As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
453199
25-07-2017
1008000.00
ORIENTAL BANK OF COMMERCE NEW DELHI
HRERA Gurugram
2
118131
26-08-2019
269115.00
ORIENTAL BANK OF COMMERCE NEW DELHI
HRERA Gurugram
3
118931
19-11-2019
361736.00
ORIENTAL BANK OF COMMERCE NEW DELHI
HRERA Gurugram
4
238501
31-12-2020
33893.00
PUNJAB NATIONAL BANK NEW DELHI
HRERA Gurugram
14390.68 (Sqr/mtrs)
1.87
1.87
14390.68 (Sqr/mtrs)
48 OF 2008 DATED 14.03.2008
Yes
28180.84 Lakhs
6372.79 Lakhs
10310.49 Lakhs
545.60 Lakhs
10951.96 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
5023.26
3
CONSTRUCTION OF ROADS
3826.95
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
4390.47
7
VEHICLE PARKINGS
1150.00
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
14390.68
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP (APPLIED)
No
WATER SUPPLY
HSVP/GMDA (APPLIED)
No
ELECTRICITY
DHBVN (TEMPORARY CONNECTION OBTAINED, REGULAR CONNECTION WITH OC
No
SEWAGE DISPOSAL
HSVP/GDMA (APPLIED)
No
STORM WATER DRAINAGE
HSVP/GMDA (APPLIED)
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
86.43
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
208.60
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
38.76
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
0
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
AS PER PROJECT REPORT
6
STREET LIGHTING
13.65
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
0
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
LIFTS
0
AS PER PROJECT REPORT
16
MAINTENANCE
116.87
AS PER PROJECT REPORT
17
SEWRAGE
71.30
YET TO BE PREPARED
18
HORTICULTURE
9.99
YET TO BE PREPARED
16-09-2020 (date)
16-09-2020 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT/SHOPS OTHER BUILDING TYPE COMMERCIAL COLONY
15481.18
235
4
231
2
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
COMMERCIAL COLONY
4
70%
31-12-2016
31-12-2019
31-12-2021
31-12-2016
70
31-12-2021
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
00
31-12-2016
70
31-12-2021
470
0
0
66
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
Shops
0
0
Plots
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
Shops
0
0
Plots
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
1619.20
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.83
0
Water Supply System
28.43
0
Sewerage treatment & garbage disposal
17.10
0
Electricity Supply System
0
0
Storm Water Drainage
6.25
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Horticulture
0.24
Maintenance
38.95
Street Light
4.55
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
235
ii. No. of Flats/ Apartments booked
4
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
236.18 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
158.11 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
78.06 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
78.06 Lakhs
vii. Amount invested in the project upto the date of application
19646.82 Lakhs
Land cost (If any)
6372.79 Lakhs
Apartments
5452.90 Lakhs
Infrastructure
250.52 Lakhs
EDC/ Taxes Etc.
7345.05 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
8534.02 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
6912.88 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
20644.53 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
86.43
77.93
II. WATER SUPPLY SYSTEM
208.60
123.31
III. STORM WATER DRAINAGE
38.76
20.00
IV. ELECTRICITY SUPPLY SYSTEM
0
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
71.30
20.00
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
140.51
9.28
Yes
Yes
PNB E BLOCK CONNAUGHT PLACE NEW DELHI
-00071232000017
PUNB0000710
-110022005
00007
PRIYA RANJAN
YES. ATTACHED.
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE NO. 48 OF 2008 DATED 14.03.2008
ALREADY BEEN OBTAINED
NA
II. FOREST NOC NO. 311-G DATED 08.05.2014
ALREADY BEEN OBTAINED
08-05-2014
III. ARAVALI NOC MEMO NO. 1390/SK2 DATED 12.06.2014
ALREADY BEEN OBTAINED
12-06-2014
IV. MINING PERMISSION VIDE MEMO NO. 2088 DATED 18.11.2014
ALREADY BEEN OBTAINED
18-11-2014
V. ENVIRONMENT CLEARANCE VIDE MEMO NO. SEIAA/HR/2015/121 DATED 05.02.2015
ALREADY BEEN OBTAINED
05-02-2015
VI. CONSENT TO ESTABLISH VIDE MEMO NO. HSPCB/CONSENT/2821215GUS0CTO1886691 DATED 11.05.2015 AND RENEWAL DATED 24.06.2017
ALREADY BEEN OBTAINED
11-05-2015
VII. HEIGHT NOC FROM AAI BEARING MEMO NO. PALM/NORTH/B/200418/341525 DATED 04.10.2018
ALREADY BEEN OBTAINED
04-10-2018
VIII. NOC FOR CONSTRUCTION ACTIVITY BY HUDA VIDE MEMO NO. 307 DATED 28.04.2014
ALREADY BEEN OBTAINED
28-04-2014
IX. APPROVAL OF FIRE FIGHTING SCHEME VIDE MEMO NO. FS/2019/125 DATED 01.08.2019
ALREADY BEEN OBTAINED
01-08-2019
X. PRE CERTIFICATION REGISTRATION NO. NBT 190037 OF JULY 2019 ISSUED BY IGBC
ALREADY BEEN OBTAINED
01-07-2019
XI. BUILDING PLANS
ALREADY BEEN OBTAINED
16-09-2020
Yes
Yes
ATTACHED
NA
0
0
0
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
0
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2023
31-12-2023
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
GRANITE/VITRIFIED TILES/KOTAH STONE
2
WALL FINISHING DETAILS
GRANITE ON LIFT LOBBIES. PLASTER AND ACRYLIC PAINT
3
KITCHEN DETAILS
GRANITE COUNTER
4
BATHROOM FITTINGS
VITRIFIED TILE FLOORING/CERAMIC TILE DODO
5
WOOD WORK ETC
LAMINATED FLUSH DOORS/T.W.FRAMES
6
DOORS AND WINDOS FRAMES
GLASS/WOODEN DOORS/ALUMINIUM WINDOWS
7
GLASS WORK
GLASS SHUTTERS/GLAZING IN SHOPS
8
ELECTRIC FITTINGS
LED LIGHTS (INTERNAL & EXTERNAL)
9
CONDUCTING AND WIRING DETAILS
MS CONDUITS/FRLS WIRES
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
UG & OVERHEAD TANKS FOR FIRE/DOMESTIC USES
12
LIFT DETAILS
HIGH SPEED LIFTS
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
STRUCTURAL GLAZING WITH DGU/ALUMINIUM GLAZINGS
14
DOORS
NA
14.1
MAIN DOORS
GLASS DOORS IN COMMERCIAL AREAS
14.2
INTERNAL DOORS
WOODEN DOORS
15
AIR CONDITIONING
CENTRAL AIR CONDITIONING
16
ELECTRICAL FITTINGS
LED LIGHTS (INTERNAL & EXTERNALS)
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
YES
19
EXTERNAL FINISHING/COLOUR SCHEME
GRANITE STONE/ ACP CLADDING/TEXTURED PAINT
20
INTERNAL FINISHING
PLASTER AND PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
PRE-CERTIFICATION REGISTRATION ISSUED BY IGBC
01-02-2024
------
2
LANDSCAPE PLAN
01-02-2024
------
3
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT