HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1412-2023
Submission Date : 08-09-2023 03:03:39 PM
Applicant Type : Company
Project Type: ONGOING




VATIKA SOVEREIGN PARK PVT. LTD
FLAT NO. 224A, 2ND FLOOR, DEVIKA TOWER, 6, NEHRU PLACE, NEW DELHI-110019
01244177777
9810566938 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
Https://www.vatikacollections.com
XXXX383D
U70109DL2011PTC215498
 
 


 
 


 
 


 
 


 
 







SOVEREIGN PARK (PHASE-II)
SECTOR-99, VILLAGE-KHERKI MAJRA DHANKOT
KADIPUR ST
GURUGRAM
01244177777
8800772626 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
ARUP KUMAR DAS
01244177777
8800772626 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
174866208-09-2023575000.00STANDARD CHARTERED BANKHRERA Gurugram
274866308-09-2023328500.00STANDARD CHARTERED BANKHRERA Gurugram







4.8338 (Acre)
175
174.98
10.43125 (Acre)
1) License No. 119.of 2012 dated 06-12-2012. 2) License No. 65.of 2013 dated 20-07-2013.
Yes







41043.41 Lakhs
4781.43 Lakhs
13385.03 Lakhs
610.36 Lakhs
22266.58 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3185.52
3CONSTRUCTION OF ROADS10688.188
4PAVEMENTS0
5PARKS AND PLAYGROUNDS883.608
6GREEN BELTS0
7VEHICLE PARKINGS562.685
8ELECTRICITY SUB-STATION245.430
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY485.664
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13WATERSUPPLY926.093
14STORMWATERDRAINS441.957
15STP407.725
16UGT460.601
17RAINWATERHARVESTING36.371
18STREETLIGHTINGANDELECTRIFICATION166.269
19RENEWABLEENERGYSYSTEM196.222
20SECURITYANDFIREFIGHTINGSERVICES834.706
21LIFT40.650
Total19561.689




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/HSVPNo
WATER SUPPLYHUDA/HSVPNo
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHUDA/HSVPNo
STORM WATER DRAINAGEHUDA/HSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS152.59SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM30.52SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE12.21SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM30.52SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL42.73SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING24.41SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING24.41SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS30.52SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA0SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM12.21SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0SUBMITTED TO TOWN & COUNTRY PLANNING
13HOSPITAL/DISPENSARY0SUBMITTED TO TOWN & COUNTRY PLANNING
14ANY OTHER0SUBMITTED TO TOWN & COUNTRY PLANNING
15PARKING91.55SUBMITTED TO TOWN & COUNTRY PLANNING
16UNDERGROUND TANK24.41SUBMITTED TO TOWN & COUNTRY PLANNING
17RAIN WATER HARVESTING12.21SUBMITTED TO TOWN & COUNTRY PLANNING
18ELECTRICAL METER ROOM30.52SUBMITTED TO TOWN & COUNTRY PLANNING
19LIFT61.04SUBMITTED TO TOWN & COUNTRY PLANNING
20STP30.52SUBMITTED TO TOWN & COUNTRY PLANNING


22-10-2014 (date)
22-10-2014 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 3BR+/1595.661595.66120120
2APARTMENT/SHOPS/OTHER BUILDINGS Type EWS+/202.15202.15310310
3APARTMENT/SHOPS/OTHER BUILDINGS Type EWS+/209.25209.25240240
4APARTMENT/SHOPS/OTHER BUILDINGS Type 3BR+/1595.981595.98200200
5APARTMENT/SHOPS/OTHER BUILDINGS Type 3BR+/1613.631613.638080
6APARTMENT/SHOPS/OTHER BUILDINGS Type 3BR+/1710.941710.941010
7APARTMENT/SHOPS/OTHER BUILDINGS Type 3BR+/1712.551712.55280280
8APARTMENT/SHOPS/OTHER BUILDINGS Type 3BR+/1721.491721.49290290
9APARTMENT/SHOPS/OTHER BUILDINGS Type 4BR+/2091.452091.452020
10APARTMENT/SHOPS/OTHER BUILDINGS Type 4BR+/2091.662091.66400400
11APARTMENT/SHOPS/OTHER BUILDINGS Type PENT HOUSE+/2484.012484.012020
12APARTMENT/SHOPS/OTHER BUILDINGS Type PENT HOUSE+/2806.52806.501010
13APARTMENT/SHOPS/OTHER BUILDINGS Type PENT HOUSE+/3492.73492.704040






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
NIL00


26-10-2014
10-07-2027
10-07-2027
11-07-2018
10
14-08-2026
PROVIDED
PROVIDED ANNEXURE-C


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NIL
11-07-2018
10
14-08-2026
PROVIDED
PROVIDED


331
25
0
21
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments1959.58
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1000.001000.00
Shops00
Plots00

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1000.00900.00900.00900.00
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments900.00900.00800.00800.00
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments800.00800.00725.450
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements45.78
Water Supply System4.58
Sewerage treatment & garbage disposal6.41
Electricity Supply System2.44
Storm Water Drainage1.22
Parks and Playgrounds3.05
Clubhouse/community centres0
Shopping area0
Other0
Electrical meter room0
Electrification1.53
Lift0
Parking18.31
Rain water harvesting pit1.22
Renewable Energy System0
Security and Fire Fighting Services2.44
STP0
Underground Tank2.44

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1410
Water Supply System44
Sewerage treatment & garbage disposal54
Electricity Supply System00
Storm Water Drainage22
Parks and Playgrounds23
Clubhouse/community centres00
Shopping area00
Other00
Electrical meter room00
Lift00
Rain water harvesting pit22
Electrification00
Security and Fire Fighting Services23
Renewable Energy System00
Parking1410
STP04
Underground Tank00

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements121288
Water Supply System3422
Sewerage treatment & garbage disposal3345
Electricity Supply System2342
Storm Water Drainage1.50.6010.8
Parks and Playgrounds3123
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Tank4432
STP2345
Parking8755
Renewable Energy System1120.7
Security and Fire Fighting Services3122
Electrification4433.5
Electrical meter room4466
Lift66812
Rain water harvesting pit1.50.6010.8

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6657
Water Supply System2111
Sewerage treatment & garbage disposal331.51
Electricity Supply System2221
Storm Water Drainage0.50.50.50.25
Parks and Playgrounds2231.5
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and Fire Fighting Services111.51.5
STP331.52
Underground Tank1121
Lift7864
Electrical meter room2231
Renewable Energy System0.70.821
Rain water harvesting pit0.50.50.50.25
Electrification1223
Parking7632

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements873.810
Water Supply System0.70.80.440
Sewerage treatment & garbage disposal210.820
Electricity Supply System120.970
Storm Water Drainage0.40.50.440
Parks and Playgrounds220.970
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical meter room20.520
Security and Fire Fighting Services1.420.57
Renewable Energy System11.20.81
Parking321.24
STP21.020
Underground Tank1.51.50.97
Electrification321.49
Rain water harvesting pit0.400.50.44
Lift21.50.54












Particulars Remarks, if any
i. No. of Flats/Apartments constructed202Unsold
ii. No. of Flats/ Apartments booked0Nil
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter0 LakhsNil
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter0 LakhsNil
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter0 LakhsNil
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 LakhsNil
vii. Amount invested in the project upto the date of application21326.62 Lakhs
Land cost (If any)4781.42 Lakhs
Apartments1959.58 Lakhs
Infrastructure89.42 Lakhs
EDC/ Taxes Etc.14496.20 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession19716.80 Lakhs
(a) In respect of existing allottees0 LakhsNil
(b) In respect of rest of the project19716.80 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
13050 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 889.00 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS152.5945.78
II. WATER SUPPLY SYSTEM30.524.58
III. STORM WATER DRAINAGE12.211.22
IV. ELECTRICITY SUPPLY SYSTEM30.521.53
V. SEWAGE TREATMENT & GARBAGE DISPOSAL42.736.4
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.30.523.05
XIII. COVERED PARKING91.5518.31
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM24.412.44
XVII. OTHER FACILITIES AS PER PROJECT REPORT195.316.10









Yes
Yes
STANDARD CHARTERED BANK, DLF BUILDING NO. -7, DLF CYBER CITY, SECTOR - 24,25 & 25A, GURGAON -122002
53105108663
SCBL0036025
110036006
036025
1. Mr. Anil Bhalla Hyde Park, Prakrati Marg, Sultanpur Farms, Gadaipur, South Delhi, Delhi 110030 2. Mr. Gautam Bhalla LCG05 PHB The Laburnam, Nathupur (67), Nathupur, Gurugram, Haryana 122002 3. Mr. K V George Flat No. 1504, Mohinder Apartment, Plot No. 17, Sector 12, Dwarika, South West Delhi - 110075
uploaded











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLAN ALREADY BEEN OBTAINED22-10-2014
II. ZONING PLAN ALREADY BEEN OBTAINED22-07-2013
III. BUILDING PLAN (BR=III) ALREADY BEEN OBTAINED22-10-2014
IV. SITE PLAN ALREADY BEEN OBTAINED22-10-2014
V. FLOOR PLAN ALREADY BEEN OBTAINED22-10-2014
VI. APARTMENT PLAN ALREADY BEEN OBTAINED22-10-2014
VII. ELEVATION PLAN ALREADY BEEN OBTAINED22-10-2014








Yes


Yes


Provided













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSELIVING/DRAWING, BEDROOM HIGH QUALITY, ABRASION RESISTANT MATT FINISHED VITREOUS, MASTER TOILET MATT FINISHED/ANTISKID CERAMIC TILES SOMANY, ROOM/UTILITY ROOM MATT FINISHED CERAMIC TILES SOMANY
2WALL FINISHING DETAILSINTERNAL WALL ACRYLIC EMULSION PAINT BERGER EXTERNAL WALL EXTERNAL GRADE ANTI FUNGAL / ANTI ALGAL PAINT BERGER
3KITCHEN DETAILSWALL TILE OF APPROVED MAKE IN CLADDING /DADO OVER ON 12-15MM THICK CEMENT MORTAR 1:3 SOMANY, BIB COCK, PILLAR COCK, ABLUTION TAP ALONG WITH NECESSARY ANGLE VALVES ETC. OF STANDARD MAKES AND BRANDS. ESSCO 5.8 SINK 18" X 14"X 8" BOWL NEELKANTH
4BATHROOM FITTINGSWASH BASIN, EUROPEAN WATER CLOSET (EWC) OF STANDARD MAKES HINDWARE PILLAR COCK, ABLUTION TAP ALONG WITH NECESSARY ANGLE VALVES ETC. OF STANDARD MAKES AND BRANDS. ESSCO
5WOOD WORK ETC35MM FLUSH DOOR WITH BOTH SIDE 0.8MM THICK LAMINATE: HARD WOOD, ALUMINUM FRAME WITH DOOR AND SHUTTER POLYWOOD SYSTEM
6DOORS AND WINDOS FRAMESDOOR FRAME WITH MIRANDI HARD WOOD ALUMINIUM FRAME WITH GLASS POLYWOOD SYSTEM
7GLASS WORKWINDOW SHUTTER 6MM CLEAR GLASS WITH FRAME SAINT GOBAIN, TOILET VENTILATOR 6MM FROSTED GLASS SAINT GOBAIN
8ELECTRIC FITTINGSFAN 1200MM SWEEP CEILING FAN: CROMPTON, EXHAUST FAN 300MM DIA WITH SHUTTER CROMPTON
9CONDUCTING AND WIRING DETAILSCONDUIT 5-32 PVC CONDUIT POLYPACK / BEC, SWITCHES MODULAR SWITCHES / SOCKETS BLUE ERA PRECISION, SOCKET MODULAR SWITCHES / SOCKETS BLUE ERA PRECISION, WIRE SKYTON, SWITCH BOARD 1MM-9MM SWITCH PLATE BLUE ERA PRECISION, MCB 6 AMP- 63 AMP MCB INCLUDING TPN LEGRAND
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSPASSANGER ELEVATOR, CAPACITY : 15 PASSENGER, 1020KG, KONE
13EXTERNAL GLAZINGS6MM CLEAR GLASS WITH FRAME SAINT GOBAIN
13.1WINDOWS/GLAZINGS6MM CLEAR GLASS WITH FRAME SAINT GOBAIN
14DOORS35MM FLUSH DOOR WITH BOTH SIDE 0.8MM THICK LAMINATE HARD WOOD
14.1MAIN DOORS35MM FLUSH DOOR WITH BOTH SIDE 0.8MM THICK LAMINATE HARD WOOD
14.2INTERNAL DOORS35MM FLUSH DOOR WITH BOTH SIDE 0.8MM THICK LAMINATE HARD WOOD
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSCALL BELL POINTS 6 AMP ONE WAY SWITCH, POWER SOCKETS FOR AC 16 A 2/3 PIN POCKET, FAN REGULATOR, 16 A 2/3 PIN SOCKET, 6 AMP TWO WAY SWITCH,6 AMP ONE WAY SWITCH, TELEPHONE SOCKET, TV POINT PRECISION -B.E, TELEPHONE SOCKET PRECISION - B.E
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADE ANTI FUNGAL / ANTI ALGAL PAINT: BERGER
20INTERNAL FINISHINGACRYLIC EMULSION PAINT: BERGER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORHIGH QUALITY, ABRASION RESISTANT MATT FINISHED VITREOUS CERAMIC TILES: SOMANY
1 . 2 WALLSPREMIUM EMULSION PAINT ON PLASTERED WALL WITH PUNNING OR PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
1 . 3 CEILINGPREMIUM EMULSION PAINT ON PLASTERED WALL WITH PUNNING OR PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORHIGH QUALITY WOODEN FLOORING: DECOR DESIGN & SERVICES
2 . 2 WALLSPREMIUM EMULSION PAINT WITH PUNNING & PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
2 . 3 CEILINGPREMIUM EMULSION PAINT WITH PUNNING & PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORMATT FINISHED /ANTI SKID CERAMIC TILE: SOMANY
3 . 2 WALLSPLASTERED SURFACE ABOVE DADO LEVEL TILES: SOMANY
3 . 3 CEILINGMOISTURE RESISTANCE ACOUSTIC GYP BOARD: EVEREST
3 . 4 COUNTERS18-20MM THICK GRANITE COUNTER TOP
3 . 5 SANITARY WARE/CP FITTINGSWASH BASIN: ROCA, SINGLE LEVER BASIN MIXER: JAQUAR, SHOWER MIXER/DIVERTOR WITH BATH SPOUT AND OVER HEAD SHOWER,HEALTH FAUCET ALONG WITH NECESSARY ANGLE VALVES ETC. JAQUAR, EUROPEAN WATER CLOSET (EWC): HINDWARE
3 . 6 FITTING/FIXTURES15MM-150M M PVC WATER SUPPLY PIPES & 15-80MM CPVC PIPE WITH STANDARD VALVES AND ACCESSORIES PVC & CPVC SUPREME, DRAINAGE PIPE 150-250MM PVC PIPE SUPREME, 15-25MM CPVC PIPE WITH STANDARD VALVES AND ACCESSORIES: SUPREME
4 . BED ROOMS
4 . 1 FLOORHIGH QUALITY WOODEN FLOORING: DECOR DESIGN & SERVICES
4 . 2 WALLSPREMIUM EMULSION PAINT WITH PUNNING & PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
4 . 3 CEILINGPREMIUM EMULSION PAINT WITH PUNNING & PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORMATT FINISHED ANTISKID CERAMIC TILE: SOMANY
5 . 2 WALLSPLASTERED SURFACE ABOVE DADO LEVEL TILES: SOMANY
5 . 3 CEILINGMOISTURE RESISTANCE ACOUSTIC GYP BOARD: EVEREST
5 . 4 COUNTERS18-20MM THICK GRANITE COUNTER TOP
5 . 5 SANITARY WARE/CP FITTINGSWASH BASIN: HINDWARE, SINGLE LEVER BASIN MIXER: JAQUAR, SHOWER MIXER/DIVERTER WITH BATH SPOUT AND OVER HEAD SHOWER, HEALTH FAUCET ALONG WITH NECESSARY ANGLE VALVES: JAQUAR
5 . 6 FIXTURESWASH BASIN, EUROPEAN WATER CLOSET (EWC) OF STANDARD MAKES HINDWARE PILLAR COCK, ABLUTION TAP ALONG WITH NECESSARY ANGLE VALVES ETC. OF STANDARD MAKES AND BRANDS. ESSCO
6 . KITCHEN
6 . 1 FLOORMATT FINISHED CERAMIC TILES: SOMANY
6 . 2 WALLS2' HIGH CERAMIC TILE DADO ABOVE COUNTER. PREMIUM EMULSION ON PLASTER IN REMAINING AREA: SOMANY
6 . 3 CEILINGPREMIUM EMULSION PAINT WITH PUNNING & PUTTY FOR LEVEL AND SMOOTHNESS: NEROLAC
6 . 4 COUNTERS18-20MM THICK GRANITE COUNTER TOP
6 . 5 FIXTURESDOUBLE BOWL SINK: JR. VICTOR TWIN, SINGLE LEVER MIXER: JAQUAR,
6 . 6 KITCHEN APPLIANCESCOOK TOP AND CHIMNEY KAFF. FABER
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORMATT FINISHED CERAMIC TILE: SOMANY
7 . 2 WALLS & CEILINGPAINT ON PLASTER: NEROLAC
7 . 3 TOILETMATT FINISHED ANTI SKID CERAMIC TILES: SOMANY
7 . 4 BALCONYFLOORS MATT FINISHED ANTI SKID CERAMIC TILES: SOMANY, WALLS EXTERIOR GRADE PAINT ON PLASTER: BURGER, CEILING EXTERIOR GRADE PAINT ON PLASTER: BURGER,
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN02-08-2023 View Document
2ZONING PLAN02-08-2023 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN02-08-2023 View Document
4SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN14-08-2023 View Document
5CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT08-09-2023 View Document
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT05-02-2024 View Document
73RD TO 21ST, TERRACE & ROOF PLAN FLOOR (A,B & C)05-02-2024 ------
811TH,12TH,TERRACE FLOOR & ROOF PLAN (BLOCK-E,G & L)05-02-2024 ------
9AFFIDAVIT BY THE PROMOTER W.R.T. ACCOUNTS05-02-2024 ------
10AIRPORT HEIGHT CLEARANCE05-02-2024 ------
11ALL ELEVATION & SECTION-XX, YY (BLOCK-D)05-02-2024 ------
12AREA CALCULATION (TOWER-A,B,C & COMMUNITY BUILDING-1)05-02-2024 ------
13AREA CALCULATION OF ALL FLOORS (BLOCK-D)05-02-2024 ------
14AREA CALCULATION OF ALL FLOORS (BLOCK-E,G & L)05-02-2024 ------
15AREA CALCULATION OF ALL FLOORS (BLOCK-F)05-02-2024 ------
16AREA CALCULATION OF ALL FLOORS (BLOCK-H)05-02-2024 ------
17AREA CALCULATION OF ALL FLOORS (BLOCK-J & COMMUNITY BUILDING-2)05-02-2024 ------
18AREA CALCULATION OF ALL FLOORS (BLOCK-M)05-02-2024 ------
19AREA CALCULATION UPPER & LOWER BASEMENT05-02-2024 ------
20ASSURANCE FOR SEWERAGE05-02-2024 ------
21ASSURANCE FOR STORM WATER05-02-2024 ------
22ASSURANCE FOR WATER SUPPLY05-02-2024 ------
23ASSURANCE OF SUPPLY OF POWER LOAD05-02-2024 ------
24BANK UNDERTAKING05-02-2024 ------
25A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS05-02-2024 View Document
26CA CERTIFICATE FOR COST INCURRED UP TO THE DATE OF EXTEN. REG.05-02-2024 ------
27CA CERTIFICATE FOR FINANCIAL & INVENTORY DETAILS05-02-2024 ------
28NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT05-02-2024 View Document
29DEMARCATION PLAN05-02-2024 View Document
30ELEVATION-1 & 2 (BLOCK-E,G & L)05-02-2024 ------
31ELEVATION-1 & 2 (TOWER-A & C)05-02-2024 ------
32ELEVATION-1 & 2 (TOWER-B)05-02-2024 ------
33ELEVATION-1,2 & 4 (BLOCK-J)05-02-2024 ------
34ELEVATION-1,2, & 3 (BLOCK-M)05-02-2024 ------
35ELEVATION-1,2,3 & 4 (BLOCK-F)05-02-2024 ------
36ELEVATION-1,2,3 & 4 (BLOCK-H)05-02-2024 ------
37ELEVATION-1,2,4 (BLOCK-K)05-02-2024 ------
38ELEVATION-3 & 4 (TOWER-A & C)05-02-2024 ------
39ELEVATION-3 & 4 (TOWER-B)05-02-2024 ------
40SERVICE PLANS AND ESTIMATES APPROVAL05-02-2024 ------
41SECTION-XX & YY (BLOCK-K)05-02-2024 ------
42ELEVATION-3 & SECTION-XX, YY (BLOCK-J)05-02-2024 ------
43ELEVATION-4 & SECTION-XX, YY (BLOCK-M)05-02-2024 ------
44ELEVATION-A,B,C & SECTION-1-1 (EWS)05-02-2024 ------
45GROUND TO TERRACE & AREA CALCULATION OF ALL FLOORS (EWS)05-02-2024 ------
46GROUND TO TERRACE FLOOR PLAN (BLOCK-D)05-02-2024 ------
47ENVIRONMENT CLEARANCE05-02-2024 ------
48EXTERNAL FIRE LINE05-02-2024 ------
49FIRE SCHEME APPROVAL05-02-2024 ------
50FLUSHING WATER SUPPLY PLAN05-02-2024 ------
51FOREST NOC05-02-2024 ------
52GROUND TO 10TH & AREA CALCULATION (BLOCK-K)05-02-2024 ------
53GROUND TO 10TH FLOOR PLAN (BLOCK-E,G & L)05-02-2024 ------
54COPY OF LICENSE ALONG WITH SCHEDULE OF LAND05-02-2024 View Document
55ROADS AND PAVEMENT PLAN05-02-2024 ------
56SECTION-Y-Y (TOWER-B)05-02-2024 ------
57SECTION-Y-Y (TOWER-A & C)05-02-2024 ------
58GROUND TO 18TH FLOOR (A,B & C)05-02-2024 ------
59GROUND TO TERRACE FLOOR PLAN (BLOCK-F)05-02-2024 ------
60GROUND TO TERRACE FLOOR PLAN (BLOCK-H)05-02-2024 ------
61GROUND TO TERRACE FLOOR PLAN (BLOCK-J)05-02-2024 ------
62HUDA CONSTRUCTION WATER NOC05-02-2024 ------
63DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD05-02-2024 View Document
64WATER SUPPLY PLAN05-02-2024 ------
65IRRIGATION LINE05-02-2024 ------
66LC-IV & LC-IV (A)05-02-2024 ------
67LOI05-02-2024 ------
68GROUND TO TERRACE FLOOR PLAN (BLOCK-M)05-02-2024 ------
69SEWERAGE PLAN05-02-2024 ------
70SERVICE PLANS ESTIMATES05-02-2024 ------
71SCHEMATIC DIAGRAM (BLOCK-A,B & C)05-02-2024 ------
72SECTION-Z-Z (TOWER-A & C)05-02-2024 ------
73SCHEMATIC DIAGRAM (BLOCK-D,F,H,J,K & M)05-02-2024 ------
74SCHEMATIC DIAGRAM (BLOCK-E,G & L)05-02-2024 ------
75TOILET DETAIL OF ALL TOWER & BLOCKS05-02-2024 ------
76SECTION-XX (BLOCK-E,G & L)05-02-2024 ------
77SECTION-XX & YY (BLOCK-H)05-02-2024 ------
78SECTION-X-X (TOWER-B)05-02-2024 ------
79SECTION-YY (BLOCK-E,G & L)05-02-2024 ------
80SITE PLAN SOVEREIGN PARK (ST-01 )05-02-2024 ------
81SITE PLAN SOVEREIGN PARK (ST-02 )05-02-2024 ------
82SITE PLAN SOVEREIGN PARK (ST-03 )05-02-2024 ------
83SITE PLAN SOVEREIGN PARK (ST-04 )05-02-2024 ------
84SITE PLAN SOVEREIGN PARK (ST-05 )05-02-2024 ------
85UPPER BASEMENT (CEILING PLAN)05-02-2024 ------
86UPPER & LOWER BASEMENT PLAN05-02-2024 ------
87TERRACE & ROOF PLAN (BLOCK-K)05-02-2024 ------
88STORM WATER SCHEME05-02-2024 ------
89DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.24-05-2024 View Document