9810773333 (Number Shared by Promoter in Public)
forteasiarealty2016@gmail.com
XXXX837A
U70200DL2011PTC224926
FORTEASIA SILICON VALLEY EXTENSION-II
VILLAGE- MAINA, SECTOR-22-D, ROHTAK, HARYANA
ROHTAK
ROHTAK
9649555541 (Number Shared by Promoter in Public)
forteasiarealty2016@gmail.com
SUDESH KUMAR
9649555541 (Number Shared by Promoter in Public)
sudeshkumar6478@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
4996
22-02-2023
135000
AXIS BANK
HRERA Panchkula
6.0625 (Acre)
2.0
2.0
6.0625 (Acre)
37 of 2023 dated 20.02.2023
Yes
1850.46 Lakhs
854.11 Lakhs
0 Lakhs
606.25 Lakhs
390.10 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.361
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1.3015
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.460
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.111
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.610
12
ANY OTHER
0
13
COMMERCIAL
0.170
14
AREA
0.049
Total
6.0625
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
EXISTING PROJECT CONNECTIVITY
No
WATER SUPPLY
CGWA
No
ELECTRICITY
UHBVN
No
SEWAGE DISPOSAL
HUDA
No
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
110
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
70
YET TO BE PREPARED
3
STORM WATER DRAINAGE
70
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
60
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
60
YET TO BE PREPARED
6
STREET LIGHTING
21
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
45
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MAINTENANCE
35
YET TO BE PREPARED
16
BOUNDARY WALL
100.25
YET TO BE PREPARED
17
EARTH FILLING
35
YET TO BE PREPARED
18
TOTAL
606.25
YET TO BE PREPARED
21-02-2023 (date)
NA (date)
01-03-2023
19-02-2028
Plot Area(In Square Meter)
Number of plots in the project
130.21
10
120
85
105
20
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
40.67
40.67
40.67
40.67
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
40.67
40.67
40.67
40.67
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
40.67
40.67
40.67
40.67
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
40.67
40.67
40.67
40.67
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
40.67
40.67
40.67
40.67
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
40.67
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.0
5.5
5.5
5.5
Water Supply System
1.5
3.5
3.5
3.5
Sewerage treatment & garbage disposal
1.95
2.95
2.95
2.95
Electricity Supply System
1.95
2.95
2.95
2.95
Storm Water Drainage
1.5
3.5
3.5
3.5
Parks and Playgrounds
2.075
2.15
2.15
2.15
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
EARTH FILLING
1.2
1.70
1.7
1.70
BOUNDARY WALL
3.85
4.85
4.85
4.85
STREET LIGHTING
1.0
1
1
1
MAINTENANCE
1.2
1.70
1.70
1.70
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5.5
5.5
5.5
5.5
Water Supply System
3.5
3.5
3.5
3.5
Sewerage treatment & garbage disposal
2.95
2.95
2.95
2.95
Electricity Supply System
2.95
2.95
2.95
2.95
Storm Water Drainage
3.5
3.5
3.5
3.5
Parks and Playgrounds
2.15
2.15
2.15
2.15
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
BOUNDARY WALL
4.85
4.85
4.85
4.85
MAINTENANCE
1.7
1.70
1.7
1.7
STREET LIGHTING
1
1
1
EARTH FILLING
1.2
1.70
1.7
1.2
STREET LIGHTING
1
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5.5
5.5
5.5
5.5
Water Supply System
3.5
3.5
3.5
3.5
Sewerage treatment & garbage disposal
2.95
2.95
2.95
2.95
Electricity Supply System
2.95
2.95
2.95
2.95
Storm Water Drainage
3.5
3.5
3.5
3.5
Parks and Playgrounds
2.15
2.15
2.15
2.15
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
BOUNDARY WALL
4.85
3.85
4.85
4.85
MAINTENANCE
1.7
1.2
1.70
1.7
STREET LIGHTING
1
1
1
1
EARTH FILLING
1.7
1.2
1.7
1.7
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5.5
5.5
5.5
5.5
Water Supply System
3.5
3.5
3.5
3.5
Sewerage treatment & garbage disposal
2.95
2.95
2.95
2.95
Electricity Supply System
2.95
2.95
2.95
2.95
Storm Water Drainage
3.5
3.5
3.5
3.5
Parks and Playgrounds
2.15
2.15
2.15
2.15
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
MAINTENANCE
1.7
1.7
1.7
1.7
STREET LIGHTING
1
1
1
1
EARTH FILLING
1.7
1.7
1.7
1.7
BOUNDARY WALL
4.85
4.85
4.85
4.85
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5.5
5.5
5.5
5.5
Water Supply System
3.5
3.5
3.5
3.5
Sewerage treatment & garbage disposal
2.95
2.95
2.95
2.95
Electricity Supply System
2.95
2.95
2.95
2.95
Storm Water Drainage
3.5
3.5
3.5
3.5
Parks and Playgrounds
2.15
2.15
2.15
2.15
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
STREET LIGHTING
1
1
1
1
EARTH FILLING
1.7
1.7
1.7
BOUNDARY WALL
4.85
4.85
4.85
4.85
MAINTENANCE
1.7
1.7
1.7
1.7
EARTH FILLLING
1.7
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
3.5
Water Supply System
2
Sewerage treatment & garbage disposal
2
Electricity Supply System
2
Storm Water Drainage
2
Parks and Playgrounds
2.075
Clubhouse/community centres
0
Shopping area
0
Other
0
Yes
No
AXIS BANK
923020000242114
UTIB0001148
110211085
001148
MR. SANDEEP MANGLA (H.NO. 210, SECTOR-46, FARIDABAD, HARYANA) AND MR. MANOJ GOYAL (E-3, NEW AASHIYANA APARTMENT, PLOT-10, SECTOR-21-D, FARIADABAD)
ATTACHED
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE
ALREADY BEEN OBTAINED
20-02-2023
II. LAYOUT PLAN
ALREADY BEEN OBTAINED
21-02-2023
Yes
Yes
ATTACHED
FORTEASIA MART AT SECTOR-26 AND 28, OMAXE CITY, ROHTAK ,HARYANA
1.098
0
45
0
45
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
60
0
60
Cost of the apartments
0
0
0
Cost of the infrastructure
60
0
60
Others costs
0
0
0
580.65 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2019
31-12-2019
FORTEASIA SILICON VALLEYAT VILLAGE SUNARI KHURD, SECTOR-22-D, ROHTAK, HARYANA
11.475
4
269
4
269
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
0
0
2021
Cost of the apartments
0
0
450
Cost of the infrastructure
0
0
829
Others costs
0
0
642
362.21 Lakhs
33.10 Lakhs
0 Lakhs
0 Lakhs
No
05-02-2023
05-02-2023
FORTEASIA PARK VIEW AT VILLAGE KHEDI SADH, TEHSIL- SAMPLA, DISTRICT- ROHTAK, HARYANA
6.925
0
122
0
5
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
625
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
692.50
0
0
Others costs
297.30
0
0
120.08 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
02-11-2027
02-11-2027
FORTEASIA SILICON VALLEY EXTENSION-I AT VILLAGE SUNARI KHURD & MAYNA, SECTOR-22-D, ROHTAK, HARYANA
8.5875
0
168
0
168
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1187.37
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
858.75
0
0
Others costs
328.62
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
28-12-2027
28-12-2027
FORTEASIA SILICON VALLEY EXTENSION-III AT VILLAGE - MAYNA, SECTOR-22D, ROHTAK, HARYANA
22.33125
0
358
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
3523.10
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
2233.10
0
0
Others costs
1350.00
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
28-12-2027
28-12-2027
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.