9650255664 (Number Shared by Promoter in Public)
abhishek.kanodia@landmarkgoc.com
http://landmarkgardencity.com
XXXX366G
U45100HR2020PTC091480
LANDMARK GARDENCITY
SECTOR 11, TOHANA
TOHANA
FATEHABAD
0000000000
9810026972 (Number Shared by Promoter in Public)
info@landmarkgardencity.com
RAJESH MALIK
0000000000
9810026972 (Number Shared by Promoter in Public)
rajesh.malik@landmarkgoc.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
21566
08-06-2023
150000
IDBI BANK LTD.
HRERA Panchkula
14.58958 (Acre)
2.0
2.0
14.58958 (Acre)
104 of 2023 Dated 08.05.2023
Yes
4262.15 Lakhs
1179.01 Lakhs
0 Lakhs
1998.20 Lakhs
1084.94 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
34085.224
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
8300
4
PAVEMENTS
4100
5
PARKS AND PLAYGROUNDS
5256.74
6
GREEN BELTS
647.238
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
128.33
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
450
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
134.999
13
COMMUNITY
5939.31
Total
59041.841
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
427.81
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
295.22
YET TO BE PREPARED
3
STORM WATER DRAINAGE
145.95
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
185
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
210.09
YET TO BE PREPARED
6
STREET LIGHTING
54.52
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
9.61
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
PARKING
0
YET TO BE PREPARED
16
STP
210.50
YET TO BE PREPARED
17
UNDERGROUND WATER TANK
84.5
YET TO BE PREPARED
18
RAIN WATER HARVESTING
30
YET TO BE PREPARED
19
ELECTRICAL SUB STATION
345
YET TO BE PREPARED
10-05-2023 (date)
10-05-2023 (date)
01-10-2023
07-05-2028
Plot Area(In Square Meter)
Number of plots in the project
61.423
3
61.545
42
62.166
18
99.739
6
115.892
16
133.650
18
140.878
11
143.918
26
147.653
21
149.850
99
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
14.76
Sewerage treatment & garbage disposal
0
10.50
Electricity Supply System
0
0
Storm Water Drainage
0
7.30
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
21.39
21.39
42.78
Water Supply System
44.28
44.28
44.28
44.28
Sewerage treatment & garbage disposal
31.51
31.51
31.51
31.51
Electricity Supply System
0
0
0
0
Storm Water Drainage
21.89
21.89
21.89
21.89
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
42.78
42.78
42.78
42.78
Water Supply System
44.28
44.28
14.76
0
Sewerage treatment & garbage disposal
31.51
31.51
10.50
0
Electricity Supply System
0
0
0
9.25
Storm Water Drainage
21.89
21.89
7.30
0
Parks and Playgrounds
0.96
0.96
0.96
0.96
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Underground Water Tank
8.45
Rain Water harvesting
3.00
Underground Tank
8.45
8.45
Rainwater harvesting
3.00
3.00
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
42.78
42.78
21.39
21.39
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
27.75
27.75
27.75
27.75
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
1.92
1.92
0.96
0.96
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Light
13.63
13.63
13.63
STP
21.05
21.05
21.05
21.05
Underground Tank
8.45
16.90
16.90
8.45
Rainwater harvesting
3.00
6.00
6.00
3.00
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
21.39
21.39
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
27.75
27.75
9.25
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STP
42.10
31.58
31.58
21.05
Electrical Sub Station
86.25
86.25
86.25
86.25
Underground Tank
8.45
Street Light
13.63
Rainwater harvesting
3.00
No
No
IDBI BANK LTD.
0171102000018434
IBKL0000171
110259013
000171
Anil Kumar
9210, DLF Phase 4, Gurugram
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE
ALREADY BEEN OBTAINED
08-05-2023
II. LAYOUT PLAN
ALREADY BEEN OBTAINED
10-05-2023
Yes
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
N.A.
2
WALL FINISHING DETAILS
N.A.
3
KITCHEN DETAILS
N.A.
4
BATHROOM FITTINGS
N.A.
5
WOOD WORK ETC
N.A.
6
DOORS AND WINDOS FRAMES
N.A.
7
GLASS WORK
N.A.
8
ELECTRIC FITTINGS
N.A.
9
CONDUCTING AND WIRING DETAILS
N.A.
10
CUPBOARD DETAILS
N.A.
11
WATER STORAGE
N.A.
12
LIFT DETAILS
N.A.
13
EXTERNAL GLAZINGS
N.A.
13.1
WINDOWS/GLAZINGS
N.A.
14
DOORS
N.A.
14.1
MAIN DOORS
N.A.
14.2
INTERNAL DOORS
N.A.
15
AIR CONDITIONING
N.A.
16
ELECTRICAL FITTINGS
N.A.
17
CNG PIPE LINE
N.A.
18
PROVISION OF WIFI AND BROADBAND FACILITY
N.A.
19
EXTERNAL FINISHING/COLOUR SCHEME
N.A.
20
INTERNAL FINISHING
N.A.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
N.A.
1 . 2
WALLS
N.A.
1 . 3
CEILING
N.A.
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
N.A.
2 . 2
WALLS
N.A.
2 . 3
CEILING
N.A.
2 . 4
MODULAR WARDROBES
N.A.
3 . MASTER TOILET
3 . 1
FLOOR
N.A.
3 . 2
WALLS
N.A.
3 . 3
CEILING
N.A.
3 . 4
COUNTERS
N.A.
3 . 5
SANITARY WARE/CP FITTINGS
N.A.
3 . 6
FITTING/FIXTURES
N.A.
4 . BED ROOMS
4 . 1
FLOOR
N.A.
4 . 2
WALLS
N.A.
4 . 3
CEILING
N.A.
4 . 4
WARDROBES
N.A.
5 . TOILET
5 . 1
FLOOR
N.A.
5 . 2
WALLS
N.A.
5 . 3
CEILING
N.A.
5 . 4
COUNTERS
N.A.
5 . 5
SANITARY WARE/CP FITTINGS
N.A.
5 . 6
FIXTURES
N.A.
6 . KITCHEN
6 . 1
FLOOR
N.A.
6 . 2
WALLS
N.A.
6 . 3
CEILING
N.A.
6 . 4
COUNTERS
N.A.
6 . 5
FIXTURES
N.A.
6 . 6
KITCHEN APPLIANCES
N.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
N.A.
7 . 2
WALLS & CEILING
N.A.
7 . 3
TOILET
N.A.
7 . 4
BALCONY
N.A.
8 . SIT-OUTS
8 . 1
FLOOR
N.A.
8 . 2
WALLS & CEILING
N.A.
8 . 3
RAILINGS
N.A.
8 . 4
FIXTURES
N.A.
Sr. No.
Document Description
Date of Document Upload
View Document
1
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.