HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1340-2023
Submission Date : 18-09-2023 03:50:48 PM
Applicant Type : Firm
Project Type: NEW


PSG PROPBUILD LLP
1F 22-26 OZONE CENTRE SECTOR 12 FARIDABAD
01292265143
9313930668 (Number Shared by Promoter in Public)
jetaishgupta@gmail.com
AAY2860
ABAFP8354R













PROSPERITY HOMES
VILLAGE BUDENA, SECTOR 86
FARIDABAD
FARIDABAD
01292265143
9313930668 (Number Shared by Promoter in Public)
adorerealtech@gmail.com
DILSHAD
01292265143
8130999376 (Number Shared by Promoter in Public)
adorerealtech@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
12635715-09-20231358000IDBI BANK HRERA Panchkula







6.34375 (Acre)
2.28
2.2776
6.34375 (Acre)
LICENSE NO. 112 OF 2023 DATED 25.05.2023 WHICH IS VALID UPTO 24.05.2028 ISSUED BY DTCP HARYANA.
Yes







21670.00 Lakhs
4600.00 Lakhs
12100.00 Lakhs
1420.00 Lakhs
3550.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5.83625
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13COMMERCIAL0.50750
Total6.34375




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALSHVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS350.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM220.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE190.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM120.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL200.00AS PER PROJECT REPORT
6STREET LIGHTING200.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS140.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


14-09-2023 (date)
NA (date)
25-12-2023
24-05-2028
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings6069613
Apartment/Shops/Other Buildings28.13902
Apartment/Shops/Other Buildings28.96902





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments720720720720
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments720720720720
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments720720720720
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments720720720720
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments580
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.5020.5020.5020.50
Water Supply System13.0013.0013.0013.00
Sewerage treatment & garbage disposal11.7511.7511.7511.75
Electricity Supply System7.007.007.007.00
Storm Water Drainage11.0011.0011.0011.00
Parks and Playgrounds8.258.258.258.25
Clubhouse/community centres0000
Shopping area0000
Other11.7511.7511.7511.75

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.5020.5020.5020.50
Water Supply System13.0013.0013.0013.00
Sewerage treatment & garbage disposal11.7511.7511.7511.75
Electricity Supply System7.007.007.007.00
Storm Water Drainage11.0011.0011.0011.00
Parks and Playgrounds8.258.258.258.25
Clubhouse/community centres0000
Shopping area0000
Other11.7511.7511.7511.75

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.5020.5020.5020.50
Water Supply System13.0013.0013.0013.00
Sewerage treatment & garbage disposal11.7511.7511.7511.75
Electricity Supply System7.007.007.007.00
Storm Water Drainage11.0011.0011.0011.00
Parks and Playgrounds8.258.258.258.25
Clubhouse/community centres0000
Shopping area0000
Other11.7511.7511.7511.75

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.5020.5020.5020.50
Water Supply System13.0013.0013.0013.00
Sewerage treatment & garbage disposal11.7511.7511.7511.75
Electricity Supply System7.007.007.007.00
Storm Water Drainage11.0011.0011.0011.00
Parks and Playgrounds8.258.258.258.25
Clubhouse/community centres0000
Shopping area0000
Other11.7511.7511.7511.75

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.00
Water Supply System12.00
Sewerage treatment & garbage disposal12.00
Electricity Supply System8.00
Storm Water Drainage14.00
Parks and Playgrounds8.00
Clubhouse/community centres0
Shopping area0
Other12.00












No
No
IDBI BANK, 5C/3 B P NIT FARIDABAD
1037102000019035
IBKL0001037
110259050
001037
Ritik 1F-22-26 Ozone Centre Sector 12 Faridabad
Uploaded in upload Section.











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO 112 OF 2023ALREADY BEEN OBTAINED24-05-2023
II. BUILDING PLANALREADY BEEN OBTAINED14-09-2023








Yes


Yes


Important provision of RERA have been incorporated in the draft agreements













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES/CERAMIC TILES
2WALL FINISHING DETAILSCOLOUR WASH/ DRY DISTEMPER/OIL BOUND DISTEMPER (OBD)
3KITCHEN DETAILSCOUNTER TOP - MARBLE TOP/ KOTA STONE, TILES UP TO 2 FEET HEIGHT ABOVE THE COUNTER
4BATHROOM FITTINGSPPR PIPES / CPVC PIPES, CP FITTINGS OD ISI MARKED
5WOOD WORK ETCFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
6DOORS AND WINDOS FRAMESFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
7GLASS WORK5MM PLAIN GLASS, ISI MARKED
8ELECTRIC FITTINGSISI MARKED
9CONDUCTING AND WIRING DETAILSISI MARKED
10CUPBOARD DETAILSNA
11WATER STORAGEWATER TREATEMENT PLANT OF 400 KLD
12LIFT DETAILS2 LIFTS IN EACH TOWER
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSAS MENTIONED ABOVE
14.1MAIN DOORSFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
14.2INTERNAL DOORSFLUSH DOOR PAINTED WITH FLAT ENAMEL PAINT
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEPLAIN TEXTURE PAINT
20INTERNAL FINISHINGCOLOUR WASH/ DRY DISTEMPER/ OIL BOUND DISTEMPER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES/ CEREMIC TILES
1 . 2 WALLSCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
1 . 3 CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES/ CEREMIC TILES
2 . 2 WALLSCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
2 . 3 CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CEREMIC TILES
3 . 2 WALLSCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
3 . 3 CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSISI MARKED
3 . 6 FITTING/FIXTURESISI MARKED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES/ CEREMIC TILES
4 . 2 WALLSCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
4 . 3 CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILES
5 . 2 WALLSCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
5 . 3 CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSISI MARKED
5 . 6 FIXTURESISI MARKED
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES/ CEREMIC TILES
6 . 2 WALLSCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
6 . 3 CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
6 . 4 COUNTERSMARBLE STONE/ KOTA STONE
6 . 5 FIXTURESISI MARKED
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES/ CEREMIC TILES
7 . 2 WALLS & CEILINGCOLOUR WASH/ DRY DISTEMPER OIL BOUND DISTEMPER
7 . 3 TOILETNA
7 . 4 BALCONYCEREMIC TILES
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND18-09-2023 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN18-09-2023 View Document
3DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.18-09-2023 View Document
4NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT18-09-2023 View Document
5CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT18-09-2023 View Document
6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS18-09-2023 View Document
7IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN18-09-2023 View Document