs
28353.92 Lakhs
145025.90 Lakhs
19974.33 Lakhs
87612.66 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 1.4379
3CONSTRUCTION OF ROADS 1.9298
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 4.0011
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0.2941
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.2842
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13COMMERCIAL 0.0620
14WATER SUPPLY 0.1384
15STROM WATER 0.3954
16STREET LIGHT 0.0136
17ELECTRICAL SUPPLY SYSTEM 0.3830
18SECURITY AND FIRE FIGHTING 0.0086
19RENEWABLE ENERGY 0.3682
20STP 0.2224
21UNDER GROUND TANK 0.0272
22RAIN WATER HARVESTING 0.0154
Total9.5813




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS309.66AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM45.29AS PER PROJECT REPORT
3STORM WATER DRAINAGE98.98AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM2275.83AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL120.35AS PER PROJECT REPORT
6STREET LIGHTING36.76AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING73.08AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS860.12AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE7253.54AS PER PROJECT REPORT
10SHOPPING AREA791.87AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM79.15AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15PARKING 321.14AS PER PROJECT REPORT
16UNDERGROUND WATER TANK79.20AS PER PROJECT REPORT
17RAIN WATER HARVESTING45.00AS PER PROJECT REPORT
18STP120.00AS PER PROJECT REPORT
19ELECTRICAL SUB STATION1602.37AS PER PROJECT REPORT
20CONSTRUCTION OF CIRCULATION ROAD 600.00AS PER PROJECT REPORT
21ELECTRIFICATION COST 5262.00AS PER PROJECT REPORT


NA (date)
NA (date)
01-04-2024
31-03-2031
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings1255999487
Apartment/Shops/Other Buildings42121661





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments083.5283.5283.52
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments936.611498.581498.581123.94
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1123.943270.295085.505490.39
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6753.687169.787860.129049.73
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments8890.519396.649528.749588.90
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments8896.216389.855817.116009.39
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6442.046954.116923.615440.58
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3496.97139.51
Shops00
Plots00




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area79.1979.1979.19
Other000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area79.1979.1979.1979.19
Other0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area79.1979.1979.190
Other0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System006.799.06
Sewerage treatment & garbage disposal006.0224.07
Electricity Supply System00341.37341.37
Storm Water Drainage4.9519.8024.7524.75
Parks and Playgrounds0000
Clubhouse/community centres725.35725.35725.35725.35
Shopping area0000
Other0000
Underground Tank7.9219.80
Rain water harvesting18.0022.50
Electrical sub station80.1280.12
STP24.00
Street Lighting7.35
Security and fire fighting3.65
Renewable energy system3.96
Underground water tank27.72

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements77.4177.4177.4177.41
Water Supply System9.069.066.794.53
Sewerage treatment & garbage disposal24.0724.0724.0718.05
Electricity Supply System341.37568.96682.750
Storm Water Drainage24.75000
Parks and Playgrounds086.01172.02258.04
Clubhouse/community centres725.35725.35725.35725.35
Shopping area0000
Other0000
Renewable energy system11.8719.7919.7923.74
STP30.0030.0036.00
Electrical sub station80.12480.71881.30
Construction of circulation road150.00150.00150.00150.00
electrification1052.401052.401052.40
Street Lighting1.841.8414.7011.03
Security and firefighting18.2721.92
Security and fire fighting10.9618.27
Rain water harvesting4.50
Underground water tank23.76

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds344.050
Clubhouse/community centres725.35725.35
Shopping area00
Other00
electrification1052.401052.40












Yes
Yes
ICICI BANK LIMITED, SHOP NO 6, 7, 26, 27, 104 & 130, NIRVANA COURTYARD, NIRVANA COUNTRY, SECTOR 50,
777705770691
ICIC0001843
110229211
229211
NAVDEEP SARDANA R/o Plot no. 4545, Ist floor, Dlf phase -4, Gurugram
YES











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ZONING PLAN ALREADY BEEN OBTAINED13-12-2023
II. AIRPORT HEIGHT CLEARANCE ALREADY BEEN OBTAINED11-01-2024
III. FOREST NOC ALREADY BEEN OBTAINED20-11-2021








Yes


Yes


As per RERA Norms







THE ASPEN - DARBARIPUR ROAD, SECTOR 76
11.96
731
0
414
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
167187.64023360
Cost of the apartments9695002541
Cost of the infrastructure64253.500
Others costs5984.14020819


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2030
31-12-2030










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE, LAMINATE WOODEN FLOORING
2WALL FINISHING DETAILSPREMIUM ACRYLIC DISTEMPER
3KITCHEN DETAILSSINGLE LEVER COUNTER TOP
4BATHROOM FITTINGSCHINAWARE , SINGLE LEVER COUNTER TOP
5WOOD WORK ETCNO
6DOORS AND WINDOS FRAMESFULL HEIGHT WINDOWS- ALUMINIUM PODER COATED SECTIONS AND WOODEN FRAME WITH FLUSH DOOR WITH VENEER FINISH (ON BOTH SIDES) & ARCHITRAVES
7GLASS WORKFULL HEIGHT WINDOWS- ALUMINIUM PODER COATED SECTIONS
8ELECTRIC FITTINGSFAN AND ELECTRIC POINT
9CONDUCTING AND WIRING DETAILSHEAVY DUTY , MODULAR
10CUPBOARD DETAILSNA
11WATER STORAGEYES
12LIFT DETAILSNA
13EXTERNAL GLAZINGS12 MM TOUGHNED GLASS DOOR
13.1WINDOWS/GLAZINGSFULL HEIGHT WINDOWS- ALUMINIUM PODER COATED SECTIONS
14DOORSWOODEN FRAME WITH FLUSH DOOR WITH LAMINATE FINISH (ON BOTH SIDES) & ARCHITRAVES
14.1MAIN DOORSWOODEN FRAME WITH FLUSH DOOR WITH LAMINATE FINISH (ON BOTH SIDES) & ARCHITRAVES
14.2INTERNAL DOORSWOODEN FRAME WITH FLUSH DOOR WITH LAMINATE FINISH (ON BOTH SIDES) & ARCHITRAVES
15AIR CONDITIONINGVARIABLE RATE FLOW SYSTEM.
16ELECTRICAL FITTINGSHEAVY DUTY CONDUTING MODULAR SWITCHES, C CURVE MCB
17CNG PIPE LINEYES
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEEXTRANL GRADE TEXTURE PAINT
20INTERNAL FINISHINGPREMIUM ACRYLIC DISTEMPER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSPREMIUM ACRYLIC DISTEMPER
1 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATE WOODEN FLOORING
2 . 2 WALLSPREMIUM ACRYLIC DISTEMPER
2 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORVITRIFIED TILE
3 . 2 WALLSPREMIUM ACRYLIC DISTEMPER
3 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
3 . 4 COUNTERSSINGLE LEVER COUNTER TOP
3 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER COUNTER TOP
3 . 6 FITTING/FIXTURESSINGLE LEVER COUNTER TOP
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILE
4 . 2 WALLSPREMIUM ACRYLIC DISTEMPER
4 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORVITRIFIED TILE
5 . 2 WALLSPREMIUM ACRYLIC DISTEMPER
5 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
5 . 4 COUNTERSSINGLE LEVER COUNTER TOP
5 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER COUNTER TOP
5 . 6 FIXTURESSINGLE LEVER COUNTER TOP
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILE
6 . 2 WALLSPREMIUM ACRYLIC DISTEMPER
6 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
6 . 4 COUNTERSSINGLE LEVER COUNTER TOP
6 . 5 FIXTURESSINGLE LEVER COUNTER TOP
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILE
7 . 2 WALLS & CEILINGPREMIUM ACRYLIC DISTEMPER
7 . 3 TOILETSINGLE LEVER COUNTER TOP
7 . 4 BALCONYIRON ROD
8 . SIT-OUTS
8 . 1 FLOORVITRIFIED TILE
8 . 2 WALLS & CEILINGPREMIUM ACRYLIC DISTEMPER
8 . 3 RAILINGSIRON ROD
8 . 4 FIXTURESSINGLE LEVER COUNTER TOP












Sr. No.Document DescriptionDate of Document UploadView Document
1SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN29-01-2024 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND28-01-2024 View Document
3DEMARCATION PLAN28-01-2024 View Document
4CASH FLOW STATEMENT OF THE PROPOSED PROJECT29-01-2024 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT29-01-2024 View Document
6CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT29-01-2024 View Document
7IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN29-01-2024 View Document
8FOREST NOC 30-01-2024 View Document
9DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.29-01-2024 View Document
10NON ENCUMBRANCE CERTIFICATE 30-01-2024 View Document
11ZONING PLAN28-01-2024 View Document
12DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD30-01-2024 View Document
13IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN29-01-2024 View Document
14AAI30-01-2024 View Document
15BALANCE SHEET 30-01-2024 View Document