HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1374-2023
Submission Date : 20-11-2023 10:18:17 PM
Applicant Type : Company
Project Type: NEW




PARCELA REAL ESTATE PVT LTD
13, AJMER ROAD, BALUGANJ AGRA
9997736373 (Number Shared by Promoter in Public)
parcelarealestate@gmail.com
XXXX063B
U70109UP2022PTC158313
 
 


 
 


 
 


 
 







KINGS COURT
SECTOR 89 FARIDABAD
FARIDABAD
FARIDABAD
7983095950 (Number Shared by Promoter in Public)
parcelarealestate@gmail.com
AMIT KUMAR SHARMA
9997736373 (Number Shared by Promoter in Public)
parcelarealestate@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
16550317-11-2023897800J&K BANKHRERA Panchkula







7.2431 (Acre)
1.75
1.75
48.038 (Acre)
LICENCE NO 34 35 36 OF 2007
No
Address     R 13 2ND FLOOR GREATER KAILASH PART 1 NEW DELHI 110048
Annexure-B- ANNEXURE B ATTACHED AGREEMENT AND POWER OF ATTORNEY
AGREEMENT AND POWER OF ATTORNEY
Yes
AN AGREEMENT EXECUTED BETWEEN PARCELA & MAXIMAL (LICENCEE). 1. PARCELA ACQUIRED RIGHT, TITLE & INTEREST IN THE CONSTRUCTION AND SALE OF THE PART OF GROUP HOUSING. 2. PARCELA SHALL DEVELOP AND CONSTRUCT AT ITS OWN COST AS PER THE SANCTIONED PLAN. 3. MAXIMAL EXECUTED IRREVOCABLE REGISTERED POA IN FAVOUR OF PARCELA.
No
Yes
Yes







18022 Lakhs
3672 Lakhs
14350 Lakhs
0 Lakhs
0 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 74062.922
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total74062.922




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS185AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM168AS PER PROJECT REPORT
3STORM WATER DRAINAGE39AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM173AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL83AS PER PROJECT REPORT
6STREET LIGHTING16AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING325AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS7AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE135AS PER PROJECT REPORT
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


23-01-2007 (date)
29-02-2008 (date)
01-01-2024
31-12-2027
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings074011





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-0
Jan-MarApr-JuneJuly-SepOct-Dec

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments287287287287
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments718718718718
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1005100511481435
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1435143514351435
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-0
Jan-MarApr-JuneJuly-SepOct-Dec

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.851.851.851.85
Water Supply System1.681.681.681.68
Sewerage treatment & garbage disposal0.830.830.830.83
Electricity Supply System1.731.731.731.73
Storm Water Drainage0.390.390.390.39
Parks and Playgrounds0.070.070.070.07
Clubhouse/community centres1.351.351.351.35
Shopping area0000
Other0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.555.555.555.55
Water Supply System5.045.045.045.04
Sewerage treatment & garbage disposal2.492.492.492.49
Electricity Supply System5.195.195.195.19
Storm Water Drainage1.171.171.171.17
Parks and Playgrounds0.210.210.210.21
Clubhouse/community centres4.054.054.054.05
Shopping area0000
Other0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements14.8014.8014.8014.80
Water Supply System13.4413.4413.4413.44
Sewerage treatment & garbage disposal6.646.646.646.64
Electricity Supply System13.8413.8413.8413.84
Storm Water Drainage3.123.123.123.12
Parks and Playgrounds0.560.560.560.56
Clubhouse/community centres10.800.5610.8010.80
Shopping area010.8000
Other0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.5018.5022.2037
Water Supply System16.8016.8020.1633.6
Sewerage treatment & garbage disposal8.308.309.9616.60
Electricity Supply System17.3017.3020.7634.60
Storm Water Drainage3.903.904.687.80
Parks and Playgrounds0.700.700.841.40
Clubhouse/community centres13.5013.5016.2027.00
Shopping area0000
Other0000












Yes
Yes
J&K BANK C 10 GREATER KAILASH 1 NEW DELHI
0459010100001005
JAKA0GKLASH
110051023
023
ASHOK KUMAR SHARMA S/O SHRI RAMESH CHAND SHARMA R/O 6D/529 AWAS VIKAS COLONY SIKANDRA AGRA UP. M.NO 9873574187
YES











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO. 34-36 OF 2007ALREADY BEEN OBTAINED23-01-2007








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TIELS
2WALL FINISHING DETAILSPAINTED IN PLEASANT SHADES OF DESIGN PRINTS OF OIL BONDS
3KITCHEN DETAILSCERAMIC TILES ABOVE WORKING PLATFORM
4BATHROOM FITTINGSCERAMIC TILES WHITE SANITARY FIXTURE CP FITTING & PROVISION FOR GEYSERS
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESANODIZED ALUMINUM GLAXING
7GLASS WORKYES
8ELECTRIC FITTINGSISI MARK
9CONDUCTING AND WIRING DETAILSCONDUCT COPPER ELECTRICAL WIRING
10CUPBOARD DETAILSALREADY PROVISION FOR CUPBOARD
11WATER STORAGEOVER HEAD WATER TANKS OF SUFFICIENT CAPACITY
12LIFT DETAILSKNOWN LIFTS INSTALLTED
13EXTERNAL GLAZINGSALUMINUM FRAME GLASS IN STAIRCASE
13.1WINDOWS/GLAZINGSALUMINUM GLAZING
14DOORSWOODEN DOORS
14.1MAIN DOORSSKIN DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGWINDOW AC PROVIDED ON GROUND FLOOR ONLY
16ELECTRICAL FITTINGSISI MARKED FITING
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMESLEEK MODERN ELEVATION WITH COMBINATION
20INTERNAL FINISHINGWALL AND CEILING VTRIFIED TILES
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRFIED TILES
1 . 2 WALLSPAINT
1 . 3 CEILINGPAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN FLOORING
2 . 2 WALLSPAINT
2 . 3 CEILINGPAINT
2 . 4 MODULAR WARDROBESPROVISION FOR WADROBES
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES
3 . 2 WALLSPAINT
3 . 3 CEILINGPAINT
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSEWC WASHBASIN CP FITTINGS
3 . 6 FITTING/FIXTURESEWC WASHBASIN CP FITTINGS
4 . BED ROOMS
4 . 1 FLOORVITRFIED TILES
4 . 2 WALLSPAINT
4 . 3 CEILINGPAINT
4 . 4 WARDROBESPROVISION FOR WARDROBES
5 . TOILET
5 . 1 FLOORCERAMIC TILES
5 . 2 WALLSPAINT
5 . 3 CEILINGPAINT
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSEWC WASHBASIN CP FITTING
5 . 6 FIXTURESEWC WASHBASIN CP FITTING
6 . KITCHEN
6 . 1 FLOORCERAMIC TILES
6 . 2 WALLSPAINT
6 . 3 CEILINGPAINT
6 . 4 COUNTERSGRANITE COUNTER
6 . 5 FIXTURESSINK & SINK MIXTURE
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORVITRIFIED TILES
8 . 2 WALLS & CEILINGPAINT
8 . 3 RAILINGSCERAMIC TILES
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 DEMARCATION PLAN 20-11-2023 View Document
2 ZONING PLAN 20-11-2023 View Document
3 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 20-11-2023 View Document
4 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 17-11-2023 View Document
5 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 20-11-2023 View Document
6 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 20-11-2023 View Document
7 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 20-11-2023 View Document
8 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 20-11-2023 View Document
9 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 20-11-2023 View Document
10 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 20-11-2023 View Document
11 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 20-11-2023 View Document
12 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 20-11-2023 View Document