HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-347-2018
Submission Date : 03-11-2018 11:30:01 AM
Applicant Type : Company
Project Type: NEW




TRUE VILLAS DEVELOPERS PRIVATE LIMITED
J-221, SARITA VIHAR, NEW DELHI-110076
01141078899
9810773333 (Number Shared by Promoter in Public)
truevillas@gmail.com
XXXX394D
U45201DL2004PTC130654
 
 


 
 


 
 


 
 


 
 







FORTEASIA-THE GRAND
VILLAGE- KHERKA MUSALMAN, SECTOR-35, BAHADURGARH
BAHADURGARH
JHAJJAR
7011892742 (Number Shared by Promoter in Public)
truevillas@gmail.com
UMESH
7011892742 (Number Shared by Promoter in Public)
truevillas@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
13893530-10-2018280000AXIS BANKHRERA Panchkula







14.15 (Acre)
Upto 65% of Net Planned Area
50.537
14.15 (Acre)
11 of 2018 , Transfer of license vide Memo No. LC-3275-JE(MK)-2018/30805 dated 31.10.2018
No
Address     J-221, SARITA VIHAR, NEW DELHI-110076
Annexure-B- BY VIRTUE OF COLLABORATION AGREEMENT & POWER OF ATTORNEY (COPIES ATTACHED IN FOLDER B)
YES, AFTER LICENSE PERMISSION OF CHANGE IN DEVELOPERS NAME (COPIES ATTACHED IN FOLDER B)
Yes
SUMMARY OF IMPORTANT CLAUSES (COPY ATTACHED)
No
No
Yes







2021 Lakhs
642 Lakhs
450 Lakhs
829 Lakhs
0 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD4.59
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2.05
3CONSTRUCTION OF ROADS4.14
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1.406
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1.415
12ANY OTHER0
13COMMERCIAL0.469
14ROAD WIDENING0.082
15TOTAL14.16875
Total28.32075




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSEXISTING VILLAGE ROADNo
WATER SUPPLYCGWANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS227YET TO BE PREPARED
2WATER SUPPLY SYSTEM218YET TO BE PREPARED
3STORM WATER DRAINAGE131YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM10YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL113.60YET TO BE PREPARED
6STREET LIGHTING4.50YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS6.87YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15MAINTENANCE118.36YET TO BE PREPARED
16TOTAL829.33YET TO BE PREPARED


21-12-2017 (date)
NA (date)
01-12-2018
05-02-2023
Plot Area(In Square Meter)Number of plots in the project
149.4016
133.6047
11750
105.1258
84.5060
61.1320


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings79.527826
Apartment/Shops/Other Buildings50.161818





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops100
Plots0
Villas450




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements280
Water Supply System270
Sewerage treatment & garbage disposal140.20
Electricity Supply System12.35
Storm Water Drainage161.65
Parks and Playgrounds8.50
Clubhouse/community centres0
Shopping area0
Other0
Street Lighting5.50












Yes
No
AXIS BANK, MALVIYA NAGAR, NEW DELHI
918020051949770
UTIB0000206
110211024
000206
SANDEEP MANGLA/ KAPIL GOYAL/ MANOJ GOYAL
CA CERTIFICATE ATTACHED











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED06-02-2018
II. TRANSFER OF LICENSE ORDERALREADY BEEN OBTAINED31-10-2018
III. LAYOUT PLANALREADY BEEN OBTAINED06-02-2018








Yes


Yes


ATTACHED







FORTEASIA MART SECTOR-26 & 28 ROHTAK
1.098
0
45
0
21
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
60030
Cost of the apartments000
Cost of the infrastructure60030
Others costs000


183 Lakhs
90 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2019
31-12-2019




FORTEASIA RESIDENCY SECTOR 28 & 28A BAHADURGARH
14.0625
57
283
57
253
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
001300
Cost of the apartments00450
Cost of the infrastructure00850
Others costs00650


3000 Lakhs
1700 Lakhs
0 Lakhs
0 Lakhs
No
07-02-2018
07-02-2018




FORTEASIA SILICON VALLEY SECTOR-22D ROHTAK
11.475
80
273
0
81
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
002021
Cost of the apartments00450
Cost of the infrastructure00829
Others costs00642


156 Lakhs
792 Lakhs
0 Lakhs
0 Lakhs
No
05-02-2023
05-02-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.01-11-2018 ------
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT01-11-2018 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN01-11-2018 View Document
4SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN01-11-2018 View Document
5BILATERAL AGREEMENT01-11-2018 ------
6LC-IV01-11-2018 ------
7POWER OF ATTORNEY01-11-2018 ------
8GIST OF COLLABORATION AGREEMENT01-11-2018 ------
9SUMMARY OF COLLABORATION AGREEMENT01-11-2018 ------
10DRAFT ALLOTMENT LETTER01-11-2018 ------
11PANCARD OF COMPANY01-11-2018 ------
12TRANSFER ORDER02-11-2018 ------
13DD02-11-2018 ------
14COPY OF LICENSE ALONG WITH SCHEDULE OF LAND02-11-2018 View Document
15JAMABANDI02-11-2018 ------
16JAMABANDI02-11-2018 ------
17DIRECTORS02-11-2018 ------
18DEMARCATION PLAN03-11-2018 View Document
19ZONING PLAN03-11-2018 View Document
20IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN03-11-2018 View Document
21A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS03-11-2018 View Document
22CASH FLOW STATEMENT OF THE PROPOSED PROJECT03-11-2018 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 CORRIGENDUM ISSUED 09-04-2021 View Document
2 Completion Certificate Uploaded. 20-08-2024 View Document