HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1544-2024
Submission Date : 01-02-2024 05:26:01 PM
Applicant Type : Company
Project Type: ONGOING




KLJ REALTECH PRIVATE LIMITED
KLJ COMPLEX I, 70/B-39 SHIVAJI MARG NAJAFGARH ROAD NEW DELHI 110015
01125458767
9868353622 (Number Shared by Promoter in Public)
legal@kljdevelopers.com
https://www.kljdevelopers.com
XXXX118A
U70200DL2008PTC175282
 
 


 
 


 
 


 
 


 
 







KLJ SQUARE
KLJ REALTECH PRIVATE LIMITED VILLAGE SHIKOHPUR SECTOR 83 GURUGRAM HARYANA 122004
MANESAR
GURUGRAM
9871292777 (Number Shared by Promoter in Public)
legal@kljdevelopers.com
SANJEEV SHARMA
9871292777 (Number Shared by Promoter in Public)
sanjeevsharma@kljdevelopers.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
145319925-07-20171008000.00ORIENTAL BANK OF COMMERCE NEW DELHIHRERA Gurugram
211813126-08-2019269115.00ORIENTAL BANK OF COMMERCE NEW DELHIHRERA Gurugram
311893119-11-2019361736.00ORIENTAL BANK OF COMMERCE NEW DELHIHRERA Gurugram
423850131-12-202033893.00PUNJAB NATIONAL BANK NEW DELHIHRERA Gurugram







14390.68 (Sqr/mtrs)
1.87
1.87
14390.68 (Sqr/mtrs)
48 OF 2008 DATED 14.03.2008
Yes







28180.84 Lakhs
6372.79 Lakhs
10310.49 Lakhs
545.60 Lakhs
10951.96 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5023.26
3CONSTRUCTION OF ROADS3826.95
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS4390.47
7VEHICLE PARKINGS1150.00
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total14390.68




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP (APPLIED)No
WATER SUPPLYHSVP/GMDA (APPLIED)No
ELECTRICITYDHBVN (TEMPORARY CONNECTION OBTAINED, REGULAR CONNECTION WITH OCNo
SEWAGE DISPOSALHSVP/GDMA (APPLIED)No
STORM WATER DRAINAGEHSVP/GMDA (APPLIED)No




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS86.43AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM208.60AS PER PROJECT REPORT
3STORM WATER DRAINAGE38.76AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL0AS PER PROJECT REPORT
6STREET LIGHTING13.65AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15LIFTS0AS PER PROJECT REPORT
16MAINTENANCE 116.87AS PER PROJECT REPORT
17SEWRAGE71.30YET TO BE PREPARED
18HORTICULTURE9.99YET TO BE PREPARED


16-09-2020 (date)
16-09-2020 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT/SHOPS OTHER BUILDING TYPE COMMERCIAL COLONY15481.1823542312






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
COMMERCIAL COLONY470%


31-12-2016
31-12-2019
31-12-2021
31-12-2016
70
31-12-2021


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT000
31-12-2016
70
31-12-2021


470
0
0
66
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops5452.90
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots00

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots00

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops1619.20
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements77.93
Water Supply System123.31
Sewerage treatment & garbage disposal20.00
Electricity Supply System0
Storm Water Drainage20.00
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Horticulture9.28

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.830
Water Supply System28.430
Sewerage treatment & garbage disposal17.100
Electricity Supply System00
Storm Water Drainage6.250
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Horticulture0.24
Maintenance38.95
Street Light4.55












Particulars Remarks, if any
i. No. of Flats/Apartments constructed235
ii. No. of Flats/ Apartments booked4
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter236.18 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter158.11 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter78.06 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter78.06 Lakhs
vii. Amount invested in the project upto the date of application19646.82 Lakhs
Land cost (If any)6372.79 Lakhs
Apartments5452.90 Lakhs
Infrastructure250.52 Lakhs
EDC/ Taxes Etc.7345.05 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession8534.02 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
6912.88 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 20644.53 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS86.4377.93
II. WATER SUPPLY SYSTEM208.60123.31
III. STORM WATER DRAINAGE38.7620.00
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL71.3020.00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT140.519.28









Yes
Yes
PNB E BLOCK CONNAUGHT PLACE NEW DELHI
-00071232000017
PUNB0000710
-110022005
00007
PRIYA RANJAN
YES. ATTACHED.











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO. 48 OF 2008 DATED 14.03.2008ALREADY BEEN OBTAINEDNA
II. FOREST NOC NO. 311-G DATED 08.05.2014ALREADY BEEN OBTAINED08-05-2014
III. ARAVALI NOC MEMO NO. 1390/SK2 DATED 12.06.2014ALREADY BEEN OBTAINED12-06-2014
IV. MINING PERMISSION VIDE MEMO NO. 2088 DATED 18.11.2014ALREADY BEEN OBTAINED18-11-2014
V. ENVIRONMENT CLEARANCE VIDE MEMO NO. SEIAA/HR/2015/121 DATED 05.02.2015ALREADY BEEN OBTAINED05-02-2015
VI. CONSENT TO ESTABLISH VIDE MEMO NO. HSPCB/CONSENT/2821215GUS0CTO1886691 DATED 11.05.2015 AND RENEWAL DATED 24.06.2017ALREADY BEEN OBTAINED11-05-2015
VII. HEIGHT NOC FROM AAI BEARING MEMO NO. PALM/NORTH/B/200418/341525 DATED 04.10.2018ALREADY BEEN OBTAINED04-10-2018
VIII. NOC FOR CONSTRUCTION ACTIVITY BY HUDA VIDE MEMO NO. 307 DATED 28.04.2014ALREADY BEEN OBTAINED28-04-2014
IX. APPROVAL OF FIRE FIGHTING SCHEME VIDE MEMO NO. FS/2019/125 DATED 01.08.2019ALREADY BEEN OBTAINED01-08-2019
X. PRE CERTIFICATION REGISTRATION NO. NBT 190037 OF JULY 2019 ISSUED BY IGBCALREADY BEEN OBTAINED01-07-2019
XI. BUILDING PLANS ALREADY BEEN OBTAINED16-09-2020








Yes


Yes


ATTACHED







NA
0
0
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
000
Cost of the apartments000
Cost of the infrastructure000
Others costs000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2023
31-12-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEGRANITE/VITRIFIED TILES/KOTAH STONE
2WALL FINISHING DETAILSGRANITE ON LIFT LOBBIES. PLASTER AND ACRYLIC PAINT
3KITCHEN DETAILSGRANITE COUNTER
4BATHROOM FITTINGSVITRIFIED TILE FLOORING/CERAMIC TILE DODO
5WOOD WORK ETCLAMINATED FLUSH DOORS/T.W.FRAMES
6DOORS AND WINDOS FRAMESGLASS/WOODEN DOORS/ALUMINIUM WINDOWS
7GLASS WORKGLASS SHUTTERS/GLAZING IN SHOPS
8ELECTRIC FITTINGSLED LIGHTS (INTERNAL & EXTERNAL)
9CONDUCTING AND WIRING DETAILSMS CONDUITS/FRLS WIRES
10CUPBOARD DETAILSNA
11WATER STORAGEUG & OVERHEAD TANKS FOR FIRE/DOMESTIC USES
12LIFT DETAILSHIGH SPEED LIFTS
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSSTRUCTURAL GLAZING WITH DGU/ALUMINIUM GLAZINGS
14DOORSNA
14.1MAIN DOORSGLASS DOORS IN COMMERCIAL AREAS
14.2INTERNAL DOORSWOODEN DOORS
15AIR CONDITIONINGCENTRAL AIR CONDITIONING
16ELECTRICAL FITTINGSLED LIGHTS (INTERNAL & EXTERNALS)
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMEGRANITE STONE/ ACP CLADDING/TEXTURED PAINT
20INTERNAL FINISHINGPLASTER AND PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1PRE-CERTIFICATION REGISTRATION ISSUED BY IGBC01-02-2024 ------
2LANDSCAPE PLAN 01-02-2024 ------
3CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT27-01-2024 View Document
4DEMARCATION PLAN27-01-2024 View Document
5RECEIPT DHBVN01-02-2024 ------
6FINAL SUPERIMPOSE WITH KHASRA NO. KLJ SQUARE01-02-2024 ------
7ZONING PLAN27-01-2024 View Document
8IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN27-01-2024 View Document
9A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS27-01-2024 View Document
10COPY OF LICENSE ALONG WITH SCHEDULE OF LAND27-01-2024 View Document
11SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN27-01-2024 View Document
12ENVIRONMENT CLEARANCE01-02-2024 ------
13HEIGHT NOC FROM AAI01-02-2024 ------
14ELEVATION-EL101-02-2024 ------
15PARKING 101-02-2024 ------
16SECTION B & C01-02-2024 ------
17SITE PLAN SERVICES01-02-2024 ------
181ST AND 2ND FLOOR PLAN01-02-2024 ------
19DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.01-02-2024 View Document
20STREET LIGHT PLAN 01-02-2024 ------
21SECTION A01-02-2024 ------
226TH AND 10TH FLOOR PLAN01-02-2024 ------
23CASH FLOW STATEMENT OF THE PROPOSED PROJECT27-01-2024 View Document
24IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN27-01-2024 View Document
25ELEVATION-EL2 & EL401-02-2024 ------
26PARKING 301-02-2024 ------
27CONSENT TO ESTABLISH01-02-2024 ------
28ELEVATION-EL301-02-2024 ------
293RD AND 4TH FLOOR PLAN01-02-2024 ------
305TH FLOOR PLAN01-02-2024 ------
31GROUND FLOOR PLAN01-02-2024 ------
32PARKING 201-02-2024 ------
33SECTION AUDITORIUM01-02-2024 ------
34APPLICATION FOR SEWAGE CONNECTION01-02-2024 ------
35APPLICATION FOR WATER CONNECTION GMDA01-02-2024 ------
36APPLICATION FOR STORM WATER DRAINAGE GMDA01-02-2024 ------
37NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT01-02-2024 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 EXTENSION NO. HARERA/GGM/REP/RC/234/ 2O17/EXT/196/2019 DATED-06.01.2020 30-05-2020 View Document
2 PROJECT CONTINUATION- RC/REP/HARERA/GGM/234 OF 2017/7(3)/2022/10 DATED 18.10.2022 12-12-2023 View Document