9811078811 (Number Shared by Promoter in Public)
accounts@mksventures.in
http://mksventures.in
XXXX105L
U45400DL2007PTC167037
MKS COUNTRY-PHASE I
SECTOR-2, SOHNA, GURUGRAM
SOHNA
GURUGRAM
01127010114
9599998111 (Number Shared by Promoter in Public)
accounts@mksventures.in
RAHUL YADAV
01127010114
9891230031 (Number Shared by Promoter in Public)
info@mksventures.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
985279
11-06-2018
350000
RBL, NOIDA SEC-63
HRERA Gurugram
2
74488
22-10-2018
400000
RBL, PITAMPURA
HRERA Gurugram
3
230896
01-02-2019
414711
CBI
HRERA Gurugram
4.66 (Acre)
1.75
1.75
12.125 (Acre)
162 of 2014(12.09.2014)
Yes
21803 Lakhs
3500 Lakhs
9726 Lakhs
1698 Lakhs
6879 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
4105.507
3
CONSTRUCTION OF ROADS
4515.4296
4
PAVEMENTS
843
5
PARKS AND PLAYGROUNDS
6026.0534
6
GREEN BELTS
0
7
VEHICLE PARKINGS
1986.255
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
256
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
MAINTENANCE
200
14
SCHOOLS
0
15
PLAYGROUND
909
Total
18841.245
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
NA
No
WATER SUPPLY
HUDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
NA
No
STORM WATER DRAINAGE
NA
No
FOREST
FOREST DEPATMENT GOVT. OF HARYANA
Yes
HEIGHT
AIRPORTS AUTHORITY OF INDIA
Yes
ENVIRONMENT
SEIAA
Yes
ARAVALI
GURUGRAM AUTHORITY
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
44
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
43
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
26
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
374.4
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
34
AS PER PROJECT REPORT
6
STREET LIGHTING
29
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
304
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
49
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
114
AS PER PROJECT REPORT
10
SHOPPING AREA
44
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
224
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
FOR ELECTRIC CONNECTION TO HSEB
90
AS PER PROJECT REPORT
16
BOUNDARY WALL
15
AS PER PROJECT REPORT
17
DEVLOPMENT OF ROAD INCLUDING DRAIN AND STREET LIGHT OUT SIDE BOUNDARY OF PROJECT
40
AS PER PROJECT REPORT
18
BASEMENT DRAINAGE
20
AS PER PROJECT REPORT
19
FOR WATER SUPPLY AND SEWAGE CONNECTION
90
SUBMITTED TO HUDA
20
MECHANICAL VENTILATION
158
AS PER PROJECT REPORT
26-10-2015 (date)
26-10-2015 (date)
20-06-2018
30-09-2024
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
57.132
68
4
Apartment/Shops/Other Buildings
53.966
2
4
Apartment/Shops/Other Buildings
65.05
2
4
Apartment/Shops/Other Buildings
7.29
2
6
Apartment/Shops/Other Buildings
15.95
2
6
Apartment/Shops/Other Buildings
20.9
7
6
Apartment/Shops/Other Buildings
111.105
34
1
Apartment/Shops/Other Buildings
118.028
2
1
Apartment/Shops/Other Buildings
87.63
2
1
Apartment/Shops/Other Buildings
99.964
32
1
Apartment/Shops/Other Buildings
81.75
93
2
Apartment/Shops/Other Buildings
93.126
2
2
Apartment/Shops/Other Buildings
88.5
2
2
Apartment/Shops/Other Buildings
75.09
4
2
Apartment/Shops/Other Buildings
75.169
2
2
Apartment/Shops/Other Buildings
75.666
2
3
Apartment/Shops/Other Buildings
99.94
34
3
Apartment/Shops/Other Buildings
105.143
2
3
Apartment/Shops/Other Buildings
80.005
34
3
Apartment/Shops/Other Buildings
66.764
36
4
Apartment/Shops/Other Buildings
16.1
123
5
Apartment/Shops/Other Buildings
16.06
7
5
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
74
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
386
386
Shops
1.4
0
7
7
Plots
0
0
0
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
420
420
420
420
Shops
7
7
8
8
Plots
0
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
420
420
420
420
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
420
420
420
420
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
420
386
420
420
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
420
420
420
420
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
420
420
420
0
Shops
0
0
0
0
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
7
7
Other
0
0
0
0
Electrification
0
0
0
security and fire fighting
0
0
0
Community Fcility
0
0
0
School
0
0
0
Mechanical Ventilation
0
0
0
Basement drainage
0
0
0
Development of Road including drain and street light outside Boundary of Project
0
0
0
Water supply and Sewrage Connection
0
0
0
Boundary Wall
0
0
0
Street lighting
0
0
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.8
1.8
1.8
1.8
Water Supply System
1.7
1.7
1.7
1.7
Sewerage treatment & garbage disposal
1.4
1.4
1.4
1.4
Electricity Supply System
4
4
4
4
Storm Water Drainage
1
1
1
1
Parks and Playgrounds
2.13
2.13
2.13
2.13
Clubhouse/community centres
4.1
4.1
4.10
4.1
Shopping area
1.9
1.9
1.9
1.9
Other
0
0
0
0
Development of Road including drain and street light outside Boundary of Project
1.7
1.7
1.7
1.7
Boundary Wall
0.7
0.7
0.7
0.7
Water supply and Sewrage Connection
4
4
4
4
Basement drainage
0.9
0.9
0.9
0.9
Mechanical Ventilation
6.9
6.9
6.9
6.9
School
9.7
9.7
9.7
9.7
Community Fcility
0.9
0.9
0.9
0.9
security and fire fighting
13.2
13.2
13.2
13.2
Street lighting
0
0
0
0
Electrification
16
16
16
16
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.8
1.8
2.6
1.8
Water Supply System
1.7
1.7
2.5
1.7
Sewerage treatment & garbage disposal
1.4
1.4
0
1.4
Electricity Supply System
4
4
22
4
Storm Water Drainage
1
1
1.7
1
Parks and Playgrounds
2.13
2.13
2.6
2.13
Clubhouse/community centres
4.1
4.1
0
4.1
Shopping area
1.9
1.9
0
1.9
Other
0
0
0
0
Street lighting
0
0
0
Basement drainage
0.9
0.9
0.9
Boundary Wall
0.7
0.7
0.7
Development of Road including drain and street light outside Boundary of Project
1.7
1.7
1.7
Water supply and Sewrage Connection
4
4
4
Mechanical Ventilation
6.9
6.9
8.3
6.9
School
9.7
9.7
9.7
Community Fcility
0.9
0.9
0.9
security and fire fighting
13.2
13.2
13.2
Electrification
16
16
16
Basement Drainage
1.1
Security and Fire Fighting
14.5
Boundary wall
0.72
community centres
1.1
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.8
1.8
1.8
1.8
Water Supply System
1.7
1.7
1.7
1.7
Sewerage treatment & garbage disposal
1.4
1.4
1.4
1.4
Electricity Supply System
4
4
4
4
Storm Water Drainage
1
1
1
1
Parks and Playgrounds
2.13
2.13
2.13
21.3
Clubhouse/community centres
4.1
4.1
4.1
4.1
Shopping area
1.9
1.9
1.9
1.9
Other
0
0
0
0
Community Fcility
0.9
0.9
0.9
0.9
Basement drainage
0.9
0.9
0.9
0.9
School
9.7
9.7
9.7
9.7
Mechanical Ventilation
6.9
6.9
6.9
6.9
Street lighting
0
0
0
0
security and fire fighting
13.2
13.2
13.2
13.2
Electrification
16
16
16
16
Boundary Wall
0.7
0.7
0.7
0.7
Development of Road including drain and street light outside Boundary of Project
1.7
1.7
1.7
1.7
Water supply and Sewrage Connection
4
4
4
4
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.6
1.8
1.8
1.8
Water Supply System
2.5
1.7
1.7
1.7
Sewerage treatment & garbage disposal
2.3
1.4
1.4
1.4
Electricity Supply System
22
4
4
4
Storm Water Drainage
1.5
1
1
1
Parks and Playgrounds
2.6
2.13
2.13
2.13
Clubhouse/community centres
6.3
4.1
4.1
4.1
Shopping area
0
1.9
1.9
1.9
Other
0
0
0
0
School
9.7
9.7
9.7
Mechanical Ventilation
8.3
6.9
6.9
6.9
Basement drainage
0.9
0.9
0.9
Boundary Wall
0.7
0.7
0.7
Development of Road including drain and street light outside Boundary of Project
1.7
1.7
1.7
Water supply and Sewrage Connection
4
4
4
Community Fcility
0.9
0.9
security and fire fighting
13.2
13.2
13.2
Street lighting
0
0
0
Electrification
16
16
16
Community Facility
0.9
community centres
1.1
Street Lightening
2.4
Security and Fire Fighting
14.5
Basement Drainage
1.2
Boundary wall
0.71
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.8
1.8
1.8
1.8
Water Supply System
1.7
1.7
1.7
1.7
Sewerage treatment & garbage disposal
1.4
1.4
1.4
1.4
Electricity Supply System
4
4
4
4
Storm Water Drainage
1
1
1
1
Parks and Playgrounds
2.13
2.13
2.13
2.13
Clubhouse/community centres
4.1
4.1
4.1
4.1
Shopping area
1.9
1.9
1.9
1.9
Other
0
0
0
0
Basement drainage
0.9
0.9
0.9
0.9
Water supply and Sewrage Connection
4
4
4
4
Development of Road including drain and street light outside Boundary of Project
1.7
1.7
1.7
1.7
Boundary Wall
0.7
0.7
0.7
0.7
Electrification
16
16
16
16
Street lighting
0
0
0
0
Security and fire fighting
13.2
13.2
13.2
Community Facility
0.9
0.9
0.9
0.9
School
9.7
9.7
9.7
9.7
Mechanical Ventilation
6.9
6.9
6.9
6.9
security and fire fighting
13.2
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.8
1.8
1.8
Water Supply System
1.7
1.7
1.7
Sewerage treatment & garbage disposal
1.4
1.4
1.4
Electricity Supply System
4
4
4
Storm Water Drainage
1
1
1
Parks and Playgrounds
2.13
2.13
2.13
Clubhouse/community centres
4.1
4.1
4.1
Shopping area
1.9
1.9
1.9
Other
0
0
0
Mechanical Ventilation
6.9
6.9
6.9
Boundary Wall
0.7
0.7
0.7
Development of Road including drain and street light outside Boundary of Project
1.7
1.7
1.7
Water supply and Sewrage Connection
4
4
4
Street lighting
0
0.145
0.145
Electrification
16
16
16
Security and fire fighting
13.2
13.2
13.2
Community Facility
0.9
0.9
0.9
School
9.7
9.7
9.7
Basement drainage
0.9
0.9
0.9
Yes
No
BANK- UNION BANK OF INDIA, BRANCH- MID CORPORATE BRANCH DELHI
497801010000220
UBIN0549797
110026046
0549797
Jai Kishore Totlani and Manoj Kumar
YES
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
12-09-2014
II. APPROVED BUILDING PLAN
ALREADY BEEN OBTAINED
26-10-2015
III. FOREST
ALREADY BEEN OBTAINED
17-12-2015
IV. AIRPORT AUTHORITY
ALREADY BEEN OBTAINED
18-12-2015
V. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
20-05-2016
VI. ELECTRICITY SUPPLY PLAN
APPLIED FOR BUT YET TO RECEIVE
02-01-2019
VII. WATER SUPPLY PLAN
APPLIED FOR BUT YET TO RECEIVE
02-01-2019
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILES IN DRAWING, DINNING AND KITCHEN, LAMINATED WOODEN FLOORING IN BEDROOM, GRANITE STONE IN BATHROOM, ANTI SKID TILES IN BALCONY.
2
WALL FINISHING DETAILS
OBD PAINT
3
KITCHEN DETAILS
GRANITE COUNTER WITH SS SINK & MODULAR CABINETS
4
BATHROOM FITTINGS
WALL MOUNTED W/C OF REPUTED BRAND WITH CORROSION FREE UPVC/PPR/CPVC PIPES & FITTINGS.
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
INTERNAL DOOR - HARD WOOD
EXTERNAL- UPVC SLIDING DOOR & WINDOW FRAME
7
GLASS WORK
5 MM CLEAR GLASS
8
ELECTRIC FITTINGS
MODULAR SWITCHES & SOCKETS
9
CONDUCTING AND WIRING DETAILS
FIRE RESISTANCE COPPER WIRING IN CONCEALED PVC CONDUITS.
10
CUPBOARD DETAILS
N.A.
11
WATER STORAGE
RCC UNDERGROUND & OVERHEAD TANK AT TERRACE LEVEL.
12
LIFT DETAILS
OTIS / KONE/THYSSENKRUPP & EQUIVALENT ELEVATOR
13
EXTERNAL GLAZINGS
WINDOWS/GLAZINGS
13.1
WINDOWS/GLAZINGS
5 MM GLASS
14
DOORS
FLUSH DOOR
14.1
MAIN DOORS
FLUSH DOOR IN POLISH/DUCO PAINT FIXED IN HARD WOOD
14.2
INTERNAL DOORS
FLUSH DOOR IN POLISH/DUCO PAINT FIXED IN HARD WOOD
15
AIR CONDITIONING
SPLIT AIR CONDITIONER IN ALL BEDROOM
16
ELECTRICAL FITTINGS
MODULAR SWITCHES & SOCKETS.
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
PROVISION KEPT
19
EXTERNAL FINISHING/COLOUR SCHEME
HIGH QUALITY TEXTURE PAINT
20
INTERNAL FINISHING
OBD PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
VITRIFIED TILES
1 . 2
WALLS
OBD PAINT
1 . 3
CEILING
OBD PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
LAMINATED WOODEN FLOORING
2 . 2
WALLS
OBD PAINT
2 . 3
CEILING
OBD PAINT
2 . 4
MODULAR WARDROBES
NOT PROVIDED
3 . MASTER TOILET
3 . 1
FLOOR
GRANITE STONE
3 . 2
WALLS
WALL TILE/ STONE UPTO LINTEL LEVEL
3 . 3
CEILING
GRID FALSE CEILING
3 . 4
COUNTERS
GRANITE STONE
3 . 5
SANITARY WARE/CP FITTINGS
WALL MOUNTED W/C OF REPUTED BRAND WITH CORROSION FREE UPVC/PPR/CPVC PIPES & FITTINGS
3 . 6
FITTING/FIXTURES
ALL TAPS & FIXTURES OF REPUTED BRANDS IN C.P.
4 . BED ROOMS
4 . 1
FLOOR
LAMINATED WOODEN FLOORING
4 . 2
WALLS
OBD PAINT
4 . 3
CEILING
OBD PAINT
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
GRANITE STONE
5 . 2
WALLS
WALL TILE/ STONE UPTO LINTEL LEVEL
5 . 3
CEILING
GRID FALSE CEILING
5 . 4
COUNTERS
GRANITE STONE
5 . 5
SANITARY WARE/CP FITTINGS
WALL MOUNTED W/C OF REPUTED BRAND WITH CORROSION FREE UPVC/PPR/CPVC PIPES & FITTINGS.
5 . 6
FIXTURES
ALL TAPS & FIXTURES OF REPUTED BRANDS IN C.P.
6 . KITCHEN
6 . 1
FLOOR
VITRIFIED TILES
6 . 2
WALLS
CERAMIC TILE UPTO 2 FT ABOVE WORKING COUNTER.
6 . 3
CEILING
OBD PAINT
6 . 4
COUNTERS
GRANITE COUNTER WITH STAINLESS STEEL SINK
6 . 5
FIXTURES
C.P. SINK MIXTURE
6 . 6
KITCHEN APPLIANCES
MODULAR CABINETS
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
CERAMIC TILES
7 . 2
WALLS & CEILING
OBD PAINT
7 . 3
TOILET
FLOOR MOUNTED WC SHEET
7 . 4
BALCONY
ANTISKID TILES
8 . SIT-OUTS
8 . 1
FLOOR
ANTISKID TILES
8 . 2
WALLS & CEILING
OBD PAINT
8 . 3
RAILINGS
GLASS WITH MS
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT