HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-330-2018
Submission Date : 19-11-2018 10:26:50 AM
Applicant Type : Company
Project Type: NEW




ALPHA CORP DEVELOPMENT PRIVATE LIMITED
GOLF VIEW CORPORATE TOWER - A, 6TH FLOOR, GOLF COURSE ROAD, SECTOR - 42, GURUGRAM, HARYANA - 122001
01244831111
8800256060 (Number Shared by Promoter in Public)
SACHIN.G@ALPHA-CORP.COM
http://www.alpha-corp.com
XXXX259Q
U45201PB2003PTC045680
 
 


 
 


 
 


 
 


 
 


 
 


 
 







YET TO BE DECIDED
VILLAGE KAILASH, SECTOR 28 & 28A,
KARNAL
KARNAL
9996789494 (Number Shared by Promoter in Public)
ARVIND.G@ALPHA-CORP.COM
ARVIND GUPTA
9996789494 (Number Shared by Promoter in Public)
ARVIND.G@ALPHA-CORP.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11907219-09-2018281000HDFC BANK LIMITEDHRERA Panchkula







14 (Acre)
PLOTTED DEVELOPMENT
0
14 (Acre)
23 OF 2018 DATED 18/04/2018
Yes







5954.19 Lakhs
2310.00 Lakhs
0 Lakhs
3504.19 Lakhs
140.00 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD24269.120
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS19119.358
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS5497.366
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION73.440
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY300.000
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES5394.500
12ANY OTHER1896.448
13OVER105.668
Total56655.9




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS240.75AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM244.95AS PER PROJECT REPORT
3STORM WATER DRAINAGE103.58AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL110.87AS PER PROJECT REPORT
6STREET LIGHTING53.71AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15MAINTENANCE CHARGES299.95AS PER PROJECT REPORT
16HORTICULTURE6.88AS PER PROJECT REPORT


NA (date)
NA (date)
01-02-2019
30-04-2023
Plot Area(In Square Meter)Number of plots in the project
122.3201
85.4161
104.00020
149.9201
127.0401
85.4161
101.28028
132.3201
109.7601
132.2587
84.42028
135.4505
104.4591
116.8008
149.7601
124.6401
116.8006
149.8401
111.9201
112.0004
149.2311
106.9601
107.4791
95.4441
87.60022
87.0391
65.3401
87.60036
87.2281
85.70224
122.0675
114.7418
122.0675
89.1803
100.5901
75.5491
104.00012
145.7601


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.824.824.824.82
Water Supply System4.904.904.904.90
Sewerage treatment & garbage disposal2.222.222.222.22
Electricity Supply System1.071.071.071.07
Storm Water Drainage2.072.072.072.07
Parks and Playgrounds0.140.140.140.14
Clubhouse/community centres0000
Shopping area0000
Other6.006.006.006.00

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.425.425.425.42
Water Supply System5.515.515.515.51
Sewerage treatment & garbage disposal2.492.492.492.49
Electricity Supply System1.211.211.211.21
Storm Water Drainage2.332.332.332.33
Parks and Playgrounds0.150.150.150.15
Clubhouse/community centres0000
Shopping area0000
Other6.756.756.756.75

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.214.214.21
Water Supply System4.294.294.29
Sewerage treatment & garbage disposal1.941.941.94
Electricity Supply System0.940.940.94
Storm Water Drainage1.811.811.81
Parks and Playgrounds0.120.120.12
Clubhouse/community centres000
Shopping area000
Other5.255.255.25

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.0412.0412.0412.04
Water Supply System12.2512.2512.2512.25
Sewerage treatment & garbage disposal5.545.545.545.54
Electricity Supply System2.692.692.692.69
Storm Water Drainage5.185.185.185.18
Parks and Playgrounds0.340.340.340.34
Clubhouse/community centres0000
Shopping area0000
Other15.0015.0015.0015.00

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements13.2413.2413.24
Water Supply System13.4713.4713.47
Sewerage treatment & garbage disposal6.106.106.10
Electricity Supply System2.952.952.95
Storm Water Drainage5.705.705.70
Parks and Playgrounds0.380.380.38
Clubhouse/community centres000
Shopping area000
Other16.5016.5016.50

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements14.4514.4514.4514.45
Water Supply System14.7014.7014.7014.70
Sewerage treatment & garbage disposal6.656.656.656.65
Electricity Supply System3.223.223.223.22
Storm Water Drainage6.216.216.216.21
Parks and Playgrounds0.410.410.410.41
Clubhouse/community centres0000
Shopping area0000
Other18.0018.0018.0018.00

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.026.026.026.02
Water Supply System6.126.126.126.12
Sewerage treatment & garbage disposal2.772.772.772.77
Electricity Supply System1.341.341.341.34
Storm Water Drainage2.592.592.592.59
Parks and Playgrounds0.170.170.170.17
Clubhouse/community centres0000
Shopping area0000
Other7.507.507.507.50












Yes
No
YES BANK LIMITED, GURUGRAM
010572500000030
YESB0000105
110532022
0105
SANTOSH AGARWAL A-407, VASUNDHARA APARTMENT, PLOT NO 16, SECTOR - 6, DWARKA, NEW DELHI
YES











Yes
Yes
Yes
No
Yes
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. FOREST NOCALREADY BEEN OBTAINED28-02-2018
II. APPROVAL OF MORTGAGE LANDALREADY BEEN OBTAINED20-03-2018
III. POWER LOAD ASSURANCEAPPLIED FOR BUT YET TO RECEIVE02-03-2018








Yes


Yes


ATTACHED













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN15-11-2018 View Document
2DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD15-11-2018 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN15-11-2018 View Document
4DEMARCATION PLAN15-11-2018 View Document
5ZONING PLAN15-11-2018 View Document
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT15-11-2018 View Document
7NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT15-11-2018 View Document
8IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN15-11-2018 View Document
9A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS15-11-2018 View Document
10COPY OF LICENSE ALONG WITH SCHEDULE OF LAND16-11-2018 View Document
11CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT19-11-2018 View Document