OFFICE NO. GF-17 JMD PACIFIC SQUARE SECTOR 15 PART II GURUGRAM
9810411227 (Number Shared by Promoter in Public)
dadwal_textchem@yahoo.com
http://www.prominenterprises.com
XXXX659F
U70109HR2019PTC079445
SWASTIK GREENS
VILLAGE BANSHARIYA SECTOR M-9 AND M-10 MANESAR
HARSARU ST
GURUGRAM
9810411227 (Number Shared by Promoter in Public)
dadwal_textchem@yahoo.com
DHIRENDRA DADWAL
9810411227 (Number Shared by Promoter in Public)
dadwal_textchem@yahoo.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
8570
11-09-2023
8735000
HDFC BANK
HRERA Gurugram
106.6625 (Acre)
1.00
1.00
106.6625 (Acre)
65 OF 2023(27-03-2023)
Yes
55659.29 Lakhs
3432.95 Lakhs
0 Lakhs
6731.93 Lakhs
45494.41 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
65.2084
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
27.4904
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
3.5634
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.3481
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.5531
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
COMMUNITY
4.7737
14
UD
4.237
15
COMMERCIAL
0.4884
Total
106.6625
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
2388.92
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
555.04
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
668.03
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
1145.04
SUBMITTED TO HUDA
6
STREET LIGHTING
105.22
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
25.55
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
1844.13
SUBMITTED TO HUDA
28-06-2023 (date)
NA (date)
01-10-2023
26-03-2028
Plot Area(In Square Meter)
Number of plots in the project
2979.76
4
2971.14
1
3841.39
3
3843.68
1
1922.99
2
2843.08
12
3374.21
1
3373.24
4
2814.86
1
282.91
2
408.47
1
437.48
2
392.23
9
391.96
1
1461.02
1
1703.35
8
2058.44
1
795.68
6
796.13
1
836.21
3
837.56
1
1001.35
1
954.66
10
126.79
1
142.17
16
143.56
2
123.68
7
124.45
1
147.71
1
147.89
5
149.97
18
148.69
2
142.57
26
140.99
2
142.61
26
141.03
2
120.00
16
127.10
14
129.26
1
111.04
32
112.09
2
137.09
1
126.54
44
128.21
2
146.28
59
100.55
20
100.84
1
139.05
40
150.00
138
148.49
40
111.12
6
110.81
2
123.41
20
124.32
2
126.30
6
126.60
2
144.08
9
141.57
13
141.96
1
135.79
4
135.42
52
124.32
4
123.95
12
133.76
36
134.31
4
142.96
2
143.55
28
141.20
18
141.79
2
150.00
14
144.60
9
145.20
1
147.11
1
149.03
69
147.11
2
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
271.65
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
95.56
Water Supply System
55.50
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
66.80
Parks and Playgrounds
2.56
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
238.89
238.89
167.22
119.45
Water Supply System
55.50
27.75
55.50
27.75
Sewerage treatment & garbage disposal
0
0
0
114.50
Electricity Supply System
0
0
0
0
Storm Water Drainage
66.80
33.40
66.80
33.40
Parks and Playgrounds
5.11
2.56
2.56
2.56
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
167.22
119.45
119.45
95.56
Water Supply System
55.50
83.26
83.26
27.75
Sewerage treatment & garbage disposal
114.50
114.50
68.70
171.76
Electricity Supply System
0
0
0
0
Storm Water Drainage
66.80
100.20
100.20
33.40
Parks and Playgrounds
5.11
2.56
2.56
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
21.04
15.78
10.52
10.52
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
119.45
119.45
119.45
143.34
Water Supply System
27.75
27.75
27.75
0
Sewerage treatment & garbage disposal
57.25
114.50
114.50
171.76
Electricity Supply System
0
0
0
0
Storm Water Drainage
33.40
33.40
33.40
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
10.52
5.26
5.26
5.26
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
15.02
47.78
71.67
71.67
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
103.05
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
5.26
5.26
3.16
4.21
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
47.78
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
STREET LIGHTING
3.16
Yes
No
HDFC BANK LTD AND A12 THE SHOPPING MALL DLF QUTUB ENCLAVE PHASE1 GURUGRAM HARYANA 122001
50200088403145
HDFC0000044
110240006
0044
1. DHIRENDRA DADWAL, P.O. PATHANKOT TEH PATHANKOT MANWAL GURDASPUR PUNJAB-145001
UPLOADED
Yes
Yes
Yes
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
27-03-2023
II. LAYOUT PLAN
ALREADY BEEN OBTAINED
28-06-2023
III. DEMARCATION PLAN
ALREADY BEEN OBTAINED
21-08-2023
IV. ZONING PLAN
ALREADY BEEN OBTAINED
21-08-2023
V. NOC ARAVALLI
ALREADY BEEN OBTAINED
08-09-2023
VI. NOC FOREST
ALREADY BEEN OBTAINED
20-03-2023
No
No
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: