3RD FLOOR, PLOT NO 35, UM HOUSE, TOWER-A, SECTOR-44, GURUGRAM, HARYANA 122002
01244956150
0124495615 (Number Shared by Promoter in Public)
parkland.estate@godrejproperties.com
U70102MH2010PLC210227
AAECG0366L
GODREJ PARKLAND ESTATE
SECTOR 41, KURUKSHETRA
THANESAR
KURUKSHETRA
01244956150
1244956150 (Number Shared by Promoter in Public)
parkland.estate@godrejproperties.com
ROHAN KHANKHOJE
01244956150
1244956150 (Number Shared by Promoter in Public)
parkland.estate@godrejproperties.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
1378
06-06-2023
1298254
AXIS BANK LIMITED
HRERA Panchkula
242673.60 (Sqr/mtrs)
1.5
1.5
242673.60 (Sqr/mtrs)
118 of 2023 dated 05.06.2023
Yes
45495 Lakhs
12487 Lakhs
0 Lakhs
10672 Lakhs
22786 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
128800
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
62035.31
4
PAVEMENTS
3265.02
5
PARKS AND PLAYGROUNDS
18240.50
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
1208.75
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
24273.55
12
ANY OTHER
0
13
COMMERCIAL
4850.47
Total
242673.6
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP/MUNICIPAL CORPORATION
No
WATER SUPPLY
HSVP/MUNICIPAL CORPORATION
No
ELECTRICITY
UHBVNL/DHBVNL
No
SEWAGE DISPOSAL
HSVP/MUNICIPAL CORPORATION
No
STORM WATER DRAINAGE
HSVP/MUNICIPAL CORPORATION
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
1288
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
602
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
305
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
1780
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
370
AS PER PROJECT REPORT
6
STREET LIGHTING
242
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
359
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
806
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
72
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
4848
AS PER PROJECT REPORT
05-06-2023 (date)
NA (date)
20-06-2023
30-09-2026
Plot Area(In Square Meter)
Number of plots in the project
150
5
149
12
148
8
145
92
139
12
139
11
137
40
137
16
135
17
134
14
133
16
129
68
127
153
124
42
121
38
121
24
121
5
120
48
117
6
117
13
115
28
114
33
114
92
113
14
112
10
108
15
106
17
104
35
100
62
99
39
94
56
94
26
1501.23
1
1775.17
1
1574.07
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Yes
No
AXIS BANK, SECTOR 30, GURUGRAM, HARYANA
923020026504216
UTIB0003622
110211230
003622
SUSHIL SHARMA, BHANU SHARMA
3rd FLOOR, UM HOUSE, PLOT NO 35, SECTOR -44, GURUGRAM, HARYANA
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE
ALREADY BEEN OBTAINED
05-06-2023
Yes
Yes
Agreement shall be executed between the Promoters and the Allottees
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT