HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1480-2023
Submission Date : 20-11-2023 02:30:37 PM
Applicant Type : Company
Project Type: NEW




GODREJ PROPERTIES LTD
3RD FLOOR, UM HOUSE, TOWER A, PLOT NO.35, SECTOR 44, GURUGRAM, HARYANA 122002
012449561500
9871163934 (Number Shared by Promoter in Public)
rishabh.goel@godrejproperties.com
https://www.godrejproperties.com
XXXX995M
L74120MH1985PLC035308
 
 


 
 


 
 


 
 


 
 







GODREJ ARISTOCRAT
SECTOR 49, GURUGRAM, HARYANA
GURGAON
GURUGRAM
7838091820
7838091820 (Number Shared by Promoter in Public)
aman.upadhyay@godrejproperties.com
MR AMAN UPADHYAY
7838091820
7838091820 (Number Shared by Promoter in Public)
aman.upadhyay@godrejproperties.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1144030-10-20234757000AXIS BANKHRERA Gurugram
2157830-11-2023113500AXIS BANKHRERA Gurugram







9.56875 (Acre)
3.542
3.542
9.56875 (Acre)
147 of 2023 dated 18.07.2023
Yes







168514 Lakhs
34942.99 Lakhs
88002.04 Lakhs
20085.40 Lakhs
25484.00 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 5740.47
3CONSTRUCTION OF ROADS 7734.26
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 4531.03
6GREEN BELTS 1280
7VEHICLE PARKINGS 2668
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 1652.508
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 12384.39
13LAND 2732.65
Total38723.308




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS338.78AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM956.98AS PER PROJECT REPORT
3STORM WATER DRAINAGE129.80AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM4705.84AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL70.80AS PER PROJECT REPORT
6STREET LIGHTING94.40AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING2128.72AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE3058.73AS PER PROJECT REPORT
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL447.23AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER8142.00AS PER PROJECT REPORT
15ELECTRICAL SUB STATION354.00AS PER PROJECT REPORT
16SOFTSCAPE135.51AS PER PROJECT REPORT
17HARDSCAPE1016.33AS PER PROJECT REPORT
18SIGNAGES159.63AS PER PROJECT REPORT
19LANDSCAPE 1180.00AS PER PROJECT REPORT


NA (date)
09-11-2023 (date)
15-01-2024
31-12-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings89.89602
Apartment/Shops/Other Buildings93.064602
Apartment/Shops/Other Buildings101.3531624
Apartment/Shops/Other Buildings103.043104
Apartment/Shops/Other Buildings103.149542
Apartment/Shops/Other Buildings103.14962
Apartment/Shops/Other Buildings130.8361822
Apartment/Shops/Other Buildings136.4281204
Apartment/Shops/Other Buildings160.83362
Apartment/Shops/Other Buildings162.716262
Apartment/Shops/Other Buildings83.07884
Apartment/Shops/Other Buildings107.34142
Apartment/Shops/Other Buildings17.51291
Apartment/Shops/Other Buildings18.2761
Apartment/Shops/Other Buildings18.8411
Apartment/Shops/Other Buildings21.7811





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments3269.0
Shops0
Plots34943.0
EDC513.0
IDC722.0
Other Cost369.0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments847.32541.992541.991694.66
Shops0000
Plots0000
Other193.0193.01193.01386.02
EDC510509.99

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2542.02541.992542.02541.99
Shops0000
Plots0000
Other193.0772.04386.0772.04
EDC510.0510.0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3389.33389.322542.02541.99
Shops0000
Plots0000
Other386.0772.04386.0193.01
EDC510.0510.0

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4236.74236.654236.74236.65
Shops0000
Plots0000
Other386.0965.051930.11930.10
EDC510.0510.0

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4236.74236.74236.654236.65
Shops0000
Plots0000
Other772.01158.1772.041158.06
EDC510.0

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3389.323389.323389.322541.99
Shops0000
Plots0000
Other772.04579.031158.06772.04

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4236.994236.9900
Shops0000
Plots0000
Other1544.09579.0300




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other00162.84162.84
EDC00020.18
Highside0020.180

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements03.393.413.55
Water Supply System9.69.5719.119.14
Sewerage treatment & garbage disposal01.421.44.96
Electricity Supply System47.147.0694.194.12
Storm Water Drainage1.31.302.62.60
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other569.9569.94651.4651.36
Highside53.8053.8120.220.18

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.920.3320.320.33
Water Supply System47.847.8557.457.42
Sewerage treatment & garbage disposal5.05.665.74.96
Electricity Supply System188.2188.23188.2188.23
Storm Water Drainage5.25.199.19.09
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other488.5488.52569.9569.94
Security and Fire Fighting127.7127.72127.7127.72
Hardscape50.850.8250.850.82
Highside20.220.1813.513.45
Signages4.79
Electrical Sub Station10.62

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.313.5513.616.94
Water Supply System57.457.4267.066.99
Sewerage treatment & garbage disposal5.05.665.74.25
Electricity Supply System235.3235.29188.2188.23
Storm Water Drainage11.711.685.25.19
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other407.1407.10325.7325.68
Electrical sub station10.624.7824.831.86
Signages4.811.1711.214.37
Highside13.520.1853.853.81
Hardscape50.871.1471.171.14
Landscape35.435.4047.247.20
Street Lighting4.74.727.67.55
Softscape4.14.075.45.42
Security and Firefighting127.7127.72127.7106.44

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.923.720.3323.71
Water Supply System67.067.076.5676.56
Sewerage treatment & garbage disposal4.23.53.542.83
Electricity Supply System235.3235.3235.29235.29
Storm Water Drainage7.87.89.099.09
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0244.3000
Other244.30162.84162.84
Street Lighting9.49.411.3311.33
Softscape6.86.89.499.49
Hardscape71.181.381.3150.82
Electrical sub station31.921.221.2417.70
Signages14.49.69.587.98
Landscape59.059.082.6082.60
Highside13.513.553.8153.81
Security and fire fighting106.4170.3170.30170.30

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.7120.3320.3313.55
Water Supply System38.2838.2819.1419.14
Sewerage treatment & garbage disposal2.832.122.120
Electricity Supply System282.35376.47376.47376.47
Storm Water Drainage5.195.195.195.19
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other162.84162.84162.84162.84
Security and fire fighting170.30106.44106.4485.15
Landscape94.4094.40106.20106.20
Signages7.987.987.9815.96
Electrical sub station17.7017.7017.7035.40
Hardscape50.8250.8250.8281.31
Softscape10.8410.8412.2012.20
Highside47.0847.0813.4513.450
Street Lighting9.449.444.724.72

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements13.55000
Water Supply System19.1419.1400
Sewerage treatment & garbage disposal0000
Electricity Supply System235.29235.2900
Storm Water Drainage2.602.6000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other162.84162.8400
Softscape13.5513.5510.84
Electrical sub station35.4035.40
Signages15.9615.96
Highside13.4513.45
Landscape118.00118.0094.40
Security and fire fighting42.57
Hardscape30.49
Street Lighting0












Yes
No
AXIS BANK LIMITED, STS 25 & 45, GR, BOYS PG BEHIND DLF STAR MALL, TOWER, SECTOR 30, GURUGRAM, HARYAN
923020054000667
UTIB0003622
110211230
3622
Sushil Kumar Kali Dass, Bah (391), Mandi, Himachal Pradesh, 175049
yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LETTER OF INTENT (LOI)ALREADY BEEN OBTAINED07-06-2023
II. LICENCE NO. 147 OF 2023ALREADY BEEN OBTAINED18-07-2023
III. NOC FOR HEIGHT CLEARANCEALREADY BEEN OBTAINED16-08-2023
IV. ASSURANCE CERTIFICATE OF ELECLTRICAL LOADALREADY BEEN OBTAINED28-08-2023
V. ASSURANCE FOR STORM WATERALREADY BEEN OBTAINED16-08-2023
VI. ASSURANCE FOR WATER SUPPLYALREADY BEEN OBTAINED21-08-2023
VII. ASSURANCE FOR SEWERAGE SUPPLYALREADY BEEN OBTAINED18-08-2023
VIII. ASSURANCE FOR SUPPLY TREATED WATER CONSTRUCTION PURPOSEALREADY BEEN OBTAINED23-08-2023
IX. FOREST NOCALREADY BEEN OBTAINED20-06-2023
X. ARAVALI NOCALREADY BEEN OBTAINED25-08-2023
XI. BR-III BUILDING PLAN APPROVALALREADY BEEN OBTAINED09-11-2023








Yes


Yes


The draft agreement is in the prescribed format.







GODREJ RETREAT AROMA
9.7063
0
180
0
177
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
3223.8200
Cost of the apartments000
Cost of the infrastructure399.1800
Others costs4344.5200


13091.065 Lakhs
1760.41 Lakhs
0 Lakhs
0.024 Lakhs
No
08-12-2022
08-12-2022




GODREJ HABITAT
7.46875
452
5
381
5
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
323003447515013
Cost of the apartments000
Cost of the infrastructure000
Others costs11500107358788


16994 Lakhs
29364 Lakhs
0 Lakhs
0 Lakhs
No
25-02-2023
24-08-2024




GODREJ RETREAT SYMPHONY
9.31875
0
166
0
159
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
3022.023022.022059.38
Cost of the apartments000
Cost of the infrastructure370.79370.79159.36
Others costs4406.554485.624485.62


7172 Lakhs
6333 Lakhs
0 Lakhs
0 Lakhs
No
08-12-2022
08-12-2022




GODREJ RETREAT VIBE
7.806
0
141
0
141
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
3065.193065.192011.11
Cost of the apartments000
Cost of the infrastructure360.64360.6471.22
Others costs4285.984286.054286.05


7118 Lakhs
5633 Lakhs
0 Lakhs
0 Lakhs
No
08-12-2022
08-12-2022




GODREJ RETREAT VISTA
6.70
0
119
0
115
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2207.912207.911523.76
Cost of the apartments000
Cost of the infrastructure272.60272.6056.26
Others costs3239.633239.633238.89


5205 Lakhs
4127 Lakhs
0 Lakhs
0 Lakhs
No
08-12-2022
08-12-2022




GODREJ RETREAT ORCHARD
10.3375
0
187
0
184
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
3403.753403.753348.83
Cost of the apartments000
Cost of the infrastructure459.76459.76139.84
Others costs5863.955863.955563.07


8992 Lakhs
7588 Lakhs
0 Lakhs
0 Lakhs
No
08-12-2022
08-12-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
2WALL FINISHING DETAILSACRYLIC EMULSION/ OIL BOUND DISTEMPER
3KITCHEN DETAILSFLOOR: VITRIFIED TILES WALL: CERAMIC TILES 2'-0" ABOVE COUNTER & OIL BOUND DISTEMPER CEILING: OIL BOUND DISTEMPER
4BATHROOM FITTINGSALL PROVIDED WITH STANDARD COMPANY MAKE
5WOOD WORK ETCLAMINATE FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)(PREHUNG- LVL WITH LAMINATE)
6DOORS AND WINDOS FRAMESLAMINATE FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)(PREHUNG- LVL WITH LAMINATE)
7GLASS WORK4MM & ABOVE AS PER SPECIFICATION
8ELECTRIC FITTINGSAS PER BUILDING NORMS
9CONDUCTING AND WIRING DETAILSAS PER BUILDING NORMS
10CUPBOARD DETAILSNA
11WATER STORAGEUNDERGROUND WASTER TANK & OVERHEAD WATER TANK
12LIFT DETAILS3 IN EACH TOWER- 2 PASSENGER AND 1 SERVICE
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSPOWDER COATED ALUMINUM / UPVC
14DOORS(LAMINATE FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)(PREHUNG- LVL WITH LAMINATE)
14.1MAIN DOORS(LAMINATE FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)(PREHUNG- LVL WITH LAMINATE)
14.2INTERNAL DOORS(LAMINATE FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)(PREHUNG- LVL WITH LAMINATE)
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSAS PER BUILDING NORMS
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETBD
20INTERNAL FINISHINGPROVIDING AND APPLYING 10 TO 12MM THICK PLASTER TO MASONRY AND RCC WALLS, COLUMNS ETC. IN CEMENT MORTAR 1:5
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSACRYLIC EMULSION/ OIL BOUND DISTEMPER
1 . 3 CEILINGOIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSACRYLIC EMULSION
2 . 3 CEILINGOIL BOUND DISTEMPER
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILES
3 . 2 WALLSCERAMIC TILES TILL 7' ON ALL SIDES & OIL BOUND DIST
3 . 3 CEILINGGRID CEILING
3 . 4 COUNTERSGRANITE
3 . 5 SANITARY WARE/CP FITTINGSALL PROVIDED OF STANDARD COMPANY NAME
3 . 6 FITTING/FIXTURESALL PROVIDED OF STANDARD COMPANY NAME
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION
4 . 3 CEILINGOIL BOUND DISTEMPER
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILE
5 . 2 WALLSACRYLIC EMULSION / OIL BOUND DISTEMPER
5 . 3 CEILINGOIL BOUND DISTEMPER
5 . 4 COUNTERSGRANITE
5 . 5 SANITARY WARE/CP FITTINGSALL PROVIDED OF STANDARD COMPANY NAME
5 . 6 FIXTURESALL PROVIDED OF STANDARD COMPANY NAME
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSOIL BOUND DISTEMPER
6 . 3 CEILINGOIL BOUND DISTEMPER
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESALL PROVIDED OF STANDARD COMPANY NAME
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES
7 . 2 WALLS & CEILINGACRYLIC EMULSION / OIL BOUND DISTEMPER
7 . 3 TOILETANTI SKID TILE
7 . 4 BALCONYANTI SKID TILE
8 . SIT-OUTS
8 . 1 FLOORANTI SKID TILE
8 . 2 WALLS & CEILINGACRYLIC EMULSION / OIL BOUND DISTEMPER
8 . 3 RAILINGSMS STEEL
8 . 4 FIXTURESALL PROVIDED OF STANDARD COMPANY NAME












Sr. No.Document DescriptionDate of Document UploadView Document
1 NOC FOR HEIGHT CLEARANCE 08-11-2023 View Document
2 ARAVALI NOC 08-11-2023 View Document
3 BR III BUILDING PLAN APPROVAL 10-11-2023 View Document
4 ASSURANCE CERTIFICATE FROM DHBVN 09-11-2023 View Document
5 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 08-11-2023 View Document
6 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 08-11-2023 View Document
7 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 08-11-2023 View Document
8 LOI 08-11-2023 View Document
9 ASSURANCE OF DRINKING WATER 08-11-2023 View Document
10 ASSURANCE OF STORM WATER 08-11-2023 View Document
11 ASSURANCE OF SEWAGE 08-11-2023 View Document
12 FOREST NOC 08-11-2023 View Document
13 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 09-11-2023 View Document
14 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 14-11-2023 View Document
15 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 14-11-2023 View Document
16 DEMARCATION PLAN 14-11-2023 View Document
17 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 15-11-2023 View Document
18 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 07-12-2023 View Document
19 ZONING PLAN 11-12-2023 View Document
20 ELEVATION 1 TOWER T3 & T4 11-06-2024 View Document
21 LC-IV & LC IVA 11-06-2024 View Document
22 GREEN AREA CALCULATION, PARKING PLAN & PODIUM GROUND COVERAGE 11-06-2024 View Document
23 REFUGEE FLOOR PLAN & AREA CALCULATION TOWER T3 & T4 11-06-2024 View Document
24 TERRACE AND MUMTY PLAN CLUB 11-06-2024 View Document
25 SITE PLAN STORM WATER & SEWERAGE LAYOUT 11-06-2024 View Document
26 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 11-06-2024 View Document
27 BASEMENT 1 11-06-2024 View Document
28 ELEVATION 3 TOWER T1 & T2 11-06-2024 View Document
29 ROOF PLAN TOWER T3 & T4 11-06-2024 View Document
30 STILT GROUND FLORR PLAN TOWER T3 & T4 11-06-2024 View Document
31 TYPICAL FLOOR PLAN & AREA CALCULATION TOWER T3 & T4 11-06-2024 View Document
32 SECOND FLOOR PLAN & AREA DIAGRAM CLUB 11-06-2024 View Document
33 TERRACE PLAN TOWER T1 & T2 11-06-2024 View Document
34 STILT GROUND FLORR PLAN TOWER T1 & T2 11-06-2024 View Document
35 CA CERTIFICATE FOR COST INCURRED 11-06-2024 View Document
36 GROUND FLOOR PLAN & AREA DIAGRAM EWS & NURSERY SCHOOL 11-06-2024 View Document
37 AFFIDAVIT OF PROMOTER REGARDING ARRANGEMENT WITH THE BANK OF MASTER ACCOUNT 11-06-2024 View Document
38 NON ENCUMBRANCE CERTIFICATE 11-06-2024 View Document
39 FIRST FLOOR PLAN TOWER T5 & T6 11-06-2024 View Document
40 MASTER PLAN & AREA STATEMENTS_SITE PLAN 11-06-2024 View Document
41 SITE PLAN IRRIGALION LAYOUT PLAN 11-06-2024 View Document
42 INFORMATION TO REVENUE DEPARTMENT SECTOR 49 11-06-2024 View Document
43 SECOND FLOOR PLAN TOWER T5 & T6 11-06-2024 View Document
44 TYPICAL FLOOR PLAN 1 & AREA CALCULATION TOWER T5 & T6 11-06-2024 View Document
45 FIRST FLOOR PLAN TOWER T3 & T4 11-06-2024 View Document
46 DEMAND DRAFT 11-06-2024 View Document
47 ELEVATION 1 TOWER T1 & T2 11-06-2024 View Document
48 FIRST FLOOR PLAN TOWER T1 & T2 11-06-2024 View Document
49 SECTIONS CC 7 DD TOWER T1 & T2 11-06-2024 View Document
50 CA CERTIFICATE FOR FINANCIAL & INVENTORY DETAILS 11-06-2024 View Document
51 MUMTY & MACHINE ROOM TOWER T5 & T6 11-06-2024 View Document
52 SUPERIMPOSED DEMARCATION PLAN ON APPROVED LAYOUT PLAN 11-06-2024 View Document
53 HUDA CONSTRUCTION WATER NOC 11-06-2024 View Document
54 SITE SECTION CC 11-06-2024 View Document
55 TERRACE PLAN TOWER T3 & T4 11-06-2024 View Document
56 REFUGEE FLOOR PLAN & AREA CALCULATION TOWER T5 & T6 11-06-2024 View Document
57 SITE SECTION AA 11-06-2024 View Document
58 EWS & NURSERY SCHOOL ELEVATION & SECTION 11-06-2024 View Document
59 SITE PLAN FIRE FIGHTING LAYOUT PLAN 11-06-2024 View Document
60 ELEVATION 3 TOWER T5 & T6 11-06-2024 View Document
61 BANK UNDERTAKING 11-06-2024 View Document
62 ROOF PLAN TOWER T5 & T6 11-06-2024 View Document
63 SECTIONS EE & FF TOWER T3 & T4 11-06-2024 View Document
64 ELEVATION 2 AND 4 TOWER T5 & T6 11-06-2024 View Document
65 ELEVATIONS AND SECTIONS EWS & NURSERY SCHOOL 11-06-2024 View Document
66 SECTIONS BB & AA T5 & T6 11-06-2024 View Document
67 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 11-06-2024 View Document
68 ELEVATION 1 TOWER T5 & T6 11-06-2024 View Document
69 GROUND STILT PLAN AREA CALCULATION _ PARKING PLAN 11-06-2024 View Document
70 ELEVATION 4 AND 2 TOWER T1 & T2 11-06-2024 View Document
71 ELEVATION 3 TOWER T3 & T4 11-06-2024 View Document
72 TERACE, MUMTY, ROOF LEVEL PLANS & AREA CALCULATION EWS & NURSERY SCHOOL 11-06-2024 View Document
73 GROUND COVERAGE DIAGRAM, SECOND TYPICAL FLOOR PLAN AND AREA DIAGRAM EWS & NURSERY SCHOOL 11-06-2024 View Document
74 BASEMET B1 & B2 _LAYOUT PLAN 11-06-2024 View Document
75 THIRD FLOOR PLAN & AREA DIAGRAM CLUB 11-06-2024 View Document
76 ELEVATION 2 & 4 TOWER T3 & T4 11-06-2024 View Document
77 SITE SECTION BB 11-06-2024 View Document
78 CONVENIENT SHOPPING, GUARD ROOM, AREA DIAGRAM ELEVATION SECTIONS 11-06-2024 View Document
79 REFUGEE FLOOR PLAN & AREA CALCULATION TOWER T1 & T2 11-06-2024 View Document
80 SECOND FLOOR PLAN TOWER T3 & T4 11-06-2024 View Document
81 TERRACE PLAN TOWER T5 & T6 11-06-2024 View Document
82 ROOF PLAN TOWER T1 & T2 11-06-2024 View Document
83 STILT GROUND FLOOR PLAN & AREA DIAGRAM CLUB 11-06-2024 View Document
84 TYPICAL FLOOR PLAN 2 & AREA CALCULATION TOWER T5 & T6 11-06-2024 View Document
85 1ST PODIUM PLAN & RAMP SECTION 11-06-2024 View Document
86 TYPICAL FLOOR PLAN & AREA CALCULATION TOWER T1 & T2 11-06-2024 View Document
87 EWS & NURSERY SCHOOL TERRACE, MUMTY AND ROOF LEVEL PLAN AND DIAGRAM 11-06-2024 View Document
88 FIRST FLOOR PLAN & AREA DIAGRAM CLUB 11-06-2024 View Document
89 SECTION & ELEVATION_ CLUB 11-06-2024 View Document
90 EWS & NURSERY SCHOOL ELEVATION & SECTION1 11-06-2024 View Document
91 SITE PLAN 11-06-2024 View Document
92 STILT GROUND FLORR PLAN TOWER T5 & T6 11-06-2024 View Document
93 MUMTY & MACHIN ROOM TOWER T1 & T2 11-06-2024 View Document
94 MUMTY & MACHINE ROOM TOWER T3 & T4 11-06-2024 View Document
95 SECOND FLOOR PLAN TOWER T1 & T2 11-06-2024 View Document